Peterson v. Eugene Water & Electric Board

275 F. Supp. 286, 1967 U.S. Dist. LEXIS 8606
CourtDistrict Court, D. Oregon
DecidedApril 18, 1967
DocketCiv. No. 65-395
StatusPublished
Cited by1 cases

This text of 275 F. Supp. 286 (Peterson v. Eugene Water & Electric Board) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peterson v. Eugene Water & Electric Board, 275 F. Supp. 286, 1967 U.S. Dist. LEXIS 8606 (D. Or. 1967).

Opinion

OPINION FINDINGS AND ORDER

KILKENNY, District Judge:

Segregated for trial is the limited issue on the effect of a receipt and release, executed by Bechtel Corporation (Bechtel) and Eugene Water & Electric Board (Eugene) on October 14, 1963.

Eugene, defendant and third-party plaintiff, owns and operates a series of hydro-electric dams and reservoirs, collectively known as the Carmen-Smith Project, on the Smith and McKenzie Rivers in Lane and Linn Counties in Oregon.

Bechtel designed and supervised the construction of certain aspects of the project under a contract with Eugene dated August 27, 1959. Plaintiff, E. W. Peterson, was Bechtel’s resident project engineer and the owner of real property adjacent to the McKenzie River below the Carmen-Smith Project.

Peterson, in his complaint, charges that about December 22, 1964, Eugene stored an immense amount of water in its reservoirs and about said date, without warning, released an abnormal amount of the water through the spillways of the dams, thus increasing the natural flow of the McKenzie River and resulting in substantial damage to his property. Eugene denies this and alleges that the damage, if any, sustained by plaintiffs was an Act of God. Also, Eugene filed a counterclaim against Peterson and the Bechtel Corporation.'

At the time plaintiffs’ property was damaged, Carmen Power House, a structure located inside the Trail Bridge Reservoir, was inundated by a rise in the water level. Eugene charges in the counterclaim that Peterson and Bechtel were responsible for the damage resulting from such rise because of negligence in design, location and construction of the power house and in failing to give proper warning and advice. Fireman’s Fund Insurance Company and Insurance Company of North America, the concerns, which had insured the power house, were added as parties plaintiff to the counterclaim on motion of plaintiffs.

In addition to the work on the Carmen Power House, Bechtel also designed, prepared cost estimates and supervised the construction of the Smith Power Tunnel, another major part of the Carmen-Smith Project. The Smith Power Tunnel failed [288]*288during tests in the early part of 1963 and thereafter a controversy arose between Eugene and Bechtel as to the latter’s responsibility for the cost of redesigning and repairing the Smith Power Tunnel. This subject was compromised and settled by the parties, at which time the receipt and release,1 here in question, was executed.

Simply stated, the issue before me is whether the instrument executed October 14, 1963, released and discharged Bechtel and Peterson from liability for the damage sustained December 22, 1964, on (1) a theory of negligence in design and supervision, or (2) liability for failure to give reasonable and proper warnings.

Generally, the breadth and scope of a release is determined by the intention of the parties at the time of execution. Consequently, its operation is limited to matters within the contemplation of the parties at that time. Hicklin v. Anders, 201 Or. 128, 253 P.2d 897, 269 P.2d 521 (1954); Rudick v. Pioneer Memorial Hospital, 296 F.2d 316 (9th Cir. 1961); United States v. Ramstad Construction Co., 194 F.Supp. 379 (D. Alaska 1961); Williston on Contracts (Rev. ed.), Vol. 6, § 1825, pp. 5167-69.

Undisputed is the fact that Bechtel, in the exercise of its expertise on the subject, designed and supervised the construction of the project. Moreover, the record is practically undisputed that it advised Eugene as to difficulties encountered and the progress on the project. When, in March, 1963, the project was nearing substantial completion Eugene incurred additional cost in excess of one million dollars in redesigning and reconstructing the Smith Power Tunnel, it very properly made a claim against Bechtel for the additional cost.

As an outgrowth of this claim, a meeting was held in Bechtel’s San Francisco offices, at which time the representatives of the respective parties thoroughly discussed the nature of the tunnel failure and the problems resulting therefrom, particularly the unfavorable financial position in which the failure placed Eugene. Even the project’s general contractor, Peter Kiewit Sons Co., was drawn into the discussion by reason of a demand for additional compensation. The meeting adjourned after a discussion of the reasons for the tunnel failure and the legal responsibility of professional engineers for project failures. The subject of a release was not mentioned at this meeting. Later, on October 7th, the executive vice-president of Bechtel' contacted the superintendent-secretary of Eugene and proposed that Bechtel make a payment or reduce its fee in connection with the tunnel controversy and suggested an additional conference. This conference was held on October 11th, at which time the parties again discussed the problem at the San Francisco offices of Bechtel. This discussion centered around the sum of money Bechtel should pay and in what form it should be paid. A release was not discussed. Bechtel, in that meeting, agreed to reduce its fee to the Board by the sum of $350,000.00. [289]*289A rough draft of a release2 was presented. This instrument, together with the final draft, was prepared by counsel for Bechtel. After preparation and execution by Bechtel, the instrument was forwarded to Eugene where it was signed on October 14th.

Manifestly, the only problems in the minds of the parties during the negotiations and at the time the release was executed were those connected with, or occasioned by, the rupture of the tunnel project and the demands being made by the project’s main contractor, Peter Kiewit Sons Co.

The language of the instrument and the actions of the parties support, beyond question, a finding that the parties never intended to discharge Bechtel from responsibility for future damages. The language of the release, when interpreted in the light of the negotiations between the parties is conclusive against Bechtel’s contention. The significance of the use of the terms “all” and “arising out of”, although they may create a certain amount of ambiguity, completely disappear when viewed in the light of the negotiations. Moreover, it must be kept in mind that Bechtel, in drafting the release, consciously made it sufficiently broad to include the substantial demands of the eon-tractor, which had not yet ripened into legal action.

Bechtel’s argument that the claim for damages resulting from improper design of the power house, or failure to warn regarding its operation, was not a “future” claim, but existed at the very time the instrument was executed, is tenuous in the extreme. The fact that Eugene knew, or by the exercise of reasonable diligence should have known, before signing the release, of the maximum operating level of the Trail Bridge Reservoir and the elevation of the door and the windows of the Carmen Power House, does not require a different conclusion. Eugene was still relying on the expertise of Bechtel.

Furthermore, a claim or a cause of action in negligence does not accrue until some damage occurs. Kropitzer v. City of Portland, 237 Or. 157, 390 P.2d 356 (1964); Berry v. Branner, Or.,

Related

Cite This Page — Counsel Stack

Bluebook (online)
275 F. Supp. 286, 1967 U.S. Dist. LEXIS 8606, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peterson-v-eugene-water-electric-board-ord-1967.