Petition of Green Mountain Power Corp.

385 A.2d 1110, 136 Vt. 170, 1978 Vt. LEXIS 711
CourtSupreme Court of Vermont
DecidedApril 5, 1978
Docket58-75 & 83-75
StatusPublished
Cited by5 cases

This text of 385 A.2d 1110 (Petition of Green Mountain Power Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petition of Green Mountain Power Corp., 385 A.2d 1110, 136 Vt. 170, 1978 Vt. LEXIS 711 (Vt. 1978).

Opinion

Barney, C.J.

Most of the issues in this rate case were disposed of by the time of the final order of the Public Service Board on March 31, 1975. Ultimately the matter has come to settle on the appeal by the Attorney General of Vermont. His appeal raises but two issues: (1) that the motion to dismiss filed by the Attorney General at a point when Green Mountain Power had allegedly put in its evidence in chief should' have been granted; (2) that'the order of the Board allowed rate relief to which the power company was not entitled.

The background of this case has already had extended exposition in a previous decision reported at 133 Vt. 107, and will not be repeated here. The factual discussion will be confined to just so much of the circumstances of the case as are essential to make clear the treatment of the two quite straightforward issues of this appeal.

It is the position of the Attorney General that failure of the power company to produce evidence, in its main casé, to support a rate increase required dismissal by the Board. We recognize that the Attorney General’s contention concerning the lack of evidence at that point in the case is contested, but for the purposes of dealing with this allegation of error we will assume it to be true.

V.R.C.P. 41 (b) (2) gives a trial court the right, in an action tried without jury, to decline to render judgment until the close of all of the evidence. Prior to the adoption of these rules a motion to dismiss, in an action tried by court, was premature prior to findings. In re Rathburn, 128 Vt. 429, 432, 266 A.2d 423 (1970). All this is in accord with the thesis that the order of reception of evidence is within the trial court’s discretion, and that the court, as trier, has the capacity to handle a defendant’s election to stand on the insufficiency *173 of the plaintiff’s proof by putting in no case of his own without the court being prejudiced by the tactic.

In a rate case involving a regulated utility, other considerations move the rule even further away from the claim for dismissal for failure of proof. The interests involved in the proceeding outreach the usual situation of contending private parties. The Board has a responsibility not only to protect the consumer from overcharge but also to preserve the capacity of the utility to provide the service required by the public.

It is for this reason the Board has the right to solicit evidence, to enlarge the proceedings or, if necessary, to originate them in the first place. Carpenter v. Home Telephone Co., 122 Vt. 50, 54, 163 A.2d 838 (1960). With such a responsibility, once a rate issue is opened, the Board is not required to terminate it merely because, as is alleged here, some insufficiency of advocacy may temporarily indicate an unsupported case at a point before the evidence was all in. Perhaps such a motion could be granted if the evidence was insufficient and it appeared to the Board that the public interest could thus best be served, but it is not required that ■it be granted. The ruling below was correct.

The second issue raised by the Attorney General is a claim that the rate order eventually granted by the Board included recoupment labelled “interim relief,” in spite of the facts that such recoupment had already been waived by the utility and there was no authority by which the Board could grant interim relief.

Neither of these positions can be sustained. The nature of the Board’s responsibility to maintain utility services and to prevent the overburdening of the ratepayer may require it to amend its orders or set aside stipulations. The test is whether the orders of the Board carry out its statutory purposes, and, of course, the Board is aided by a presumption in favor of the validity of its orders. Wendland v. Green Mountain Power Corp., 132 Vt. 320, 322, 318 A.2d 668 (1974).

A discussion of the second issue requires some history. This rate case began in September, 1973. The utility requested a *174 16.7 percent increase in its retail rates for electricity. At that time, in separate litigation, the validity of automatic purchased power and fuel adjustment clauses was under scrutiny before the courts. As a consequence the Board extended the time for filing direct evidence until determination of the propriety of the fuel adjustment clause. It granted a 10 percent temporary increase. This decision came down March 29, 1974. Both of these cases were at a time of rapidly advancing fuel costs.

The utility amended its request for a permanent increase April 15, 1974, asking for 35 percent. In May the Board cancelled the existing fuel adjustment clause and granted the utility a second temporary increase of 15.4 percent. That aspect of this case was challenged and brought to this Court in the case reported at 133 Vt. 107.

Meanwhile, time was passing and the utility, in June 1974, further amended its permanent rate increase request by 27.5 percent, bringing its total requested level of permanent rate increase to 62.5 percent. This request was suspended pending final determination, as the previous requests had been, and an increase in the temporary rates already allowed of an additional 30 percent was allowed at the end of July. This meant that the total of temporary rate increases allowed represented a total increase of 55.6 percent.

The permanent rate increase hearing began in October, 1974, and concluded on March 21,1975. During this period, on November 28, the Board reduced the temporary rate increase previously allowed to a level of 35 percent over base rates. In January of 1975 the temporary rates were restored to the previous 55.6 percent level. The final order was issued March 31, 1975, and allowed a 36.36 percent permanent increase over the former base rates. The order also provided that this utility would not be required to refund any of the money collected under any temporary rate increases granted in this proceeding, nor would it be allowed to collect any recoupment for this sixteen month period.

It is the second argument of the Attorney General that this rather pragmatic decision to allow the utility to retain the additional money collected under temporary rate increases to cover established revenue deficiencies is actually recoup *175 ment. More than that, claims the Attorney General, as recoupment it fails to follow the requirements of 30 V.S.A. § 226 (b) and sets at naught the stipulation entered by the utility waiving “any claim to recoup or recover any difference between the rates finally approved in such order and the rates charged prior thereto.”

30 V.S.A. § 226 provides in subsection (a) that if the Board finds justification on any of three grounds, after ordering that proposed rate changes not go into effect, it may authorize temporary rate increases pending disposition as it did here. In re New England Tel. & Tel. Co., 131 Vt. 310, 316, 305 A.2d 598 (1973).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Central Vermont Public Service Corp.
463 A.2d 525 (Supreme Court of Vermont, 1983)
In Re Consolidated Rate Appeals of Green Mountain Power Corp.
455 A.2d 823 (Supreme Court of Vermont, 1983)
In re Vermont Electric Cooperative, Inc.
451 A.2d 1110 (Supreme Court of Vermont, 1982)
Petition of Central Vt. Public Service Corp.
449 A.2d 904 (Supreme Court of Vermont, 1982)
In Re New England Telephone & Telegraph Co.
433 A.2d 263 (Supreme Court of Vermont, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
385 A.2d 1110, 136 Vt. 170, 1978 Vt. LEXIS 711, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petition-of-green-mountain-power-corp-vt-1978.