Petra, Inc. v. BEI Construction, LLC; Selective Insurance Company of America; Frankenmuth Agency, Inc. d/b/a Frankenmuth Insurance Company; and BEI Framing, LLC

CourtDistrict Court, D. Idaho
DecidedMarch 23, 2026
Docket1:24-cv-00097
StatusUnknown

This text of Petra, Inc. v. BEI Construction, LLC; Selective Insurance Company of America; Frankenmuth Agency, Inc. d/b/a Frankenmuth Insurance Company; and BEI Framing, LLC (Petra, Inc. v. BEI Construction, LLC; Selective Insurance Company of America; Frankenmuth Agency, Inc. d/b/a Frankenmuth Insurance Company; and BEI Framing, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petra, Inc. v. BEI Construction, LLC; Selective Insurance Company of America; Frankenmuth Agency, Inc. d/b/a Frankenmuth Insurance Company; and BEI Framing, LLC, (D. Idaho 2026).

Opinion

UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF IDAHO

PETRA, INC., and Idaho Corporation, Case No. 1:24-cv-00097-DCN Plaintiff, MEMORANDUM DECISION AND v. ORDER

BEI CONSTRUCTION, LLC, an Indiana limited liability company; SELECTIVE INSURANCE COMPANY OF AMERICA, a New Jersey corporation; FRANKENMUTH AGENCY, INC. d/b/a FRANKENMUTH INSURANCE COMPANY, a Michigan corporation; and BEI FRAMING, LLC, a Michigan limited liability company,

Defendants.

I. INTRODUCTION Before the Court is Defendants BEI Construction, LLC and BEI Framing, LLC’s (collectively “BEI”) Joint Motion for Summary Judgment. Dkt. 37. Plaintiff Petra, Inc. opposes the Motion. Dkt. 40. The Court held oral argument on December 18, 2025, and took the matter under advisement. Upon review, and for the reasons outlined below, the Court GRANTS in PART and DENIES in PART BEI’s Motion for Summary Judgment. II. BACKGROUND On March 11, 2021, Petra entered into a contract with Meridian Hotel Holdings,

LLC (the “Owner”) to act as the general contractor for the construction of the WoodSpring Suites Meridian (the “Project”). On September 10, 2021, Petra entered into a subcontract (the “Subcontract”) with BEI Construction, LLC. The scope of work under the Subcontract required BEI Construction to “provide all labor, equipment and materials for all Rough Carpentry.” Dkt.

39-1, at 24. This included wood framing, installation of truss systems, wood blocking, and backing/fasteners (such as nails and staples). Id. Separately, the Parties contracted additional work from BEI including building wrap installation and window installation. Id. BEI, in turn, hired subcontractors to complete various tasks. In March of 2022, BEI Construction sold all its assets to BEI Framing, LLC. Petra

consented to the assignment of the Subcontract to BEI Framing. On June 30, 2022, the Project was substantially completed. In December of 2022, the Owner hired Rich Blakeley at Intermountain Building Inspections Corporation (“IBIC”) to inspect the Project. Blakeley generated an inspection report which found, in relevant part, inadequately sloped and sealed Packaged Terminal

Air Conditioner (“PTAC”) sleeves (the area around an air conditioning unit) and missing cap flashing (a waterproofing barrier). Dkt. 39-3, at 23, 29, 42. Blakeley also noted the window frames would need to be repaired or replaced. Id. at 42. Owner notified Petra of the alleged defects/deficiencies on the Project via a Notice of Claim (the “Notice”) letter dated December 30, 2022. Petra, in turn, notified multiple subcontractors, including BEI, that their work may be contemplated by the Notice. Petra

took the position that BEI should immediately defend and indemnify it from any claims arising from BEI’s work under the Subcontract. BEI refused. BEI countered that, because it did not install the PTAC units or the windows (only the window framing), its workmanship was not at issue and the damage outlined was outside its scope of work. Owner hired RDH Building Science, Inc. (“RDH”) in January of 2023 to conduct

additional inspections and provide supplemental reports. In a supplemental report published in March of 2023, RDH noted the PTAC units were installed without the proper slope and noted certain issues with the window installation. Relevant here, RDH found the window frame openings were larger than necessary and, therefore, had been lined with framing lumber and sheathing products to reduce the rough opening size. However, RDH

noted this “furring out” of oversized openings was industry practice. Petra then filed this lawsuit. Dkt. 1. BEI informed Petra that the defects alleged in the various reports related to other subcontractors, that they were not liable, and asked Petra to dismiss them from the suit. Petra refused. On March 25, 2024, Petra filed its Second Amended Complaint alleging the following causes of action: (1) Breach of Contract; (2)

Negligence, and (3) Defense and Indemnity. Dkt. 9.1

1 Petra subsequently settled its claims with all parties except BEI. See, e.g., Dkt. 36. As part of discovery, Petra identified IBIC and RDH as their non-retained experts and incorporated by reference the December 2022 Report and the March 2023 report outlining the defects each expert identified. RDH produced a cost-estimate report as part

of this process suggesting all 133 windows would need to be removed to “access rough opening framing, adjust the rough opening as needed to install new windows or reinstall existing windows, adjust the rough opening framing as needed to install windows plumb and square, and with adequate clearances to properly install backer rod and sealant.” Dkt. 42-3, at 4. The cost associated with this: $133,000. Id.

BEI hired two experts of their own. The first concluded that “[n]o evidence suggests that the rough carpentry work of BEI either caused or contributed to the water intrusion” and that “BEI neither caused nor in any manner contributed to the alleged defective work or the damages claims by Owner in this matter.” Dkt. 39-5, at 25–26. BEI’s second expert came to the same conclusion:

BEI did not install the windows or PTACs and would therefore have no responsibility for the quality of the installation executed. Given that BEI provided adequate space for the products to be installed within the rough openings, the responsibility for the final installed condition would then fall on the window subcontractor and Petra as the general contractor.

Dkt. 39-7, at 13. Based upon these reports, BEI again requested Petra dismiss them. Petra again refused. BEI then filed the instant Motion for Summary Judgment asking the Court to enter judgment in its favor on each of Petra’s claims. Dkt. 37.2

2 On February 6, 2025, Petra filed a Complaint in Federal Court, Case 1:25-cv-00068-BLW, including a claim for relief against Owner for Breach of Contract and arising from the Project. Owner filed its Answer on May 19, 2025, including counterclaims for alleged construction defects and costs to repair that implicate work by BEI, such as “[i]mproper framing and missing flashing around multiple windows and window frames.” Dkt. 42-5, at 12. That case is ongoing. III. LEGAL STANDARD Summary judgment is proper “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R.

Civ. P. 56(a). The Court’s role at summary judgment is not “to weigh the evidence and determine the truth of the matter but to determine whether there is a genuine issue for trial.” Zetwick v. Cnty. of Yolo, 850 F.3d 436, 441 (9th Cir. 2017) (citation modified). In considering a motion for summary judgment, the Court must “view[] the facts in the non- moving party’s favor.” Id.

To defeat a motion for summary judgment, the respondent need only present evidence upon which “a reasonable juror drawing all inferences in favor of the respondent could return a verdict in [his or her] favor.” Id. Accordingly, the Court must enter summary judgment if a party “fails to make a showing sufficient to establish the existence of an element essential to that party’s case, and on which that party will bear the burden of proof

at trial.” Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). The respondent cannot simply rely on an unsworn affidavit or the pleadings to defeat a motion for summary judgment; rather the respondent must set forth the “specific facts,” supported by evidence, with “reasonable particularity” that precludes summary judgment. Far Out Productions, Inc. v. Oskar, 247 F.3d 986, 997 (9th Cir. 2001).

IV.

Free access — add to your briefcase to read the full text and ask questions with AI

Hill v. American Family Mutual Insurance
249 P.3d 812 (Idaho Supreme Court, 2011)
Brian & Christie, Inc. v. Leishman Electric, Inc.
244 P.3d 166 (Idaho Supreme Court, 2010)
Taylor v. Herbold
483 P.2d 664 (Idaho Supreme Court, 1971)
Carroll v. United Steelworkers of America
692 P.2d 361 (Idaho Supreme Court, 1984)
Duffin v. Idaho Crop Improvement Ass'n
895 P.2d 1195 (Idaho Supreme Court, 1995)
Salmon Rivers Sportsman Camps, Inc. v. Cessna Aircraft Co.
544 P.2d 306 (Idaho Supreme Court, 1975)
Toyota of Florence, Inc. v. Lynch
713 F. Supp. 898 (D. South Carolina, 1989)
Sumpter v. Holland Realty, Inc.
93 P.3d 680 (Idaho Supreme Court, 2004)
Path to Health v. Daren Long
383 P.3d 1220 (Idaho Supreme Court, 2016)
Victoria Zetwick v. County of Yolo
850 F.3d 436 (Ninth Circuit, 2017)
Adams v. United States
823 F. Supp. 2d 1074 (D. Idaho, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Petra, Inc. v. BEI Construction, LLC; Selective Insurance Company of America; Frankenmuth Agency, Inc. d/b/a Frankenmuth Insurance Company; and BEI Framing, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petra-inc-v-bei-construction-llc-selective-insurance-company-of-idd-2026.