Perryman Construction Management Inc. v. Doeppel Premier Properties Idaho, LLC

CourtIdaho Court of Appeals
DecidedNovember 15, 2024
Docket51024
StatusPublished

This text of Perryman Construction Management Inc. v. Doeppel Premier Properties Idaho, LLC (Perryman Construction Management Inc. v. Doeppel Premier Properties Idaho, LLC) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perryman Construction Management Inc. v. Doeppel Premier Properties Idaho, LLC, (Idaho Ct. App. 2024).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF IDAHO

Docket No. 51024

PERRYMAN CONSTRUCTION ) MANAGEMENT, INC., an Idaho ) Filed: November 15, 2024 corporation, ) ) Melanie Gagnepain, Clerk Plaintiff-Counterdefendant- ) Respondent, ) ) and ) ) ALL PRO MECHANICAL, LLC, an ) Idaho limited liability company, ) ) Plaintiff-Counterdefendant, ) ) v. ) ) DOEPPEL PREMIER PROPERTIES ) IDAHO, LLC, an Idaho limited liability ) company, ) ) Defendant-Counterclaimant- ) Appellant, ) ) and ) ) STEPHEN’S ELECTRIC, INC., ) ) Intervenor. ) )

Appeal from the District Court of the Third Judicial District, State of Idaho, Canyon County. Hon. Brent L. Whiting, District Judge.

Judgment awarding attorney fees to All Pro Mechanical, LLC and Perryman Construction Management, Inc., affirmed; judgment confirming arbitration award and awarding attorney fees and costs to All Pro Mechanical, LLC and Perryman Construction Management, Inc., affirmed.

Borton-Lakey Law & Policy; Victor Villegas, Meridian, for appellant. Victor Villegas argued.

1 Smith + Malek, PLLC; Kirk Houston, Boise, for respondent. Kolby Reddish argued. ________________________________________________ TRIBE, Judge Doeppel Premier Properties Idaho, LLC (Doeppel) appeals from two judgments entered by the district court affirming an arbitration award and granting attorney fees and costs to All Pro Mechanical, LLC (All Pro) and Perryman Construction Management, Inc. (Perryman). We affirm. I. FACTUAL AND PROCEDURAL BACKGROUND Doeppel hired Perryman to be the general contractor for a construction project. The parties entered into a “Construction Services Agreement” (contract) wherein Perryman agreed to build five buildings within 200 days for a cost not to exceed $2,265,670.00. Based on Doeppel’s dissatisfaction with Perryman’s progress, Doeppel sent written notices to Perryman demanding the defects be cured within thirty days. Seven days after the last notice was sent, John Doeppel, the owner of Doeppel, came to the project site and told Kelly Perryman, the owner and principal officer of Perryman, to “[g]et the f*** off my site.”1 Perryman ceased operations and asked the City of Caldwell to remove Perryman as the general contractor for the project. Perryman filed a complaint against Doeppel for foreclosure of a mechanic’s lien, breach of contract, quantum meruit, and unjust enrichment.2 Doeppel responded by asserting the following counterclaims: breach of contract, breach of warranties, unjust enrichment, and a breach of fiduciary duties. Both parties stipulated to submit all claims and counterclaims to arbitration in

1 There is conflicting testimony about the exact phrase used by John Doeppel. Kelly Perryman testified that John Doeppel said “[g]et the f*** off my site” while a bystander testified that the phrase was “[g]et the f*** off my property.” For consistency purposes, we will use the former phraseology when referring to the statement. 2 All Pro Mechanical LLC (All Pro) was hired as a subcontractor by Perryman. All Pro was a complaining party and remained a party until after arbitration. The arbitrator awarded All Pro $111,279.69. Pending this appeal, Doeppel paid the judgment amount to All Pro and All Pro was dismissed as a party to this appeal.

2 conformity with the arbitration clause of the contract.3 At the conclusion of the hearing, the arbitrator issued an interim decision and then a final decision. The final decision and award were in favor of Perryman. In district court, Perryman filed a motion to confirm the award, and Doeppel filed a motion to vacate the award. At a hearing on the motions, the district court orally denied Doeppel’s motion to vacate the award and later entered an order confirming the arbitration award. Judgment was entered awarding Perryman attorney fees. A second judgment was entered on the arbitration award. Doeppel appeals both judgments of the district court. II. STANDARD OF REVIEW When reviewing a district court’s decision to vacate or modify an award of an arbitration panel, this Court employs virtually the same standard of review as that of the district court when ruling on the petition for review of the arbitration award. Bingham Cnty. Comm’n v. Interstate Elec. Corp., 105 Idaho 36, 42, 665 P.2d 1046, 1052 (1983). Review of an arbitrator’s award is limited to whether any of the grounds for relief stated in the Idaho Uniform Arbitration Act (UAA) exist. Idaho Code § 7-912; Moore v. Omnicare, Inc., 141 Idaho 809, 814, 118 P.3d 141, 146 (2005). An arbitrator’s rulings on questions of law and fact are binding, even where erroneous, unless one of the statutory grounds enumerated in I.C. § 7-912(a) is present. Moore, 141 Idaho at 815, 118 P.3d at 147. III. ANALYSIS Doeppel presents several issues on appeal. The first issue is whether the district court erred in confirming the arbitration award. Doeppel alleges the arbitrator exceeded his powers in two ways: the first was by exceeding the bounds of the contract by finding the contract was terminated by verbal communication, excusing Perryman from liability for Doeppel’s work after Perryman ceased work, and awarding damages to nonparties; and the second was by considering issues that were not submitted to the arbitrator by the parties. In response, Perryman contends that the arbitrator did not err and, therefore, Doeppel’s claims should not be reviewed on the merits.

3 Article 9.1. of the contract requires “[a]ny claim, dispute or other matter arising” out of the contract must be “decided by binding arbitration under the American Arbitration Association Construction Industry Rules.”

3 Alternatively, Perryman asserts that, even if the issues are reviewed, Doeppel’s arguments fail because the arbitrator’s findings are reasonable and the arbitrator considered issues that were properly before him. The second issue presented on appeal is whether the arbitration award can be modified. Doeppel argues the arbitration award can be modified pursuant to I.C. § 7-913(a)(2), which allows the modification or correction of an award when an arbitrator considers an award not submitted to the arbitrator. The final issue is whether Perryman is entitled to attorney fees on appeal. Perryman argues he is entitled to attorney fees pursuant to a contractual provision permitting fees when a party is enforcing arbitration. Doeppel argues the plain language of the contract does not provide for attorney fees on appeal. A. Arbitrator’s Powers Review of an arbitrator’s award is limited to whether any of the grounds for relief stated in the UAA exist. Idaho Code § 7-912; Moore, 141 Idaho at 814, 118 P.3d at 146. An arbitrator’s rulings on questions of law and fact are binding, even where erroneous, unless one of the statutory grounds enumerated in I.C. § 7-912(a) is present. Moore, 141 Idaho at 815, 118 P.3d at 147. Those grounds include an arbitrator exceeding his powers. I.C. § 7-912(a)(3). The Idaho Supreme Court has explained that an arbitrator exceeds its powers when the arbitrator considers an issue not submitted by the parties or when the arbitrator exceeds the bounds of the contract between the parties. Bingham Cnty. Comm’n, 105 Idaho at 42, 665 P.2d at 1052.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ticor Title Co. v. Stanion
157 P.3d 613 (Idaho Supreme Court, 2007)
Bingham County Commission v. Interstate Electric Co.
665 P.2d 1046 (Idaho Supreme Court, 1983)
American & Foreign Ins. Co. v. Reichert
94 P.3d 699 (Idaho Supreme Court, 2004)
Moore v. Omnicare, Inc.
118 P.3d 141 (Idaho Supreme Court, 2005)
Mumford v. Miller
137 P.3d 1021 (Idaho Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Perryman Construction Management Inc. v. Doeppel Premier Properties Idaho, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perryman-construction-management-inc-v-doeppel-premier-properties-idaho-idahoctapp-2024.