Peterson v. State

645 S.W.2d 807, 1983 Tex. Crim. App. LEXIS 900
CourtCourt of Criminal Appeals of Texas
DecidedFebruary 16, 1983
Docket60679
StatusPublished
Cited by70 cases

This text of 645 S.W.2d 807 (Peterson v. State) is published on Counsel Stack Legal Research, covering Court of Criminal Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peterson v. State, 645 S.W.2d 807, 1983 Tex. Crim. App. LEXIS 900 (Tex. 1983).

Opinion

OPINION ON REHEARING ON COURT’S OWN MOTION

ONION, Presiding Judge.

This is an appeal from a conviction for theft over $10,000.00, a felony of the second degree. V.T.C.A., Penal Code, § 31.03. Following the jury’s guilty verdict, the court assessed punishment at five (5) years’ imprisonment, probated, with a requirement of $8,480.21 in restitution as a condition of probation.

On original submission the conviction was affirmed in a panel opinion with one judge dissenting as to the sufficiency of the evidence to sustain the conviction. The court on its own motion has granted rehearing to consider en banc the sufficiency of the evidence issue. The opinions on original submission are withdrawn.

This case arose out of a construction contract. Marvin Loveless, the complaining witness, decided to build a second unit to his mini-warehouse with an apartment on the top at one end. The appellant, a con *808 struction contractor, was recommended to bim. Loveless sought a bid from the appellant as well as the Denton Construction Company. The latter bid $84,000.00 or $85,-000.00 and the appellant bid $61,000.00. Appellant's bid of November 2, 1976 was accepted on November 3, 1976 by Loveless and the agreement then entered into excluded site work, electrical and plumbing work and a permit which was to be arranged for by Loveless. The agreement provided for payments “Every 30 days for material on job site & work performed.”

On November 18, 1976, Loveless paid appellant $10,000.00. On December 2, 1976, a payment of $20,000.00 was made. Another payment of $15,000.00 was made on January 8, 1977 by Loveless to appellant. On February 18,1977, a $5,000.00 payment was made, and on March 24, 1977, a $4,000.00 payment was made by Loveless to the appellant. On April 12, 1977, another $4,000.00 payment was made. In all, Loveless paid the appellant $58,000.00. It was Loveless’ understanding from his conversations with the appellant that the money advanced was being used by the appellant for materials needed for the construction job.

The construction at the site by the appellant commenced in December, 1976, and progressed until sometime in May, 1977. It was not at the rate of progress appellant had promised, but Loveless knew at the time of agreement the appellant was working on at least two other larger construction sites at the same time. No date of completion was placed in the agreement or contract.

In May, 1977, Loveless began receiving calls from various suppliers who stated they had not been paid for materials they had furnished for his job site. Loveless began having difficulty in contacting the appellant. He finally found the appellant on the job site. Appellant asked for an additional advance of money to pay for sheet metal for partitioning. Loveless first told appellant to make arrangements to pay for it himself, but later stated he would pay for it personally, which he did. On May 25, 1977, he mailed to the appellant a list of things that needed to be done at the- site, and on May 31, 1977, mailed a letter to appellant, stating that since no work had been done recently at the site he assumed appellant had abandoned the site. These letters were returned “addressee unknown.” It was later established that the letters had been mailed to the wrong address.

Loveless then hired a worker previously employed by the appellant to complete the job. He testified that when appellant ceased working on the building it was “more than seventy-five percent” completed and he was satisfied with most of the work.

Charles Davis, Jr., of the Denton Concrete Company, testified that the appellant had an outstanding bill of $2,064.00 for concrete, etc., supplied to the Loveless job site. After billing appellant and unsuccessfully trying to contact him by telephone, his company placed a lien on Loveless’ property. David related that approximately a month before trial, May, 1978, appellant paid the outstanding bill in full and a release of the lien against Loveless’ property was executed.

Doug Rankin of the Boyd Houston Company testified his company supplied concrete accessories to the Loveless job site and their bill was approximately $900.00. He had been in contact with appellant, but the bill had not been paid. Rankin related that no lien had been placed against the Loveless property and the company was looking solely to the appellant for payment.

H.A.' Hollerman of Ward and Capers, Inc., testified his company supplied steel doors and frames and other hardware to the Loveless job site. Appellant did not pay the bill for $3,986.21. The company was still looking to appellant for payment.

Pat Bell of the Bell Roofing Company testified that his company put the roof on the Loveless building at the direction of the *809 appellant. He testified his 35 to 40 efforts to contact the appellant about the bill of $2,700.00 were unsuccessful. Since appellant did not pay the bill, a lien was placed on the Loveless property.

Bod Edwards of Hipwell Sheet Metal, Inc., testified his company installed the sheet metal gravel guards on the roof of the Loveless building. His attempts for seven or eight months to collect the bill from the appellant were unsuccessful and a lien of $1,082.00 was placed against the Loveless property.

Appellant testified that he entered the agreement as a subcontractor and considered Loveless the general contractor since there were several contractors over which he had no control, and the agreement expressly excluded site work, plumbing and electrical work and permits. Appellant also related he was to build the shell of the building and Loveless was to paint, caulk and “fix up” the building.

Loveless told him that their written agreement would be drafted into a formal contract by his lawyer-son, but the same was never done.

Appellant admitted receiving the money from Loveless described above. He related the agreement called for monthly payments and he and Loveless agreed on the payments for materials furnished and work done before the payments were made. Appellant testified he used one operating bank account for his business, and that all operating costs were paid out of this account. He had placed the money he received from Loveless in this account. This was the manner in which he had conducted his construction business for five years. Appellant stated his agreement with Loveless did not include a provision as to a fiduciary or trust account and there was no requirement of any separate account. He had six construction jobs between November, 1976 and May, 1977. In March, 1977, he testified that a $36,000.00 payment was withheld from a Lewisville school project on which he was working and he had hired an attorney to pursue collection. Appellant did not pay Hipwell Sheet Metal, Inc., because he did not have a contract with them and understood the particular work was to be included in his contract with Bell Roofing Company. He had not paid Bell because he had been charged more than the agreed price, and felt he would lose any leverage necessary for a settlement if he paid the amount he thought was due. He had not paid Ward and Capers because the door jambs, door and locks he received were not the proper size and he felt he was entitled to an offset. He acknowledged he was indebted to the Denton Concrete Company and he had since paid them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christie Zimmerman Kissinger v. State
Court of Appeals of Texas, 2017
Gerald Christopher Zuliani v. State
Court of Appeals of Texas, 2015
Taylor, Henry Jr.
450 S.W.3d 528 (Court of Criminal Appeals of Texas, 2014)
Daugherty, Tonya Jean
387 S.W.3d 654 (Court of Criminal Appeals of Texas, 2013)
Larry Allen Mize v. State
Court of Appeals of Texas, 2012
Wirth v. State
361 S.W.3d 694 (Court of Criminal Appeals of Texas, 2012)
Wirth, Raymond Waier
Court of Criminal Appeals of Texas, 2012
Jose De Leon Pena v. State
Court of Appeals of Texas, 2011
Romie Jewel Blount v. State
Court of Appeals of Texas, 2011
Kenneth Garrett Beatty v. State
Court of Appeals of Texas, 2010
Bailey v. State
304 S.W.3d 544 (Court of Appeals of Texas, 2009)
Joe Don Bailey v. State
Court of Appeals of Texas, 2009
Wirth v. State
296 S.W.3d 895 (Court of Appeals of Texas, 2009)
Raymond Waier Wirth v. State
Court of Appeals of Texas, 2009
Casey J. Moore v. State
Court of Appeals of Texas, 2009
Sergio Sierra v. State
Court of Appeals of Texas, 2008
H. A. Reed D/B/A Reed Construction v. State
Court of Appeals of Texas, 2008
Christensen v. State
240 S.W.3d 25 (Court of Appeals of Texas, 2007)
Edward Christensen v. State
Court of Appeals of Texas, 2007

Cite This Page — Counsel Stack

Bluebook (online)
645 S.W.2d 807, 1983 Tex. Crim. App. LEXIS 900, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peterson-v-state-texcrimapp-1983.