Peter Scott v. Andrew Grim and Rachel Grim

CourtCourt of Appeals of Texas
DecidedOctober 21, 2024
Docket05-23-01250-CV
StatusPublished

This text of Peter Scott v. Andrew Grim and Rachel Grim (Peter Scott v. Andrew Grim and Rachel Grim) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peter Scott v. Andrew Grim and Rachel Grim, (Tex. Ct. App. 2024).

Opinion

Reversed and Remanded and Opinion Filed October 21, 2024

In The Court of Appeals Fifth District of Texas at Dallas No. 05-23-01250-CV

PETER SCOTT, Appellant V. ANDREW GRIM AND RACHEL GRIM, Appellees

On Appeal from the County Court at Law No. 5 Dallas County, Texas Trial Court Cause No. CC-23-02984-E

MEMORANDUM OPINION Before Justices Reichek, Nowell, and Wright1 Opinion by Justice Reichek In this interlocutory appeal, Peter Scott contends the trial court erred in

denying his motion to compel arbitration of the claims asserted against him by

Andrew and Rachel Grim. Because we conclude (1) the agreement to arbitrate is

enforceable by Scott and (2) the agreement delegates arbitrability issues to the

arbitrator, we reverse the trial court’s order and remand the cause for further

proceedings consistent with this opinion.

1 The Hon. Carolyn Wright, Justice, Assigned Background

In February 2020, the Grims purchased a residential home in Dallas, Texas

and began the process of renovating the property. Scott, as the principal and

managing member of Jim Scott and Sons Builders LLC (“JSS”), submitted a bid for

his company to do the remodeling work. On June 8, 2020, the Grims paid Scott an

initial deposit of $201,050 to begin work on the house. Four months later, they

signed a Construction Agreement with JSS with an effective date of May 21, 2020.

The Construction Agreement defines the parties to the contract to be Andrew

and Rachel Grim as the owners and JSS as the contractor. The contract includes an

arbitration provision stating in part,

The Parties agree that any case of any controversy or claim arising out of or relating to this Contract, including but not limited to the breach of any provision hereof, or the Project, shall be submitted to mediation (the Parties to mutually agree upon a mediator) with the Parties splitting the cost of any mediation fees and, if not settled during mediation, shall thereafter be submitted to binding arbitration. The arbitrator shall be selected by the mutual agreement of the Parties or, if the Parties cannot agree, the selection will be made pursuant to the American Arbitration Association (“AAA”) Construction Industry Rules from a panel of arbitrators approved by the AAA. The arbitration shall be conducted pursuant to the AAA Construction Industry Rules.

Immediately following the arbitration provision is a provision entitled “Binding

Effect.” The Binding Effect provision states,

This Contract and the terms, covenants, conditions, provisions, obligations, rights, and benefits shall be binding upon and shall inure to the benefit of the Parties and their respective directors, officers, members, employees, agents, legal representatives, successors, predecessors, and assigns.

–2– The contract specifies it is to be interpreted, enforced, and governed under the laws

of the State of Texas, and any arbitration or mediation of claims arising under the

contract is to be conducted in Dallas County. Both the Grims signed the contract in

their individual capacities as the owners of the property. Scott signed the contract

on behalf of JSS as the company’s principal.

The Grims filed this suit on May 17, 2023 asserting claims against Scott for

fraudulent inducement, fraudulent misrepresentation, fraud by non-disclosure,

misapplication of construction trust funds, breach of fiduciary duty, and violations

of the Texas Deceptive Trade Practices Act.2 They later added claims for

conversion, trespass, and conspiracy. In the “Overview” section of their live

pleading, the Grims asserted the basis of their suit was that Scott had fraudulently

induced them into hiring him to manage a construction project he was “completely

unqualified to handle.”

Scott filed a motion to compel arbitration asserting the Construction

Agreement included a valid agreement to arbitrate all claims arising out of or relating

to either the agreement or the construction project. Scott further argued the

agreement delegated issues of arbitrability to the arbitrator. The Grims responded

that their agreement to arbitrate was with JSS, not Scott, and their claims against

Scott were not based on his actions as an agent for JSS or the work he performed

2 The Grims additionally asserted claims against Tulip Project Group LLC, a separate entity allegedly owned by Scott. Tulip Project Group is not a party to this appeal. –3– pursuant to the contract. In addition, the Grims argued the conduct made the basis

of their claims occurred before they signed the Construction Agreement.

The trial court conducted a hearing on Scott’s motion. After considering the

parties’ arguments and the evidence submitted, the trial court denied Scott’s request

to compel arbitration. Scott brought this appeal.

Analysis

We review a trial court’s order denying a motion to compel arbitration for an

abuse of discretion. Henry v. Cash Biz, LP, 551 S.W.3d 111, 115 (Tex. 2018).

Under that standard, we defer to the trial court’s factual determinations if they are

supported by evidence and review its legal determinations de novo. Id.

The Construction Agreement does not reference either the Federal Arbitration

Act or the Texas Arbitration Act, but states that the laws of the State of Texas apply.

A general choice-of-law provision does not select the TAA to the exclusion of the

FAA. Roehrs v. FSI Holdings, Inc., 246 S.W.3d 796, 803 (Tex. App.—Dallas 2008,

pet. denied). Instead, both acts apply and the FAA will preempt the TAA only if the

TAA is inconsistent with the FAA or would subvert enforcement of an agreement

otherwise enforceable under the FAA. In re D. Wilson Constr. Co., 196 S.W.3d 774,

780 (Tex. 2006); PER Group, L.P. v. Dava Oncology, L.P., 294 S.W.3d 378, 384

(Tex. App.—Dallas 2009, no pet.).

Arbitration is a matter of contract, and a party cannot be required to submit a

dispute to arbitration it has not agreed to so submit. AT & T Techs., Inc. v. Commc’ns

–4– Workers of Am., 475 U.S. 643, 648 (1986); Barantas Inc. v. Enterprise Fin. Grp.

Inc., No. 05-17-00896-CV, 2018 WL 3738089, at *6 (Tex. App.—Dallas Aug. 7,

2018, no pet.). A party seeking to compel arbitration must establish (1) there is a

valid arbitration agreement and (2) the claims in dispute fall within that agreement’s

scope. G.T. Leach Builders, LLC v. Sapphire V.P., LP, 458 S.W.3d 502, 524 (Tex.

2015); In re Rubiola, 334 S.W.3d 220, 223 (Tex. 2011). Whether a binding

arbitration agreement exists between specific parties is a gateway matter ordinarily

committed to the trial court to decide. G.T. Leach, 458 S.W.3d at 524; Zurvita

Holdings, Inc. v. Jarvis, No. 05-23-00661-CV, 2024 WL 1163209, at *8 (Tex.

App.—Dallas March 14, 2024, pet. filed) (mem. op.). As a general rule, an

arbitration provision cannot be invoked by a non-signatory to the contract. G.T.

Leach, 458 S.W.3d at 524. Ultimately, the question requires us to apply ordinary

Free access — add to your briefcase to read the full text and ask questions with AI

Related

At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
In Re D. Wilson Const. Co.
196 S.W.3d 774 (Texas Supreme Court, 2006)
In Re Rubiola
334 S.W.3d 220 (Texas Supreme Court, 2011)
Sherer v. Green Tree Servicing LLC
548 F.3d 379 (Fifth Circuit, 2008)
McGrath v. FSI Holdings, Inc.
246 S.W.3d 796 (Court of Appeals of Texas, 2008)
Sefzik v. Mady Development, L.P.
231 S.W.3d 456 (Court of Appeals of Texas, 2007)
PER Group, L.P. v. Dava Oncology, L.P.
294 S.W.3d 378 (Court of Appeals of Texas, 2009)
G.T. Leach Builders, LLC v. Sapphire V.P., Lp
458 S.W.3d 502 (Texas Supreme Court, 2015)
Jody James Farms, Jv v. the Altman Group, Inc. and Laurie Diaz
547 S.W.3d 624 (Texas Supreme Court, 2018)
Henry v. Cash Biz, LP
551 S.W.3d 111 (Texas Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Peter Scott v. Andrew Grim and Rachel Grim, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peter-scott-v-andrew-grim-and-rachel-grim-texapp-2024.