Petersburg Plumbing & Heating Co. v. State

36 Ill. Ct. Cl. 171, 1984 Ill. Ct. Cl. LEXIS 89
CourtCourt of Claims of Illinois
DecidedJanuary 25, 1984
DocketNo. 80-CC-1811
StatusPublished

This text of 36 Ill. Ct. Cl. 171 (Petersburg Plumbing & Heating Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petersburg Plumbing & Heating Co. v. State, 36 Ill. Ct. Cl. 171, 1984 Ill. Ct. Cl. LEXIS 89 (Ill. Super. Ct. 1984).

Opinion

Roe, C.J.

The case at bar is yet another claim by a contractor seeking to recover damages arising out of the breach of a contract by the Secretary of State relating to the remodeling and rehabilitation of the Illinois State Capitol Building which began in the latter half of calendar year 1977. This Claimant had contracted to perform the heating and air conditioning work. As in the other claims, the Respondent breached the contract by failing to vacate certain areas of the Capitol which were undergoing renovation, the result being that the contractor was prevented from proceeding with the work from time to time, particularly when the legislature was in session.

Although at all relevant points in time this Claimant stood ready and willing to perform its end of the contract, it was not until April of 1980 that the Claimant completed its work, nearly a year and one-half after the projected completion date. Claimant promptly filed this claim. The damages arose out of the lengthy suspensions and delays of the work. In calculating the dollar amount of its bid and in agreeing to the contract Claimant had relied on being able to complete the project within the time specified and agreed to. Other claims of a similar nature which arose out of the delays in this project have been awarded and paid. See R. D. Lawrence Construction Company v. State (1983), 35 Ill. Ct. Cl. 709.

In its complaint Claimant seeks the sum of $26,537.00. However, the Claimant and the Respondent subsequently entered into a compromise and agreed that $13,494.52 represented a fair and reasonable settlement of this claim. Said amount was arrived as itemized below:

Additional labor................... $ 3,599.43

Insurance......................... 1,461.09

Tool rental........................ 700.00

Nonproductive labor............... 4,750.00

Supervision (supervisor time actually spent at construction meetings)....+ 1,224.00

Subtotal ......................... $11,734.52

Overhead and profit at 15%.......+ 1,760.10

Total............................. $13,494.52

We have reviewed the entire record in this matter including the evidence offered in support of the settlement, find that the settlement was arrived at fairly by arms length negotiation, and agree with the parties that it is fair and reasonable according to the facts of this case. Therefore, we hereby award the Claimant the sum of $13,494.52.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R. D. Lawrence Construction Co. v. State
35 Ill. Ct. Cl. 709 (Court of Claims of Illinois, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
36 Ill. Ct. Cl. 171, 1984 Ill. Ct. Cl. LEXIS 89, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petersburg-plumbing-heating-co-v-state-ilclaimsct-1984.