Pettee v. Tenn. Manufacturing Co.

33 Tenn. 381
Tennessee Supreme Court·Decided December 15, 1853·Published

Opinion

E. B. Fogg, Special J.,

delivered the opinion of the court.

This is an action of assumpsit brought by Otis Pettee against the Tennessee Manufacturing Company,' for a balance claimed to be due him for certain machinery furnished them for their cotton and woollen mills in Lebanon. There are three counts in the declaration, one on a special contract in writing, made the 8th day of September, 1847, whereby the plaintiff agreed to furnish the defendants with certain articles of machinery specified in the agreement, to be delivered, one-third on or [383]*383before the first day of February, one-third on or before the first of March, and the remainder on or before the first of April, 1848, and when delivered the defendants were to pay the prices stipulated in the agreement, in a check at five days’ sight drawn on Philadelphia, on receiving notice of the shipment of the same from Boston. In this count of the declaration, it is averred that the machinery was delivered according to contract, and that the value thereof was thirty-seven thousand, one hundred and sixty-six dollars and forty-five cents, of which only twenty-eight thousand' five hundred dollars had been paid to him, leaving a balance due him of eight thousand six hundred and sixty-six dollars and forty-five cents, which the defendants refused to pay.

The second count is for machinery sold and delivered, and for materials, work, and labor, &c., according to the account annexed, in which a balance was claimed by plaintiff on the eighteenth of May, 1850, of nine thousand one hundred and forty-three dollars and ten cents. The third count was for money paid, laid out, and expended.

The pleas were non-assumpsit and payment, with leave to give any special matter in evidence. At January Term, 1853, the jury found a verdict in favor of the plaintiff, for eight thousand dollars.

The machinery was not delivered according to contract, but appears to have been delivered from the 26th of May, 1848, to the 14th of May, 1849, and was received by defendants in parcels, and payments were made by them at different periods from 31st of May, 1848, to April 25th, 1849, amounting in the whole to twenty-eight thousand five hundred dollars.

[384]*384There was proof tending to show that if the machinery had been delivered agreeably to the special contract, that the mills would have commenced operations in the spring of 1848, and that the profits of the mill might probably have been to a large amount, and that the capital stock was called in from the stockholders U2Don the faith of the compliance with the contract by the plaintiff, much sooner than it otherwise would have been, and that large sums were lost in the interest on their capital invested. It was also proved that expenses to the amount of upwards of five hundred dollars, had been incurred by the company in sending a special messenger to Massachusetts, where the plaintiff resided, and where the machinery was made, for the purpose of hastening the plaintiff in the delivery of the machinery. It appears, however, unnecessary to state the proof, as the cause has been argued in this court upon exceptions taken to a portion of the charge of the honorable circuit judge to the jury, and a refusal to grant a new trial for the error in the charge.

The court below charged the jury, that the plaintiff could not recover ou the first count, in the declaration, upon the special contract, because it was conceded that the machinery had not been delivered according to the terms of his contract. That upon the other counts in the declaration, he could recover the reasonable value of the machinery or benefit conferred, as the same had been received and enjoyed by the defendants. To this part of the charge all objections were waived.

The court also instructed the jury as follows: “ It is insisted strenuously for the defendants, that upon the whole case they have a right to recoup (as the phrase [385]*385is) tbe plaintiffs recovery to tbe extent they sustained damage by reason- of tbe failure of tbe plaintiff to comply witb bis contract, and they insist first, that they can abate tbe recovery so much as they could bave made by running tbe ■ factory during tbe time they alleged they were delayed by the failure to ship tbe machinery; and secondly, at all events, to tbe extent of tbe capital paid in and drawing interest. But tbe court is of opinion that to enable tbe defendant to maintain bis position, tbe claims for recoupment ought to be such that tbe defendants could maintain a cross action for it against tbe plaintiff. Such cross action will not lie for “ delay in business ” or for speculative profits. Tbe consequence is that in tbe opinion of tbe court, tbe claim for recoupment of damages insisted on, falls within .the principle announced, and which having been so held by tbe supreme court, this court feels bound to declare as tbe law, and to bold as furnishing no such defense as is made. If,- therefore, tbe proof shows that tbe plaintiff failed to fulfill tbe special contract, if such failure caused a delay in business or delay in starting tbe operations of the factory, and if tbe profits they might bave made by running it, were speculative and not capable of being arrived at or computed witb reasonable certainty and precision, then tbe claim for recoupment or reduction of the recovery of tbe plaintiff cannot apply to that case.”

To this part of tbe charge, tbe defendants excepted.

It is settled as tbe law of this State, by tbe case of Porter vs. Woods, Stacker & Co., 3 Humph. 56, that after tbe abandonment of a special agreement, compensation for partial performance may be recovered, equal to and limited by tbe value and extent of the benefit- conferred [386]*386Therefore, the defendant is entitled to abate the recovery of the plaintiff by the damages he has sustained on account of the non-performance of the plaintiff’s portion of the agreement. The plaintiff being entitled to recover for valuable materials furnished or beneficial services rendered, and only to the extent of the benefit conferred on the defendants, the latter must be entitled in abatement, and in ascertaining the extent of such benefit, to such damages as in a cross action he ought to recover for the non-performance by the other of his portion of the agreement.

In 5 Humph., 586, Crouch vs. Miller, it is decided that recoupment of damages is allowed the defendant in cases where the plaintiff, who -has only partially performed his portion of the contract, comes into court asking compensation for such partial performance.

In 8 Humph., 678, Fanning vs. Vanhook, it is said by the court that the doctrine of recoupment is applicable to cases where there has been a special contract, which has been partially executed, but not according to its terms; then the defendant is liable to the plaintiff, not upon the special contract which he has failed to execute, but upon an indebitatus assumpsit for so much as the defendant may be found ex eguo et bono, to pay for the partially or defectively executed contract, and in such case, in order to ascertain what the defendant does, ex eguo et bono really owe, he shall be allowed by way of recoupment, such damages as he has sustained by reason of the non-performance of the contract as it was entered into by the plaintiff, and which he could recover by a cross ' action.

[387]

Free access — add to your briefcase to read the full text and ask questions with AI

Pettee v. Tenn. Manufacturing Co., 33 Tenn. 381 (Tenn. 1853).

33 Tenn. 381 (Pettee v. Tenn. Manufacturing Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.