Petrocon Engineering, Inc. v. Mac Equipment, Inc.

199 F. Supp. 2d 599, 2002 U.S. Dist. LEXIS 7840, 2002 WL 825701
CourtDistrict Court, E.D. Texas
DecidedMarch 5, 2002
Docket1:00-cv-00203
StatusPublished

This text of 199 F. Supp. 2d 599 (Petrocon Engineering, Inc. v. Mac Equipment, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petrocon Engineering, Inc. v. Mac Equipment, Inc., 199 F. Supp. 2d 599, 2002 U.S. Dist. LEXIS 7840, 2002 WL 825701 (E.D. Tex. 2002).

Opinion

MEMORANDUM OPINION

COBB, District Judge.

Before the court is defendant’s Motion for Summary Judgment. The court having reviewed the motions and responses on file, is of the opinion that summary judgment for the defendant should be GRANTED.

I. Introduction

This is a contractor case. The plaintiff, Petrocon Engineering (Petrocon), is a contractor and was working on a project for Mobil Chemical Company (Mobil). Petro-con subcontracted the construction of a vessel which was to be used in the completion of the project to the defendant, MAC Equipment (MAC). MAC constructed the vessel, which was installed at the Mobil facility. However, Mobil decided to improve the quality of the welds, which cost Mobil $225,000. Upon completion of the entire project, Mobil did not pay Petrocon a bonus in the amount of $168,000. Petro-con now brings this suit against MAC for the amount of $168,000.

II. Facts

Petrocon is a Texas corporation with a principle place of business in Jefferson County, Texas. MAC is a Kansas corporation, doing business in Texas. Therefore, this court has jurisdiction and venue.

Beginning in December, 1997, through a usual exchange of documents in a contractor-subcontractor setting, MAC entered into a written contract with Petrocon to manufacture and supply a Product Purge Vessel Extension with Bag House (vessel) for use at the Mobil plant in Beaumont, Texas. On December 30, 1997, Petrocon submitted a request for quotation. That request incorporated Mobil Guide EGE 12-B-l, which included requirements regarding welding and testing of welds. On January 18, 1998, Petrocon received a response from MAC which contained the following provisions entitled “Clarifications and Exceptions”:

•We will weld .a head on the bottom of the vessel and then perform a hydrostatic test in lieu of 100% radiography. The head will be removed once all testing is complete.
•Our proposal is based on 70% joint efficiency in lieu of 100% joint efficiency.
•Per ASME, radiography is not required for.joint efficiency of .70. No radiography will be performed.
•MAC Equipment will provide a certificate of hydrostatic test. We take exception to providing hydrostatic test charts.

Defendant’s Exhibit C. On January 26, 1998, Petrocon was sent a letter submitting a commercial summary with references to dates for “approval drawings” and “certified drawings”. Defendant’s Exhibit D. On March 26,1998, Petrocon responded by letter to the “Clarifications and Exceptions” from above, and did not object to the exceptions aside from noting “Minimum spot radiography is required.” Defendant’s Exhibit E. On March 31, 1998, MAC responded to this most recent letter with a letter containing detailed welding procedure specifications. On April 2,1998, Petrocon responded, again regarding welding specifications.

On April 23, 1998, Petrocon sent a Purchase Order to MAC for the manufacture of the vessel. The following relevant provision were contained in the order:

•The vendor must adhere to the requirements of Mobil Guide EGE 12-B-1.
•As a minimum, the Vendor shall perform spot radiography.
*602 •All of Vendor’s or Subvendor’s welding procedures must be in compliance with Mobil EGE 00-B-21.
•Certificate of Hydrostatic test in lieu of test chart is acceptable.
•Vendor shall revise the design documents as may be required per Purchaser’s comments and then present the revised documents to the Purchaser for initialing prior to issuing for construction.
•Any subsequent revisions to the approved drawings, specifications, or other documents shall be presented to the Purchaser for approval and initialing prior to reissue.

Defendant’s Exhibit J (emphasis omitted). On April 27, 1998, MAC responded with additional welding specification comments. Petrocon responded with an April 29,1998, letter stating its approval of MAC’s written welding procedure specification.

On May 21, 1998, MAC submitted an engineering drawing to Petrocon for approval. Contained on that drawing were the following specifications. “Radiography required [ — ] None, Joint efficiency (shell/ head) [ — ] .70, Shop hydro test pressure [ — ] 60 psig.” Defense Exhibit K. This drawing was signed by David Grim, Petro-con’s representative, and marked for resubmission. On June 29, 1998, a final engineering drawing was signed by David Crim, and marked “Approved with Changes”. Defense Exhibit L.

MAC proceeded to fabricate the vessel. The hydrostatic test was performed on August 28, 1998, and 60 psig of pressure were applied for one hour. Petrocoris authorized inspector, Ken Rutherford, visited MAC’s facilities in Houston three times during the fabrication of the vessel, and was present when the vessel passed the hydrostatic test on August 28, 1998. Defense Exhibit 0. The vessel was shipped to Petrocon on September 2,1998.

III. Summary Judgment Standard

A court should grant summary judgment when “there is no genuine issue as to any material fact and [ ] the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). A fact is material if it might affect the outcome of a case under the governing substantive law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). A genuine issue exists when, in the context of the entire record, a reasonable fact-finder could return a verdict for the non-movant. Lujan v. National Wildlife Federation, 497 U.S. 871, 885-86, 110 S.Ct. 3177, 111 L.Ed.2d 695 (1990). The court must view the evidence introduced and all factual inferences from the evidence in the light most favorable to the party opposing summary judgment. Eastman Kodak v. Image Technical Services, 504 U.S. 451, 478, 112 S.Ct. 2072, 119 L.Ed.2d 265 (1992); Lemelle v. Universal Mfg. Corp., 18 F.3d 1268, 1272 (5th Cir.1994). However, this favorable presumption for the non-movant exists only when the non-movant presents an actual controversy of fact. Little v. Liquid Air Corp., 37 F.3d 1069, 1075 (5th Cir.1994).

IV. Breach of Contract Claim

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Little v. Liquid Air Corp.
37 F.3d 1069 (Fifth Circuit, 1994)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
Eastman Kodak Co. v. Image Technical Services, Inc.
504 U.S. 451 (Supreme Court, 1992)
Rio Grande Valley Gas Co. v. City of Edinburg
59 S.W.3d 199 (Court of Appeals of Texas, 2000)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
R & P Enterprises v. LaGuarta, Gavrel & Kirk, Inc.
596 S.W.2d 517 (Texas Supreme Court, 1980)
Pierce v. Benefit Trust Life Insurance Co.
784 S.W.2d 516 (Court of Appeals of Texas, 1990)
Archer v. Griffith
390 S.W.2d 735 (Texas Supreme Court, 1964)
Harris v. Rowe
593 S.W.2d 303 (Texas Supreme Court, 1979)
Gracia v. RC Cola-7-Up Bottling Co.
667 S.W.2d 517 (Texas Supreme Court, 1984)
Nguyen Ngoc Giao v. Smith & Lamm, P.C.
714 S.W.2d 144 (Court of Appeals of Texas, 1986)
Sun Oil Co. (Delaware) v. Madeley
626 S.W.2d 726 (Texas Supreme Court, 1981)
Sage Street Associates v. Northdale Construction Co.
863 S.W.2d 438 (Texas Supreme Court, 1993)
GTE Mobilnet of South Texas Ltd. Partnership v. Telecell Cellular, Inc.
955 S.W.2d 286 (Court of Appeals of Texas, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
199 F. Supp. 2d 599, 2002 U.S. Dist. LEXIS 7840, 2002 WL 825701, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petrocon-engineering-inc-v-mac-equipment-inc-txed-2002.