Perrotto Builders, Ltd. v. Reading School District

108 A.3d 175, 2015 Pa. Commw. LEXIS 23
CourtCommonwealth Court of Pennsylvania
DecidedJanuary 9, 2015
StatusPublished
Cited by2 cases

This text of 108 A.3d 175 (Perrotto Builders, Ltd. v. Reading School District) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perrotto Builders, Ltd. v. Reading School District, 108 A.3d 175, 2015 Pa. Commw. LEXIS 23 (Pa. Ct. App. 2015).

Opinion

OPINION BY

Judge LEAVITT.

Perrotto Builders, Ltd. (Perrotto) appeals the order of the Berks County Court of Common Pleas (trial court) that denied its request for a preliminary injunction to stop the implementation of a construction contract to renovate several school buildings in the Reading School District (School District). Perrotto contends that the School District did not adhere to the terms of its own bidding procedures because it changed the stated basis for awarding the contract after the bids were opened. The trial court refused to grant the preliminary injunction for several reasons. Chief among them was its finding that the School District did, in fact, follow the terms of its bid procedures. The gravamen of the trial court’s decision was that Perrotto was not likely to prevail on the merits of its permanent injunction request and, further, that the grant of the preliminary injunction was more likely to cause harm than the harm that would be caused by its refusal. We affirm.

On October 15, 2013, the School District issued an Invitation to Bid for a “Miscellaneous Building Renovation & Repairs Project.” There were two parts to the project which the School District identified as the “Group A” contract and the “Group B” contract. The Group A contract involved renovations to five elementary schools, two middle schools and one high school. It is this part of the project that generated the instant litigation.

The School District developed a 24-page form and a number of instructional documents for the submission of bids for the Group A contract.1 The submission form required the bidder to provide a separate “base bid” and “alternate bids” for each of the eight schools. The base bid covered the work requested by the School District on a particular school building. The alternate bids were items that the School District could choose to add or deduct from the individual school project after opening the bids. The “total base bid” consisted of the sum of the eight individual bids for the Group A contract. Reproduced Record at 26a (R.R. -). The bidding document also stated that “[the School District] may cho[o]se not to proceed with construction work at one or more of the above locations [177]*177based on the collective value of bids received.” Id.

On December 17, 2013, the School District opened the bids and determined that Perrotto was the lowest bidder based on its total base bid for the Group A contract. However, the combined lowest bids for both the Group A and Group B contracts exceeded by $1.4 million the School District’s budget of approximately $40 million. Accordingly, the School District had to revise the project, and its cost had to be reduced by more than $1.4 million.

John George, the executive director of the Berks County Intermediate Unit and superintendent of record for the School District,2 testified at the preliminary injunction hearing about the School District’s serious financial challenges. He explained that because of the School District’s poor bond rating, it is not likely to be able to issue new bonds for the next seven to ten years. As a result, the School District needed to retain $7 million, out of the $40 million available, as a reserve for essential repairs that were expected to arise over the next seven to ten years. This reserve reduced the amount available for the project to approximately $33 million. George explained that the School District had over $400 million in existing bond debt and $25 million in budgeted debt.

Given these financial challenges, the School District decided to remove the five elementary schools from the Group A contract, which left two middle schools and the high school. It also selected one “deduct” alternate bid. After recalculating the total base bids on the three schools remaining in the project, the School District awarded the Group A contract to Lobar, Inc. as the lowest bidder. Perrot-to’s total base bid on the schools remaining in the project was higher than Lobar’s total base bid by $201,450.

On February 28, 2014, two days after the School District awarded the Group A contract to Lobar, Perrotto filed an injunction action to challenge the School District’s award of the Group A contract to Lobar. It also sought a preliminary injunction to stop any work on the project until its request for a permanent injunction was decided. On March 14, 2014, the trial court conducted a hearing on Perrotto’s request for a preliminary injunction and denied it. Perrotto appealed to this Court.3

Perrotto raises several issues. First, Perrotto contends that the trial court erred in concluding that the bidding documents allowed the School District to remove work from the Project after the bids had been opened. Second, Perrotto argues that the trial court abused its discretion and erred as a matter of law in view[178]*178ing the present case as a disappointed-bidder case and not a taxpayer suit. Third, Perrotto argues that the trial court abused its discretion in balancing the harm by treating it as a financial matter only. Perrotto contends that excusing the School District from rebidding the project results in greater harm because it trivializes the sanctity of the public contracting process. Finally, Perrotto argues, in the alternative, that the trial court erred in finding that the bidding documents were clear and unambiguous!

In response, the School District and Lobar argue that Perrotto lacks taxpayer standing to challenge the award of the Group A contract because it does not own real property in the School District. The School District also argues that Perrotto’s injunction action is barred by laches, noting that Perrotto did not seek to stay the trial court’s decision during the appeal. The School District filed a motion to dismiss Perrotto’s appeal, arguing that it is moot because the project is nearly completed.4 Both appellees contend the trial court did not err in any respect.

We begin with a summary of the requirements for the issuance of a preliminary injunction. First, the injunction must be necessary to prevent immediate and irreparable harm. Second, greater injury would result from not granting the injunction and the grant of an injunction must not substantially harm an interested party. Third, the injunction will restore the parties to the status quo ante, ie., their position before the alleged wrongful conduct. Fourth, the moving party must be likely to prevail on the merits. Fifth, the injunction must be reasonably suited to stop the harm. Finally, the moving party must prove that the injunction would not adversely affect the public interest. Summit Towne Centre, Inc. v. Shoe Show of Rocky Mount, Inc., 573 Pa. 637, 828 A.2d 995, 1001 (2003). Failure to satisfy any one of these requirements bars the preliminary injunction, making it unnecessary for the court to address the other injunction requirements. Id.

A school district’s construction project is subject to competitive bidding and must be awarded to the lowest responsive and responsible bidder. Section 751(a.2) of the Public School Code of 1949, Act of March 10, 1949, P.L. 30, as amended, added by the Act of June 30, 2012, P.L. 684, 24 P.S. § 7-751(a.2).5 The purpose of [179]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
108 A.3d 175, 2015 Pa. Commw. LEXIS 23, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perrotto-builders-ltd-v-reading-school-district-pacommwct-2015.