Petition of Peoples Natural Gas Co.

358 N.W.2d 684, 1984 Minn. App. LEXIS 3862
CourtCourt of Appeals of Minnesota
DecidedDecember 4, 1984
DocketC5-84-875, C9-84-913, C0-84-914, C8-84-921 and C6-84-934
StatusPublished
Cited by11 cases

This text of 358 N.W.2d 684 (Petition of Peoples Natural Gas Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petition of Peoples Natural Gas Co., 358 N.W.2d 684, 1984 Minn. App. LEXIS 3862 (Mich. Ct. App. 1984).

Opinion

OPINION

HUSPENI, Judge.

Peoples Natural Gas Company (Peoples), a division of InterNorth, Inc., petitioned the Minnesota Public Utilities Commission (Commission) to increase its rates for retail natural gas service within Minnesota by approximately $2,622,000. The Commission issued a decision on June 1, 1983, allowing Peoples to increase its rates on an interim basis, subject to refund, by $2,035,-000 for gas service to all classes of customers. By orders dated February 8, April 26, and June 22, 1984, the Commission allowed Peoples a final increase of only $276,000.

Appeals were filed by Hanna Mining Company, Hibbing Joint Venture, Erie Mining Company, United States Steel Corporation, Eveleth Taconite Company, and Reserve Mining Company regarding the refunding procedure followed by the Commission, and by Peoples contesting the denial of the full increase. All appeals were consolidated. We affirm.

FACTS

1. Peoples’ appeal

Peoples is an operating division of Inter-North, Inc., distributing natural gas at retail to customers in Minnesota and other states. Northern Natural Gas Company (Northern), a sister division of InterNorth and Peoples’ wholesale supplier, operates an extensive pipeline system through central United States and is regulated by the Federal Energy Regulatory Commission (FERC).

*687 On April 8, 1983, Peoples filed a petition with the Commission pursuant to Minn. Stat. § 216B.16 (1982) for increased gas rates, to produce an additional $2,622,000 in annual gross revenue. Pursuant to Minn. Stat. § 216B.16, subd. 3 (1982), the Commission authorized and established Peoples’ interim rates for Peoples to collect $2,035,-000 of additional annual revenues, subject to refund, pending a final order.

In 1981, InterNorth constructed two extensions from the Northern Natural Pipeline to serve Hibbing Taconite Co. and Inland Steel Company. Each extension consisted of a lateral pipeline and a town border station (which consisted of a measuring and regulating facility). The lateral pipelines connected the existing Northern Natural Pipeline with the town border stations. The total cost was $2.6 million ($2.3 million to build the lateral pipeline and $313,000 to build the measuring and regulating facilities).

InterNorth charged the entire cost of the extensions to Peoples. Construction was the responsibility of Northern, and legal title is in Northern’s name. The cost of construction was to be paid by Peoples through a “contribution in aid of construction” to Northern. Peoples included in their requested rate base a return for the contributions to Northern. The Commission approved the inclusion of the contribution in Peoples’ rate base in a 1981 rate case.

In the present 1983 rate case, a hearing examiner recommended the contributions be excluded from Peoples’ rate base. The Commission rejected the recommendation, noting no additional evidence had been presented. It simply summarized what it had done in the 1981 case and reaffirmed its original decision. In its February 8, 1984, Findings of Fact, Conclusions of Law and Order, the Commission stated:

The Commission considered this issue in Peoples’ first rate ease, G-011/GR-80-850. No additional evidence has been presented in the current proceeding. In that case, the Commission found that Northern’s applications to FERC for authority to construct and operate the facilities necessary to establish new delivery points for Peoples for the service of two taconite customers were filed on the basis that Northern would be reimbursed by Peoples for the cost of constructing the new facilities. The Commission also found that the FERC certificates of public convenience and necessity authorizing that construction were granted on the basis that Northern would be reimbursed by Peoples for the cost of construction. As a consequence, the Commission found that the cost of constructing the new facilities could not be included in Northern’s FERC rate base and should be included in Peoples’ Minnesota rate base. The Commission reaffirms its original decision on this issue in this proceeding.

(Emphasis added.)

A dissent was filed, claiming fourteen miles of pipeline does not constitute an appurtenance to the measuring and regulating facilities, and urging that this was “a blatant attempt by the parties to manipulate the Minnesota rate base and resultant rates.”

Upon reconsideration, the Commission issued an order dated April 26, 1984, reversing its prior decisions by eliminating the costs of the pipeline extensions from Peoples’ rate base. The Commission concluded that the Federal Energy Regulating Commission Tariff, pursuant to which these costs were assigned to Peoples, did not cover such costs. On the other hand, the cost of constructing the measuring and regulating facilities at the town border station was properly allowable in the rate base. The Commission stated in its April 26, 1984, Order After Reconsideration:

While the evidence may be similar to that before it in the earlier case, the Commission finds that upon re-examination of the record in this proceeding it must ipiestion the inferences drawn from such evidence in its initial decision. The Commission now finds that it gave inadequate weight to the relationship between Peoples and Northern and the *688 record evidence of how that relationship affected the contributions in aid of construction. Moreover, it had not adequately considered the meaning of “appurtenances” in its prior decisions. Upon reconsideration, taking these factors into account, the Commission reverses its prior decisions regarding these contributions in aid.

Peoples then filed a Petition for Further Hearing asking the Commission to receive additional testimony and evidence. By order of May 3, 1984, the Commission denied Peoples’ petition. Peoples appeals from the Commission’s orders of April 26 and May 3, 1984.

2.Taconite appeal

Peoples’ customers in Minnesota are divided into six classes: general service, small volume firm, small volume interrupti-ble, large volume firm, large volume inter-ruptible and taconite. The interim rate increase of $2,035,000 was allocated to each customer class based on an equal percentage of nongas costs. Peoples had requested the entire amount of the proposed general rate increase and the interim rate increase be assigned to Peoples’ general service class customers only.

In its order of February 8, 1984, the Commission determined that the general service class would be allocated a rate increase of only $829,000 in contrast to the $2,622,000 sought by Peoples and the $2,035,000 authorized as an interim rate increase by the Commission. (The $829,000 was reduced to $276,000 after the removal from the base rate of the unamortized contributions in aid of construction for the pipeline extensions). No other class rate was increased. The Commission did not refund to the other classes, however, all of the interim increases they had paid even though the Commission found the nongen-eral service class rates should not be increased.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rudebeck v. Paulson
612 N.W.2d 450 (Court of Appeals of Minnesota, 2000)
Kellar v. Von Holtum
605 N.W.2d 696 (Supreme Court of Minnesota, 2000)
Contel of Minnesota, Inc. v. Minnesota Public Utilities Commission
532 N.W.2d 583 (Court of Appeals of Minnesota, 1995)
Matter of Intra-Lata Equal Access
532 N.W.2d 583 (Court of Appeals of Minnesota, 1995)
Wangen v. Commissioner of Public Safety
437 N.W.2d 120 (Court of Appeals of Minnesota, 1989)
Application of Peoples Natural Gas Co.
413 N.W.2d 607 (Court of Appeals of Minnesota, 1987)
Application of Peoples Natural Gas Co.
389 N.W.2d 903 (Supreme Court of Minnesota, 1986)
Petition of Inter-City Gas Corp.
358 N.W.2d 692 (Court of Appeals of Minnesota, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
358 N.W.2d 684, 1984 Minn. App. LEXIS 3862, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petition-of-peoples-natural-gas-co-minnctapp-1984.