Peyton Creek Irr. Dist. v. White

230 S.W. 1060
CourtCourt of Appeals of Texas
DecidedMay 5, 1921
DocketNo. 7988
StatusPublished
Cited by6 cases

This text of 230 S.W. 1060 (Peyton Creek Irr. Dist. v. White) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peyton Creek Irr. Dist. v. White, 230 S.W. 1060 (Tex. Ct. App. 1921).

Opinion

GRAVES, J.

White sued the Peyton Creek Irrigation District of Matagorda county, Tex., a body corporate existing under and by virtue of title 73, chapter 2, of our Revised Statutes, to recover the sums of $1,824.50 and $1,040.80, respectively, for certain work alleged to have been done by him for it on Lake Austin Dam in Matagorda county, claiming the first amount as the balance unpaid under a written contract between them calling for a total of $6,960, and the second [1062]*1062for extras pursuant to a yerbal agreement. He averred completion of tbe work, its acceptance by tbe district, and compliance on bis part witb tbe terms of botb contracts.

Tbe district answered witb demurrers and denials, general and special, by means of wbicb, in different ways, it was asserted that, not only bad plaintiff failed to complete tbe work in a workmanlike manner and witbin a reasonable time, as be bad. obligated himself to do, but that be bad never completed it at all, and tbe district bad never accepted it. Tbe defendant further answered witb a cross-action against tbe plaintiff and Sutherland and Le Tulle, tbe sureties on bis contractor’s bond, by wbicb it sought to get back $5,075.50 it bad paid White on tbe written contract for tbe work, and also to recover various items of damage it claimed to have sustained by reason of bis negligent and willful failure to reconstruct tbe dam as contracted.

Tbe court sustained exceptions to tbe plaintiff’s claim for tbe $1,040.80 for additional work under tbe verbal agreement, and to all of tbe defendant’s cross-action except so much as sought a recovery of tbe $5,075.50 paid on tbe written contract.

Tbe cause was then submitted to a jury upon these two special issues:

“Question No. 1: Did the plaintiff, John W. White, construct the dam described in plaintiff’s petition substantially in accordance witb the plans and specifications attached to and made a part of said contract offered in evidence ?
“Question No. 2: Did the plaintiff, John W. White, construct the dam described in plaintiff’s petition and fully complete the same within a reasonable time from March 27, 1916, the date of said contract?
“In considering your answer to question No. 2, you will take into consideration all of the evidence introduced in the case, and all the circumstances and conditions incident to the construction of the dam as detailed by the evidence.”

Affirmative answers to botb questions were returned, 'whereupon judgment that tbe irrigation district take nothing on its cross-action against White or bis bondsmen, and that be recover against it tbe $1,824.50 sued for, witb interest, followed. From that decree below this appeal on tbe part of tbe defendant there proceeds.

[1] Appellant’s first contention is that the court erred in overruling its general demurrer to tbe petition of appellee White. Tbe ground for this position is that tbe petition did not specifically allege performance of tbe detailed procedure prescribed by sections 21, 85 to 87, inclusive, 89 and 92 of Vernon’s Ann. Civ. Supp. 1918 Statutes, article 5197, for tbe procurement of a contract of the character declared upon.

We do not think tbe objection well taken, but consider tbe petition good as against such a demurrer. In general terms it charged tbe organization, existence, and functioning of tbe appellant under tbe statute; the making and delivery of tbe written contract for the work by it through its then board of directors under attestation by its secretary, and attachment of its corporate seal; the construction and completion of tbe work under tbe direction and supervision of tbe directors by tbe appellee in a workmanlike manner, according to tbe plans and specifications attached to such written instrument, and final acceptance of tbe completed job by tbe district acting by and through these directors after tbe.appellee bad also made some minor changes required by tbe organization’s consulting engineer; part payment to tbe extent of $5,075.50 on tbe contract price of $6,900, and refusal after due demand to pay tbe balance of $1,824.50 was also set up. A count was added, declaring upon tbe above-mentioned and subsequent verbal agreement to pay $1,040.80 more for extras occasioned by tbe development of a leak in tbe dam after tbe alleged completion of tbe work called for in tbe written contract. This was cut out under special exception, and, as no complaint against tbe action is presented here by the appellee, it becomes immaterial.

Tbe written contract as so declared upon was prima facie a valid and binding obligation against appellant, to say nothing of tbe effect of its alleged action thereunder. If any facts rendering it otherwise existed, they were matter of defense that should have been pleaded and proved. Tbe assignment is overruled.

[2] It is next said tbe court should have sustained defendant’s special exceptions Nos. 1 and 2, pointing out that tbe written contract declared upon by plaintiff was not set out verbatim in his pleadings, nor was it averred that tbe law regulating such a contract bad been complied with. There is no merit in this suggestion; we do not understand that such particularity was required.

[3] A further objection, under defendant’s special exception No. 3, was that tbe contract showed the authority of E. B. Wells to be limited to estimating tbe work and labor performed and tbe materials furnished, and did not confer on him the right to accept the work, wbicb was a nondelegable duty imposed by tbe statute upon tbe directors.

We do not understand paragraph 3 of tbe pleading, to which this exception was directed, to charge that É. B. Wells alone for tbe district accepted tbe work, because its concluding recitation is, “and that tbe said irrigation district acting by and through its directors, accepted tbe said work”; but if that be its import, and if it could further be said to have been error to overrule tbe exception, it became a wholly immaterial one, in view of tbe other parts of tbe pleading, wbicb did clearly charge acceptance of tbe work by tbe district and its board of directors.

[1063]*1063[4] Assignments Nos. 7 to 18, inclusive, complain of the court’s action in sustaining a number of special exceptions interposed by one or another of the opposing litigants to the defendant’s cross-action, hereinbefore referred to. As stated, it sought by way of counterclaim to recover in behalf of the irrigation district certain damages alleged to have resulted to it from the willful and negligent failure of White to complete the wort according to the contract between them, such as the loss of $8,000, occurring by reason of its consequent inability to impound and store sufficient water for the raising of a full crop of rice along its canals and laterals, its being compelled to purchase water for the irrigation of 890 acres of such contiguous lands at a cost of $7S0, curtailment of $5,000 in its revenues because of its being left unable to undertake the watering of more than 500 acres of land when 1,000 acres were available to it with sufficient water, and a large number of other and similar items, aggregating altogether a considerable sum of money.

Under the statute involved, article 5107, vol. 2, Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burges v. Commissioner
17 B.T.A. 275 (Board of Tax Appeals, 1929)
Jones v. Commissioner
16 B.T.A. 1208 (Board of Tax Appeals, 1929)
Strickland v. Commissioner
16 B.T.A. 419 (Board of Tax Appeals, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
230 S.W. 1060, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peyton-creek-irr-dist-v-white-texapp-1921.