Petrucci Constr. v. Strafach Sons, No. Cv 87 23 86 75 (Jan. 30, 1991)

1991 Conn. Super. Ct. 598
CourtConnecticut Superior Court
DecidedJanuary 30, 1991
DocketNo. CV 87 23 86 75
StatusUnpublished

This text of 1991 Conn. Super. Ct. 598 (Petrucci Constr. v. Strafach Sons, No. Cv 87 23 86 75 (Jan. 30, 1991)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petrucci Constr. v. Strafach Sons, No. Cv 87 23 86 75 (Jan. 30, 1991), 1991 Conn. Super. Ct. 598 (Colo. Ct. App. 1991).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION This litigation originates by virtue of a complaint, formulated in two counts.

The first count, alleging a breach of contract on the part of the defendant in essence asserts that the named parties herein entered into a contract, on or about August 14, 1985 to furnish materials and labor for the plaintiff.

The plaintiff, a general contractor, hired the defendant, as one of many sub-contractors, to do certain concrete work for the west expansion parking structure at the Trumbull Shopping Park in Trumbull, Connecticut. This defendant sub-contracted to do some, but not all of the concrete work for this project.

The dollar value of the contract between the plaintiff and the defendant, approximated more than one million dollars, including four change orders which added to that base contract price.

The over-all contract value between the plaintiff, general contractor and the owner of the shopping mall, where CT Page 599 the added construction was to be performed was in the area of three million dollars. Admittedly, the portion of the work contracted for between the parties hereto was an important part of the project.

It is further asserted that the plaintiff fulfilled all the provisions of the agreement on its part, including payments to the defendant in the undisputed amount of $959,259.00.

The plaintiff claims that the defendant's work on the concrete was unskillful and negligent and accordingly is in breach of its contract with the plaintiff.

It is further alleged that the defendant was dismissed from the plaintiff's employ after refusing to comply with the plaintiff's instructions to perform in compliance with the contractual terms.

As a result of the defendant's failure to do the work as required, the plaintiff asserts that it was compelled to finish the work and supply necessary materials at its own expense. It is claimed that this cost substantially exceeds any claimed moneys due to the defendant.

It is to recover this excess money, or excess cost for which the plaintiff has instituted this action.

The second count of the complaint is essentially a re-assertion of the allegations of the first count, except that it sounds in negligence. The plaintiff claims herein that the defendant breached its duties in the performance of its contractual obligations, thereby imposing upon the plaintiff the burden of completing what was the defendant's job in the first instance, again at a cost in excess of any moneys owed by the plaintiff to the defendant.

In essence, the answer of the defendant denies the essential allegations of the complaint and has appended thereto two special defenses: the first asserts that the plaintiff by its own negligence, caused any damage to itself because it directed, accepted and participated in the work being done; and the second special defense is a restatement of the first special defense, except that it declares that the plaintiff waived any rights to maintain this action, and for the same reasons above-stated.

In addition to the responsive pleadings by the defendant, it has filed a counterclaim of five counts. In a concise compilation of the allegations of the first count it is asserted that a balance of $77,041.00 is due the defendant on CT Page 600 an over-all contractual valuation of $1,036,300.00; count two essentially re-states the allegations of count one; count three asserts that a mechanics' lien was placed on the subject property, dated September 1, 1986 for the sum of $77,041.00 which was later released for a substituted bond in the same amount; count four asserts that the parties entered into a contract to perform work and provide materials on a separate project from that indicated above and on which the balance due is $30,210.00, the over-all price thereof, including change orders being in the sum of $149,700.00. Count five is essentially a re-statement of the allegations in Count 4.

The plaintiff has denied all of the special defenses, as well as the essential allegations of the counterclaims, in its five counts.

Comprehensively, this litigation concerns itself with the claims and cross-claims for moneys due to and from the named litigants.

It further concerns itself with two separate construction projects — unrelated to each other — and for different owners. Obviously, the plaintiff — general contractor, and the defendant — sub-contractor, — are the same litigants herein.

The first project is known as the Trumbull Shopping Mall, or the Mall, and the second project is the Westport Motel, i.e. the Motel.

The first project was covered by a contract executed on August 14, 1985, and the second project was encompassed by a contract which was signed by the parties on February 20, 1986.

Both parties are in disagreement as to the date on which the defendant discontinued working on either or both projects; or in the alternative, when the defendant's services were terminated, or if they were terminated by the plaintiff under any provisions of the contract, dated August 14, 1985 and relating to the Mall as distinguished from the Motel.

On September 9, 1986, the defendant filed a mechanics lien against the Mall property to secure the sum of $77,041.00 claimed to be due to it for work and materials furnished under that contract.

The instant action was commenced in March of 1987, post-dating the filing of the defendant's mechanic's lien by approximately six months. CT Page 601

Again, the issue before the court is the amount of money owed to either litigant and the difference in these amounts, if any.

At the request of the plaintiff and the defendant, the Court has viewed the premises, i.e., the Mall, as it relates to the work done or not done by either party, whether done satisfactorily or not.

The Court has examined the testimony in this case, as well as the many exhibits on file.

The Court has also studied and re-studied the thoroughly well prepared briefs which have been submitted.

The plaintiff asserts in the first of its two briefs that "the cause of action between the above parties is for breach of contract, i.e., Count 1: BREACH OF CONTRACT.

The Court queries whether it was the intention of the plaintiff to abandon its quest for relief on the remaining count which is captioned: Count II: NEGLIGENCE.

This may very well be evidenced by one or all of three reasons. One, the failure by the plaintiff to allude to this count in its brief; two, the failure by the plaintiff to offer even a minimal amount of evidence in support of that count; and three, the specific indications by the plaintiff in its brief that this action is for "breach of contract."

Nevertheless, the Court will embrace both counts in its holdings to the extent that it becomes pertinent to do so. It would appear, however, that the resolution of the issues raised by the one count might very well be dispositive of the issues, if any, raised in the second Count.

The core of this litigation concerns itself primarily with the provisions of the Mall sub-contract between these parties, which absorbs within its terms, an earlier contract between the named plaintiff, the general contractor, and the owner of the subject premises, i.e. Westfield Inc. For reasons of brevity, the latter, where it becomes necessary to do so, will be referred to as the "owner".

This latter agreement, the over-all contract will be referred to as #1, and the sub-contract will be referred to as #2.

An examination of contract #2 would indicate that the defendant obligated itself to perform some — but not all — of CT Page 602 the concrete work for the "Mall" project, for the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sturman v. Socha
463 A.2d 527 (Supreme Court of Connecticut, 1983)
Hallmark of Farmington v. Roy
471 A.2d 651 (Connecticut Appellate Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
1991 Conn. Super. Ct. 598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petrucci-constr-v-strafach-sons-no-cv-87-23-86-75-jan-30-1991-connsuperct-1991.