Peterman v. Goss

160 P. 432, 93 Wash. 184, 1916 Wash. LEXIS 1182
CourtWashington Supreme Court
DecidedOctober 17, 1916
DocketNo. 12753
StatusPublished
Cited by2 cases

This text of 160 P. 432 (Peterman v. Goss) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peterman v. Goss, 160 P. 432, 93 Wash. 184, 1916 Wash. LEXIS 1182 (Wash. 1916).

Opinion

Pee Curiam.

Tacoma School District No. 10, on September 9, 1912, let to F. H. Goss the general contract for the construction of the Central School building, in the city of Tacoma. This contract required the building to be completed by July 15,1913. The contracts for excavation, heating, plumbing, electric work and painting were let to other contractors. Goss’ contract contained the following provisions :

“(1) Contractor. The contractor is to provide all materials and labor necessary for the complete and substantial execution of everything described, shown or reasonably implied in the drawings and specifications for his part of the work, including all transportation, scaffolding, apparatus and tools necessary for the same. All materials shall be the best of their respective kind, and all workmanship shall be of the best quality.
'“(2) Other Contractors. The general contractor shall allow the contractors for parts of the work not included in his contract proper room for the storage of their materials and the execution of their work. The contractors shall work in harmony. The architects and superintendent will settle all differences arising, and their advice and orders shall be binding and final. Each contractor is to carefully read all of the specifications, so as to better understand his part of the work. The contractors are to carry on their work at all times with the greatest reasonable rapidity under the direction and to the satisfaction of the architects, superintendent and owner.
[186]*186“(3) Interpretation of Drawings. In the event of any doubt or question arising respecting the true meaning of the drawings or specifications, reference shall be made to the architects, whose decision shall be final and conclusive.
“(4) Damages Claimed for Delays by Other Contractors. Should any contractor or subcontractor claim damages on account of the delay, negligence or carelessness of other contractors, or for any other cause, he must declare the amount of such damages and make claim for same in writing at the time the damage is incurred. He shall deliver such written claim to the architects or superintendent and to the party at fault, within 48 hours of the occurrence, that such claim may be adjusted by the architects or superintendent. Failure to act as provided above will render such claim null and void.
“(5) The heating, plumbing, electric work, painting and general excavation will be let in separate contracts, and are not included in the general contract.”

On November 4,1912, Goss entered into a subcontract with the Peterman Manufacturing Company to supply the necessary mill work for the building. This contract was as follows :

“Contract for Millwork for Central School.
“Tacoma, Washington, Nov. 4th, 1912.
“We propose to furnish you all the mill work to be used in the construction of the new Central school building situated on South G street between South 7th and South 8th, in the city of Tacoma, according to plans, specifications and details prepared by the architects, Heath & Gove, for the sum of eight thousand seven hundred dollars ($8,700), delivered to the building site.
“Delivery.
“We agree to keep in touch with the contractor of this building and furnish said mill work when needed and in such a manner so as not to detain the progress of the building.
“Terms.
“Eighty per cent to be paid upon delivery of material, on or before the 10th of each month for all material delivered during the preceding month, and the remaining 20 per cent to be paid when building is completed and mill work accepted by architects. (Said 80 per cent to be paid upon approval of mill work by the architects.)
[187]*187“We agree to make good any defects in material or workmanship for a period of six months after final acceptance by the architects as required by the specifications.
“It is further understood that we have read all the general conditions of the architects’ specifications, and the specifications connected with our portion of the work, and this bid and agreement is made in accordance therewith.”

The subcontractor began furnishing mill work on December 5, 1912, and continued to do so until November 8, 1913. The building was ready for the interior finish on April 30, 1913, and the subcontractor began supplying material therefor on May 1, 1913. From this date until September 11, 1913, constant protests were made by the contractor against the delay in furnishing mill work. On February 10, 1913, the Peterman Company was paid $938 on account, and on June 28, 1913, was paid $2,000 on a bill rendered for $4,000. F. H. Goss having died, his widow was appointed executrix and proceeded with the contract. On her refusal to pay the balance of the contract price in the sum of $5,762, together with a claim of $721 for extras, the Peterman Manufacturing Company brought suit for $6,483 against the executrix and the sureties upon the contractor’s bond. The defendants set up a counterclaim for damages in the sum of $549.83 for material the plaintiff had neglected to supply and which was procured at the contractor’s expense; $913 for expense of handling and refinishing defective mill work; $1,120 for overhead expenses for seventy days’ delay; $1,412.50 for twenty-five per cent loss in erection efficiency and expense, due to delay on the part of the subcontractor; and $122.50 for interest paid on money borrowed by reason of the plaintiff’s delay. The action was tried by the court, which reduced plaintiff’s claim for extras to $389.50, and reduced defendants’ set-off for plaintiff’s failure to furnish items called for by the contract to $440.83. The balance of plaintiff’s contract price was allowed in full, and judgment given for plaintiff in the sum of $5,710.67. The defendants appeal.

[188]*188The only question involved on this appeal is the right of appellants to set off the items of $913, $1,120, $1,412.50, and $122.50, set out above.

In its memorandum decision the trial court recited that,

“Defendant claims items amounting to $913 for working over imperfect mill work. The court finds that defendant is not entitled to credit for these. No notice of any such claim was given at the time as required by specifications on page 7.”
“Defendant claims that they were damaged by delay on the part of plaintiff in furnishing materials. Items amounting to $2,654.50. The court finds that plaintiff did occasion considerable delay by not furnishing the mill work as required. However, defendants never gave notice of their claim in this respect as required by the specifications on page 7.”

The provision referred to by the court as being on page seven of the specifications is the paragraph numbered (4) which we have quoted from the contract.

Construing the different sections of the specifications together, we think it is plain that the term “other contractors,” as used in this section, does not have reference to the subcontractors or materialmen under the general contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westland Construction Co. v. Chris Berg, Inc.
215 P.2d 683 (Washington Supreme Court, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
160 P. 432, 93 Wash. 184, 1916 Wash. LEXIS 1182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peterman-v-goss-wash-1916.