PetSmart, Inc. v. Dancor Construction, Inc.

CourtDistrict Court, N.D. Oklahoma
DecidedJanuary 31, 2020
Docket4:17-cv-00361
StatusUnknown

This text of PetSmart, Inc. v. Dancor Construction, Inc. (PetSmart, Inc. v. Dancor Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PetSmart, Inc. v. Dancor Construction, Inc., (N.D. Okla. 2020).

Opinion

UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF OKLAHOMA PETSMART, INC., ) ) Plaintiff, ) ) v. ) Case No. 17-CV-0361-CVE-JFJ ) DANCOR CONSTRUCTION, INC. and ) DANIEL J. POLICICCHIO, SR., ) ) Defendants. ) OPINION AND ORDER On October 22, 2018, the Court entered an opinion and order (Dkt. # 117) finding that default judgment should be entered against defendant Daniel J. Policicchio, Sr. and that plaintiff Petsmart, Inc’s (Petsmart) motion for summary judgment against defendant Dancor Construction, Inc. (Dancor) should be granted. The Court determined that the parties should be given an opportunity to submit additional briefing and evidence on the issue of damages. The parties have submitted opening and response briefs on the issue of damages, and the issue is fully briefed. Plaintiff asks the Court to award it compensatory damages in the amount of $800,754 on its fraud and breach of contract claims against Policicchio. Dkt. # 131. Plaintiff seeks the same amount of damages on its fraud claim against Dancor, plus an additional sum of liquidated damages due to Dancor’s failure to finish its work on time. Dkt. # 132. Plaintiff seeks punitive damages from Policicchio and Dancor for twice the amount of the actual damages. Defendants respond that the damages sought by plaintiff are excessive, and the maximum amount of damages that should award to plaintiff under a benefit of the bargain theory is $65,135. Dkt. ## 130, 138. Petsmart filed this case alleging breach of contract and contractual indemnification claims against Dancor. Dkt. # 2. Petsmart alleged that it entered a contract with Dancor for the construction of a new store in Tulsa, Oklahoma and that it agreed to pay Dancor $1,269,397 to build the store. Id. at 2. Petsmart made periodic payments to Dancor, and Dancor was to use this money

to pay subcontractors as the work progressed. Id. However, Dancor failed to pay many of the subcontractors, and subcontractors filed liens on the property in amounts in excess of $490,000. Petsmart sought damages caused by Dancor’s delay in completing the work and for expenses incurred to have liens released or defend against claims by subcontractors. Id. at 4-6. Petsmart filed an amended complaint (Dkt. # 39) adding Dancor’s president, Policicchio, as a party, and adding fraud claims against Dancor and Policicchio. Defendants largely failed to defend against plaintiff’s claims and numerous discovery

disputes arose; defendants were sanctioned for their failure to participate in discovery. Dkt. # 92. Plaintiff filed a motion for default judgment against Policicchio and sought compensatory damages in the amount of $928,814.01. This amount was determined by subtracting the amount that could be verified that Dancor paid to subcontractors ($257,782.25) from the amount that Plaintiff paid to Dancor for the purpose of paying subcontractors ($1,186,596.26). Dkt. # 103, at 3. Plaintiff filed a motion for summary judgment (Dkt. # 107) against Dancor as to liability, and Dancor failed to file a response to the motion. The Court entered an opinion and order (Dkt. # 117) granting the motion for default judgment against Policicchio and the motion for summary judgment against Dancor.

However, the Court did not have sufficient evidence or argument on the issue of damages, and the parties were directed to file additional briefing as to plaintiff’s damages.

2 The parties are generally in agreement that plaintiff’s damages should be determined under a benefit of the bargain theory, but they vastly differ as to how this theory should be applied. Plaintiff argues that damages for fraud and breach of contract should be calculated by subtracting the amount that defendants actually paid subcontractors ($389,626) from the amount that defendants

represented that they had paid subcontractors ($969,680). Dkt. # 131, at 1-2; Dkt. # 132, at 1-2. This results in a difference of $584,054. Plaintiff also seeks to recover damages for attorney fees that it incurred in having liens released and defending against claims brought by subcontractors due to defendant’s failure to pay subcontractors who performed work at the new Petsmart store. Petsmart has provided a declaration by its attorney, Robert Alexander, Jr., that Petsmart paid $220,700 for attorney fees in state court litigation to have liens released from its property. Policicchio responds that the benefit of the bargain is a completed store, and the damages are the same whether Court is

considering plaintiff’s breach of contract or fraud claims. Dkt. # 138, at 3. He claims that the completed store cost plaintiff $1,383,576.15 and plaintiff should have paid $1,318,440.29 to Dancor for its work, and this results in damages in the amount of $65,135.86.1 Id. Policicchio also argues that plaintiff has failed to show that the attorney fees sought by plaintiff are reasonable in the terms of the work performed and the rate charged by counsel. Id. at 6-10. The Court must determine the damages for plaintiff’s breach of contract and fraud claims using the benefit of the bargain doctrine. Under the “benefit of the bargain” doctrine, a plaintiff

1 Policicchio states that the initial contract price of $1,269,397 should be increased to $1,318,440.29 due to change orders allegedly submitted by Dancor. Dkt. # 130, at 2-3. The Court has reviewed the evidence and the statements for payment submitted by defendants show that the parties adjusted the final payment to $1,318,440.29. Dkt. # 131-6, at 3. The Court will rely on this figure as the final amount owed to Dancor if it had completed the contract under the terms agreed to by the parties. 3 alleging fraud is entitled to recover the difference between “the actual value received and the value the defrauded party would have received had the value been as represented.” Bowman v Presley, 212 P.3d 1210, 1218 (Okla. 2009). The same analysis applies when determining contractual damages under the benefit of the bargain doctrine. Smoot v. B & J Restoration Servs. Inc., 279 P.3d

805, 822 (Okla. Civ. App. 2012). The starting point for this analysis is determine what bargain the parties made, and then the Court will determine what amount plaintiff actually paid to obtain the benefit of the bargain. Plaintiff argues that the contract obligated Dancor to pay subcontractors $969,680, but Dancor paid its subcontractors only $389,626. However, plaintiff and Dancor entered a contract for the construction of a Petsmart store, and the payment of subcontractors was simply part of the performance of the contract. The Court finds that the bargain for the purpose of determining plaintiff’s damages was the construction of the store, and the parties agreed that Dancor would build

a store for $1,269,397. The evidence submitted by plaintiff shows that there were adjustments to the contract, and the final value of the contract was $1,318.440.29. Dkt. # 132-6, at 3. Plaintiff is entitled to damages it incurred to complete construction of the store for any amounts above the adjusted contract price of $1,318,440.29. In a prior opinion and order, the Court found that any undisputed facts stated in plaintiff’s motion for summary judgment were deemed confessed, and one of those confessed facts was that plaintiff paid $1,186,596.26 to Dancor as construction progressed. Dkt. # 107, at 3. Plaintiff also stated as an undisputed fact that it paid an additional $196,979.89 to discharge liens filed against plaintiff’s property by unpaid subcontractors. Id. at 4. This results in

a total payment of $1,383,576.15 by plaintiff to complete construction of the Petsmart store, and this results in damages in the amount of $65,135.86.

4 Plaintiff seeks an award of damages for attorney fees and costs that it incurred to defend against litigation filed by subcontractors to recover sums that were not paid by Dancor and Policicchio pursuant to subcontracts. Dkt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Griffin v. Bredouw
1966 OK 226 (Supreme Court of Oklahoma, 1966)
Sun Ridge Investors, Ltd. v. Parker
1998 OK 22 (Supreme Court of Oklahoma, 1998)
Barnes v. Oklahoma Farm Bureau Mutual Insurance Co.
2000 OK 55 (Supreme Court of Oklahoma, 2001)
Bowman v. Presley
2009 OK 48 (Supreme Court of Oklahoma, 2009)
Smoot v. B & J Restoration Services, Inc.
2012 OK CIV APP 58 (Court of Civil Appeals of Oklahoma, 2012)
Hetronic International, Inc. v. Rempe
697 F. App'x 589 (Tenth Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
PetSmart, Inc. v. Dancor Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/petsmart-inc-v-dancor-construction-inc-oknd-2020.