Petition of Citizens Utilities Company

216 A.2d 923, 125 Vt. 388, 1966 Vt. LEXIS 198
CourtSupreme Court of Vermont
DecidedFebruary 1, 1966
Docket1969
StatusPublished
Cited by2 cases

This text of 216 A.2d 923 (Petition of Citizens Utilities Company) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petition of Citizens Utilities Company, 216 A.2d 923, 125 Vt. 388, 1966 Vt. LEXIS 198 (Vt. 1966).

Opinion

Keyser J.

This is an appeal by Citizens Utilities Company (Citizens) from an order of the Public Service Board (Board) dated October 22, 1963.

The petition of Citizens seeks an order directing Vermont Electric Power Company, Inc. (Velco) to supply subtransmission of Citizens own allotments of St. Lawrence power and Niagara Power Project.

Citizens contends it is entitled to be compensated for the transmission of its own allocations of such power from its interconnection with Velco at Highgate to its load centers or principal distribution areas.

. The first hearing was held on January 23, 1962. At the close of the hearing that day the hearing was scheduled for another date but was adjourned from time to time thereafter. On August 10, 1962, Citizens filed a motion to amend its petition requesting the approval of the Board of an annexed stipulation entered into by Citizens and Velco which provided for a settlement of the proceedings agreeable to them.

The Board set this motion to amend for hearing on October 2, 1962, notice of which was ordered to be given to all parties of record and others. The reporter engaged to take the hearing lacked the required proficiency which necessitated a recess of the hearing until the following day to permit the Board to obtain a second reporter. On April 12, 1963, it appeared to the Board that this reporter also was unable to furnish a transcript. The Board then gave notice it “would proceed without a transcript.” It allowed time for the filing of requests for findings of fact which both Citizens and Velco filed.

The Board filed findings of fact on September 13, 1963, and its order on October 22, 1963. The order denied Citizens’ motion to amend its petition, declined to accept the stipulation of Citizens and Velco, and dismissed Citizens original petition.

The only hearing held on the original petition was on January 23, 1962, of which a transcript was made. In the preface to its findings of fact the Board stated under the caption of “Summary of Proceedings” that Citizens was “fully heard.” The transcript of that hearing on January 23, 1962 shows that counsel for Citizens then stated it had other evidence to present on the issues raised by its petition. Other parties, also, especially Velco, had not been heard in opposition to the *390 petition. The Board announced it would recess and reconvene on February 14, 1962 but no further hearing was held on that petition.

The Board, by legislative act, is authorized as agent of the State, with the approval of the Governor, to contract for the purchase of electric energy from any source outside of Vermont and to resell it on a non-profit basis to electric distribution utilities, without preference or discrimination, for distribution within the state. 30 V.S.A. §211. In January, 1956, the Board entered into a contract with the Power Authority of the State of New York, expiring in 1985, for the purchase of 100,000 kilowatts of firm power and energy generated at the St. Lawrence Project.

On June 13, 1957, the Board acting for the State entered into an agreement with Velco to deliver this state-owned power either directly, or through the facilities of others, from the state boundary to the various electric utility companies (state’s allottees) in Vermont. Delivery was to be at such locations and at voltages specified by the State, there being twenty-eight allottees.

To fully perform its transmission contract of St. Lawrence power, Velco was required to make contracts with six other utilities for the subtransmission of the state power over their systems to reach allottees not directly connected with Velco’s transmission system. Payment for the use of such facilities was made on a uniform method of computation. The terms and conditions of such contracts were approved by the Board.

One such contract was with Citizens entered into on September 23, 1958. The contract stipulated for the delivery of St. Lawrence power over Citizen’s system to six allottees in the northeast part of the state.

In 1960, Citizens completed construction of a second circuit from Highgate to Newport. The circuit from Highgate to Richford was constructed as a 115 KV H-Frame line and has been operated at 48KV. The circuit from Richford to Newport was constructed at 48 KV as a second circuit installed on existing steel towers.

In 1961 the State entered into a second contract with the Power Authority of the State of New York for the purchase of an additional 50,000 kilowatts of firm power and energy generated at the Niagara Project. 30 V.S.A. §21 la. Again, this power was resold by the State to its allottees on the same formula or basis as the St. Lawrence power.

The contracts which Velco had made with other utilities for the use of their facilities for the subtransmission of St. Lawrence power were amended to also cover Niagara power and were approved by the *391 Board. Citizens refused to sign the amendment to its contract with Velco. This precipitated a petition to the Board by Velco to require Citizens to transmit Niagara power for Velco to the six allottees interconnected with Citizens’ system.

On December 29, 1961, the Board in that case ordered Citizens to accept at its Highgate interconnection, and transmit to those allottees, the allocated power from the Niagara project over its facilities on the same terms and conditions set forth in the 1958 transmission contract between Velco and Citizens relating to St. Lawrence power. On appeal to this court in that case the order of the Board has been affirmed by opinion filed concurrently herewith. In re Petition of Vermont Electric Power Company, Inc., 125 Vt......., 216 A.2d 918.

Velco transmits state power from near Plattsburg, New York, to Essex, thence to Highgate where delivery is made to Citizens by an interconnection between the two systems. Citizens has 15 major distribution areas serving around 25,000 people. Citizens is a single interconnected distribution system receiving its power from the Highgate interconnection with Velco and from its own generating point. Citizens’ allotment is 5101 KW of St. Lawrence power and 2478 KW of Niagara power. At the outset Citizens purchased only 1 KW of St. Lawrence power with the right to recall the balance. When Niagara power became available it elected to purchase its entire allotment of 7579 KW.

Highgate is the only delivery point of state power to Citizens’ system. Highgate is around 15 miles east of Alburg and 70 miles west of Island Pond, both distribution areas of Citizens. Newport, the largest area, is some 50 miles east of Highgate.

As a result of this distance from its interconnection with Velco at Highgate to these areas, Citizens, as conceded in the Board’s brief, has a relatively high cost per kilowatt for transmission of its own allotment of state power. Herein lies Citizens claim by its original petition that it should be supplied subtransmission of state power from High-gate to its distribution areas. Citizens claims it will then be given equal treatment with the other utilities which it asserts do receive their allotments from Velco, at or near their principle distribution areas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Citizens Utilities Co.
250 A.2d 844 (Supreme Court of Vermont, 1969)
Petition of Vermont Electric Power Company
216 A.2d 918 (Supreme Court of Vermont, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
216 A.2d 923, 125 Vt. 388, 1966 Vt. LEXIS 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petition-of-citizens-utilities-company-vt-1966.