Perry Engineering Company, Incorporated v. At & T Communications, Incorporated

998 F.2d 1010, 1993 U.S. App. LEXIS 25971, 1993 WL 264461
CourtCourt of Appeals for the Fourth Circuit
DecidedJuly 13, 1993
Docket92-2050
StatusUnpublished
Cited by3 cases

This text of 998 F.2d 1010 (Perry Engineering Company, Incorporated v. At & T Communications, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perry Engineering Company, Incorporated v. At & T Communications, Incorporated, 998 F.2d 1010, 1993 U.S. App. LEXIS 25971, 1993 WL 264461 (4th Cir. 1993).

Opinion

998 F.2d 1010

NOTICE: Fourth Circuit I.O.P. 36.6 states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Fourth Circuit.
PERRY ENGINEERING COMPANY, INCORPORATED, Plaintiff-Appellant,
v.
AT & T COMMUNICATIONS, INCORPORATED, Defendant-Appellee.

No. 92-2050.

United States Court of Appeals,
Fourth Circuit.

Argued: May 6, 1993.
Decided: July 13, 1993.

Appeal from the United States District Court for the Western District of Virginia, at Harrisonburg. James H. Michael, Jr., District Judge. (CA-90-153-H)

Argued: Gerald Isadore Katz, Katz & Stone, Vienna, Virginia, for Appellant.

John Foster Anderson, McGuire, Woods, Battle & Boothe, Alexandria, Virginia, for Appellee.

W.D.Va.

AFFIRMED.

Before PHILLIPS, NIEMEYER, and WILLIAMS, Circuit Judges.

PER CURIAM:

OPINION

Perry Engineering Co. brought this breach of contract action against AT & T Communications, Inc., seeking damages for cost-overruns in a construction contract. AT & T asserted that Perry was not entitled to additional compensation because it had failed to comply with the contract's procedure for obtaining compensation for expenses related to work changes. The district court agreed and granted summary judgment for AT & T. We affirm.

* Perry and AT & T entered into a contract under which Perry promised to provide all necessary labor and equipment to install approximately seventy miles of fiber optic cable in remote parts of West Virginia. The contract incorporated estimates AT & T had prepared regarding the work requirements which indicated that the cable was to be buried at a depth of forty-four inches. The estimates also indicated that 4,500 cubic yards of rock would be excavated using a jackhammer or hoe-ram at $50 per cubic yard and that 100 cubic yards of rock would be excavated using a trencher at $100 per cubic yard.

The actual specifications for burial of the cable, which were not included as part of the contract, provided for variations in the forty-four inch depth mentioned in the contract. These specifications indicated the cable was to be buried at a depth of forty-eight inches, but that the depth could be as little as twenty-four inches where solid rock was encountered.

Installation of the cable did not proceed on schedule. In order to allow timely completion of the project, the burial depth of the cable was modified to twenty-four inches with steel casing, regardless of the terrain. The parties dispute whether AT & T or Perry initiated this change, but its result is clear. Most of the excavation at the twenty-four inch depth was accomplished with a trencher, not a jackhammer or hoe-ram. Although AT & T paid Perry for this work at the higher rate of $100 per cubic yard, Perry, relying on the 4,500 cubic yard estimate, had already rented jackhammers that sat idle throughout the remainder of the project.

Ten months after completion of work, Perry asked AT & T to compensate it for the cost of this idle equipment. AT & T asserted that under the contract Perry was only entitled to compensation on a unit price basis. To the extent that the costs for idle equipment were caused by changes in the contract, AT & T claimed that Perry had not complied with contractual notice requirements in the"changes" clause of the contract that were a condition precedent for additional compensation.

Perry brought this action in Virginia state court for breach of contract, and AT & T removed the action under the diversity jurisdiction of the district court. The district court determined that the idle equipment expenses were caused by a change in the contract, and hence that the "changes" clause of the contract applied. The district court also determined that the "changes" clause in the contract was clear and unambiguous, that Perry had not provided timely notice, and that AT & T was therefore not obligated to recompense Perry for the additional expenses. Accordingly, the district court granted summary judgment for AT & T. Perry now appeals.

II

Perry urges that the court erred in three respects. First, Perry contends that the parties did not foresee that changes in the contract might result in additional expenses for idle equipment, and hence that the contract does not determine who bore the risk of incurring such expenses. Perry asks the court to determine, independently of the contract, who bore this risk. Second, Perry urges that if the contract does determine the rights of parties with regard to expenses for idle equipment, then AT & T has waived the requirement of timely notice. Perry contends that, with the exception of the ten-day timeliness requirement, the letter it sent to AT & T requesting additional compensation complies with the procedure set forth in the contract for obtaining additional compensation. Finally, Perry urges that because the contract is ambiguous regarding the rights of the parties, it is entitled to recover in quantum meruit.

We review de novo the district court's grant of summary judgment. Baber v. Hospital Corp. of Am., 977 F.2d 872, 874 (4th Cir. 1992). A party is entitled to summary judgment "if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." Fed. R. Civ. P. 56(c). With this standard in mind, we address Perry's arguments on appeal.

III

Perry first contends that the contract does not determine the parties' rights with regard to idle equipment expenses incurred as a result of changes in the contract. Perry urges that, because the parties omitted any provision defining the parties' rights in these circumstances, this court should supply such a provision by implication.

"When the parties to a bargain sufficiently defined to be a contract have not agreed with respect to a term which is essential to a determination of their rights and duties, a term which is reasonable in the circumstances is supplied by the court." Restatement (Second) of Contracts § 204 (1979). "Interpretation is necessarily the first step in [this] process, since a court will supply a term only after it has determined that the language of the agreement does not cover the case at hand." 2 E. Allan Farnsworth, Farnsworth on Contracts § 7.16, at 303 (1990); see also Restatement (Second) of Contracts § 204 cmt. c.

With regard to interpretation of a contract, Virginia adheres to the plain meaning rule. Where "the terms of an agreement are clear and unambiguous, the language used will be taken in its ordinary signification, and the plain meaning will be ascribed to it." Marriott Corp. v. Combined Properties Ltd. Partnership, 391 S.E.2d 313, 316 (Va. 1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bernsen v. Innovative Legal Marketing, LLC
885 F. Supp. 2d 830 (E.D. Virginia, 2012)
ASHLEY RIVER INDUSTRIES, INC. v. Mobil Oil Corp.
135 F. Supp. 2d 733 (D. South Carolina, 2000)
Oppedahl & Larson v. Network Solutions, Inc.
3 F. Supp. 2d 1147 (D. Colorado, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
998 F.2d 1010, 1993 U.S. App. LEXIS 25971, 1993 WL 264461, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perry-engineering-company-incorporated-v-at-t-communications-ca4-1993.