Pete Lien & Sons, Inc. v. Ellsworth Peck Construction Co.

896 P.2d 761, 1995 Wyo. LEXIS 92, 1995 WL 340636
CourtWyoming Supreme Court
DecidedJune 9, 1995
Docket94-203
StatusPublished
Cited by12 cases

This text of 896 P.2d 761 (Pete Lien & Sons, Inc. v. Ellsworth Peck Construction Co.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pete Lien & Sons, Inc. v. Ellsworth Peck Construction Co., 896 P.2d 761, 1995 Wyo. LEXIS 92, 1995 WL 340636 (Wyo. 1995).

Opinion

LEHMAN, Justice.

Appellant, Pete Lien & Sons, Inc., d/b/a/ Dakota Block Company, (Lien) appeals the *762 district court’s grant of summary judgment in favor of appellee Ellsworth Peck Construction Company (Peck) and United States Fidelity and Guaranty Company (U.S.F. & G.). Lien claims it is entitled to payment under a labor and materials bond from Peck, as principal, and U.S.F. & G., as surety, for construction materials Lien supplied. The district court found the question one of contract interpretation and granted summary judgment in favor of Peck and U.S.F. & G.

We affirm.

Lien raises two issues:

I. Can a surety who secretly provides a labor and material payment bond unknown to material suppliers, but benefitting material suppliers, which by its written terms provides for a 90 day dual notice provision as a precondition to litigation, but also by its own terms specifically incorporates Wyoming law and amends the period of limitation in which to commence litigation to conform to Wyoming law, circumvent the statutory minimum period of limitation by requiring compliance with the more stringent 90 day dual notice precondition thus extinguishing the claim of a material supplier?
II. Are the due process requirements of the Fourteenth Amendment to the United States Constitution and Article 1 Section 6 of the Wyoming Constitution triggered in a private contractual relationship between a state chartered surety company and a state chartered general contractor under a labor and material payment bond posted by the surety thus requiring actual or personal notice to be given to known claimants under the bond before a claim against the bond is extinguished?

Peck and U.S.F. & G. phrase the issues as follows:

I. Did the trial court err in its interpretation of the plain and clear language of the labor and material payment bond?
II. Are the constitutional issues of due process raised by appellant in its brief properly presented before this court and preserved for appeal since appellant did not present these issues or present argument on them at the time of trial?
III.Has appellant, a third party beneficiary, been deprived of any constitutional due process rights?

FACTS

Peck was in charge of constructing a K-Mart in Gillette, Wyoming, subcontracting the masonry work to Intermountain Contracting and Development Inc. (Intermoun-tain). Intermountain purchased concrete block from Lien in the amount of $54,024.70, charged to an open account, with the last invoice from Lien to Intermountain being sent on June 19, 1992. Lien attempted unsuccessfully to secure payment from Inter-mountain.

A year later, in June 1993, Lien learned that Peck had furnished a labor and materials bond to the owner of the K-Mart. Lien received a copy of the bond with a letter dated August 31, 1993. Lien then filed a complaint against Intermountain, Peck and U.S.F. & G. on October 28, 1993, alleging that Intermountain had failed or refused to pay Lien for the concrete block used in the K-Mart job. Lien also claimed that Peck, as principal, and U.S.F. & G., as surety, are bound to Lien for payment of materials used in the project. Lien obtained a default judgment against Intermountain which remains unsatisfied.

In granting summary judgment in favor of Peek and U.S.F. & G., the district court found the question one of contract interpretation and concluded that Lien had failed to make a claim in compliance with the terms of the bond. Lien timely appeals.

DISCUSSION

Summary judgment is appropriate when no genuine issues of material fact exist and the prevailing party is entitled to judgment as a matter of law. Union Pacific Resources Co. v. Texaco, Inc., 882 P.2d 212, 218 (Wyo.1994); W.R.C.P. 56(c). The interpretation of an unambiguous contract presents a question of law. Id., at 219. This court gives no special deference to the district court’s decisions on matters of law. Id. The material facts in this case are not disputed, thus the question is whether Peck was *763 entitled to summary judgment as a matter of law.

Lien contends the district court incorrectly interpreted the bond, arguing that the bond must be construed in its entirety, giving effect to all the various parts. Specifically, Lien argues paragraph 3(b) of the bond amends paragraph 3(a). The pertinent parts of the bond are as follows:

(3) No suit or action shall be commenced hereunder by any claimant,
(a) Unless claimant, other than one having a direct contract with the Principal, shall have given written notice to any two of the following: The Principal, the Owner, or the Surety above named, within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials * * *.
(b) After the expiration of one (1) year following the date on which Principal ceased work on said Contract, it being understood, however, that if any limitation embodied in this bond is prohibited by any law controlling the construction hereof such limitation shall be deemed to be amended so as to be equal to the minimum period of limitation permitted by such law.
(c) Other than in a state court of competent jurisdiction in and for the county or other political subdivision of the state in which the project, or any part thereof, is situated, or in the United States District Court for the district in which the project, or any part thereof, is situated, and not elsewhere.

Relying on paragraph 3(b), Lien claims W.S. 38-1-101 (1977) amends paragraph 3(a) so that the words “a reasonable time” lengthen the 90-day provision. Section 38-1-101 states:

A person bound as surety in a written instrument for the payment of money, or other valuable thing, may, if right of action accrues thereon, require his creditor by a notice in writing, to commence an action on such instrument forthwith, against the principal debtor; and unless the creditor commences such action within a reasonable time thereafter, * * * shall thereby forfeit the right which he would otherwise have * * *.

Lien claims it did act within a “reasonable time,” having discovered the bond’s existence in June 1993, receiving a copy August 31, and initiating suit in October 1993.

If an agreement is in writing, and its language is clear and unambiguous, the parties’ intention is to be secured from the words of the agreement. Moncrief v. Louisiana Land & Exploration Co., 861 P.2d 516, 524 (Wyo.1993); True Oil Co. v. Sinclair Oil Corp., 771 P.2d 781, 790 (Wyo.1989). When the meaning of a contract is unambiguous, the plain meaning of the terms is used. Union Pacific, 882 P.2d at 220;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mathisen v. Thunder Basin Coal Co., LLC
2007 WY 161 (Wyoming Supreme Court, 2007)
Hickman v. Groves
2003 WY 76 (Wyoming Supreme Court, 2003)
McGee v. Caballo Coal Co.
2003 WY 68 (Wyoming Supreme Court, 2003)
Newman v. RAG Wyoming Land Co.
2002 WY 132 (Wyoming Supreme Court, 2002)
State Ex Rel. Baker v. Strange
960 P.2d 1016 (Wyoming Supreme Court, 1998)
Hollingshead v. Hollingshead
942 P.2d 1104 (Wyoming Supreme Court, 1997)
Emmett Ranch, Inc. v. Goldmark Engineering, Inc.
908 P.2d 941 (Wyoming Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
896 P.2d 761, 1995 Wyo. LEXIS 92, 1995 WL 340636, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pete-lien-sons-inc-v-ellsworth-peck-construction-co-wyo-1995.