Pfeifer v. Reiman

161 A. 825, 10 N.J. Misc. 898, 1932 N.J. Ch. LEXIS 90
CourtNew Jersey Court of Chancery
DecidedJuly 8, 1932
StatusPublished
Cited by3 cases

This text of 161 A. 825 (Pfeifer v. Reiman) is published on Counsel Stack Legal Research, covering New Jersey Court of Chancery primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pfeifer v. Reiman, 161 A. 825, 10 N.J. Misc. 898, 1932 N.J. Ch. LEXIS 90 (N.J. Ct. App. 1932).

Opinion

Berry, Y. C.

This is an interpleader suit. The complainants allege that on September 12th, 1930, a written contract was entered into by one Adolph Kulzer with Bobert A. Beiman, under which Beiman agreed to erect a dwelling house in Maplewood, New Jersey, for Kulzer, at a cost of $19,500. Before any work was done or materials furnished the contract was filed in [900]*900the office of the clerk of Essex county. At the time the contract was executed, and at all times thereafter, the complainants were the record owners of the land upon which the building was erected, and Kulzer was actually the agent of the complainants in executing the contract, although it was not so stated therein, nor was there any record or other notice of these facts to the defendants until after default by the contractor. Eeiman abandoned his contract shortly before its completion leaving unfinished work estimated to cost $610. After deducting this $610 from the money in their hands the complainants had a balance of $4,665.51 for which they admit liability to the contractor, or to persons who furnished labor and material.

Most of the materialmen filed stop notices under section 3 of the Mechanics5 Lien act, some of the notices being directed to the owners and some to Kulzer. In addition, claims were served upon the owners by persons to whom the contractor had given orders and by one materialman who held an assignment.

The total of these claims by the stop notice claimants and assignees was in excess of the funds in the hands of the owners, hence this bill.

On April 9th, 1931, the bill of complaint was adjudged as confessed against all of the defendants, and an interlocutory decree entered.

The taxed costs allowed to the complainants were $192.98, leaving a balance of $4,472.53, which is now on deposit in this court for distribution among the various claimants.

When the case came on for final hearing the parties entered into a written stipulation of facts in which it was agreed that the building contract referred to, with specifications attached, and was filed in the office of the clerk of Essex county on September 15th, 1930, which was before any work was done in the erection of the building; that the contract was between Adolph Kulzer and Eobert A. Eeiman; that Kulzer was referred to throughout the contract as the owner; that there is nothing in the contract to show that he was acting as the agent for the Pfeifers and that the Pfeifers [901]*901were the owners of record on the date of the execution of the contract, which was September 12th, 1930.

The facts concerning the stop notices and assignees as shown in the stipulation are as follows:

STOP NOTICE CLAIMANTS

Name Date of Filing Directed to Amount
Passa'ie-Bergen Lumber Co. January 17, 1931 Adolph Kulzer $991.81
Watchung Garden Nurseries, Inc. January 21, 1931 Adolph Kulzer 256.00
Andrew Isenberg January 24, 1931 Adolph Kulzer 1.175.00
Birkenmeier & Kuhn Co. February 5, 1931 Adolph Kulzer 283.50
Grover C. Porch February 6, 1931 Adolph Kulzer 1.700.00
Louis Wesson February 7, 1931 Adolph Kulzer 282.00
Birkenmeier & Kuhn Co., Inc. February 7, 1931 Edwin F. Pfeifer and Helen P. Pfeifer This is a duplicate 283.50
W. A. Thornley Co. February 9, 1931 Edwin F. Pfeifer and Helen P. Pfeifer 1,389.11
F. Storsberg February 10, 1931 Adolph Kulzer 500.00
Adolph K. Artke February 10, 1931 Edwin F. Pfeifer and Helen P. Pfeifer 230.00
Thomas Roofing Co. February 10, 1931 Adolph Kulzer former owner—Edwin F. Pfeifer present owner 540.00
Geo. P. Heuser, trading as Irvington Hardware Co. February 11, 1931 Edwin F. Pfeifer, Helen P. Pfeifer, Adolph Kulzer and Robert Reiman 39.75
Frederick Schill & Co. February 19, 1931 Adolph Kulzer 1,152.25
Bing & Fink February 19, 1931 Edwin F. Pfeifer and Helen P. Pfeifer or Adolph Kulzer 185.00
Theodore August February 24, 1931 Edwin F. Pfeifer and Helen P. Pfeifer, Adolph Kulzer and Robert Reiman 182.00
Frederick Schill & Co. March 9, 1931 Edwin F. Pfeifer and Helen P. Pfeifer This is a duplicate 1,152.25

[902]*902ASSIGNMENTS AND ORDERS

Name Date Amount
Grover C. Porch (assignee) January 24, 1931 $1,700.00
Andrew Isenberg January 27, 1931 1,175.00
Adolph K. Artke January 27, 1931 530.00
Theodore August January 27, 1931 212.00
Reese Metal Weatherstrip Co. (duplicate of Bing & Fink) February 10, 1931 185.00
Russell C. Gavett January 30, 1931 213.45
E. Storsberg Co. February 2, 1931 500.00
(This last order is not mentioned an exhibit.) in the stipulation but appears. as

The exhibits also show that there was one other order '•given, but not - mentioned in the stipulation, to Abraham ..Schottenfeld fot $122, dated January 20th, 1931. There was no statement of claim filed by this defendant, and it may be assumed that it was either paid or abandoned.

The stipulation and the exhibits disclose that the defendant, W. A. Thornley Company, Incorporated, obtained a judgment against the owners specially and against Reiman generally in a mechanics’ lien suit. The claim was filed on or about May 25th, 1931, and the suit started on the same day. Judgment was entered on September 30th, 1931, in the sum of $1,520.90.

It is apparent, therefore, that there are four groups of claimants to this fund, viz.:

1. The mechanics’ lien creditor whose judgment is for $1,520.90.

2. The holders of the assignment and orders whose claims total $4,015.25.

3. Stop notice claimants who directed their notices to the Pfeifers as owners.

4. Stop notice claimants who directed their notices to Kulzer as owner.

The mechanics’ lien claimant, the assignee and the holders of the orders, excepting Gavett, filed stop notices. The total of all claims is $9,082.46.

W. A. Thornley Company, Incorporated, and the holders of the assignment and the orders contend that the only [903]*903remedy in this ease was by lien claim, and that the filing of stop notices was ineffective for the reason that the building contract was not signed by the owner of record as required by section 2 of the Mechanics’ Lien act as amended in 1930.

Prior to the amendment the wording of section 2 of the statute was as follows: “Whenever any building shall be erected in whole or in part by contract, in writing, such building and the land whereon it stands shall be liable to the contractor alone for work done or materials furnished in pursuance of such contract, &c.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chesebro-Whitman Co., Inc. v. EDENBORO APTS.
207 A.2d 186 (New Jersey Superior Court App Division, 1965)
Suburban Lumber Co. v. Gerber
85 A.2d 275 (New Jersey Superior Court App Division, 1951)
Tipula v. Garfield Mill, Inc.
170 A. 228 (New Jersey Court of Chancery, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
161 A. 825, 10 N.J. Misc. 898, 1932 N.J. Ch. LEXIS 90, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pfeifer-v-reiman-njch-1932.