Perry v. Potashinski

47 N.E. 1022, 169 Mass. 351, 1897 Mass. LEXIS 78
CourtMassachusetts Supreme Judicial Court
DecidedOctober 21, 1897
StatusPublished
Cited by5 cases

This text of 47 N.E. 1022 (Perry v. Potashinski) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perry v. Potashinski, 47 N.E. 1022, 169 Mass. 351, 1897 Mass. LEXIS 78 (Mass. 1897).

Opinion

Holmes, J.

This is a petition to enforce a mechanic’s lien for labor, under Pub. Sts. c. 191, and comes here on report. We will take up in their order the points that were argued.

1. The respondent had employed a contractor to build a house upon his land, under a contract which provided that the contractor should “ not let, assign, or transfer this contract, or any interest therein, without the written consent of the architect.” The petitioner made a written subcontract with the contractor .to excavate for the cellar, do the grading about the building, and build the foundation walls, referring to the principal contract. There was no evidence that the respondent knew that the petitioner made the subcontract or did any work, and there was no written consent of the architect. The auditor to whom the case was sent, and the judge who tried the case upon the auditor’s report, found that the nature of the contract was such that the contractor, as matter of law, had authority from the respondent to employ the petitioner, and so that the petitioner’s labor was performed by consent of the respondent, within the meaning of § 1. The main contention of the latter is that the words quoted above from this contract do not admit of such a finding.

We are of opinion that the finding of the judge was right. The words quoted, literally interpreted, do not refer to subcontracts but to attempted assignments of an interest in the principal contract, a different matter. The literal interpretation is the only sensible one. Of course the contract did not mean that the contractor was to do all the work with his own hands, or that he was to apply to the architect for consent before he bespoke window frames or bricks. It must have contemplated the employment of subcontractors in the usual way. This is the scope of the decision in Wahlstrom v. Trulson, 165 Mass. 429, 434, which was not intended to suggest that, if this clause was known to the petitioner and means what the respondent contends, it would be immaterial on the question of the latter’s consent, or might not withdraw the consent otherwise to be implied from the nature of [353]*353the contract. Borden v. Mercer, 163 Mass. 7. Landers v. Dexter, 106 Mass. 531. Parker v. Bell, 7 Gray, 429.

2. On the question of the amount to be recovered, however, the petitioner’s right is not by way of subrogation to the principal contract. Bowen v. Phinney, 162 Mass. 593. The provision in the latter as to the allowance of claims of the "contractor for additional work does not refer to or affect claims like the petitioner’s.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green v. Reese
1953 OK 198 (Supreme Court of Oklahoma, 1953)
Vickery v. Richardson
75 N.E. 136 (Massachusetts Supreme Judicial Court, 1905)
Reid v. Berry
59 N.E. 760 (Massachusetts Supreme Judicial Court, 1901)
Monaghan v. Goddard
53 N.E. 895 (Massachusetts Supreme Judicial Court, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
47 N.E. 1022, 169 Mass. 351, 1897 Mass. LEXIS 78, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perry-v-potashinski-mass-1897.