Perkinson v. City of St. Louis

4 Mo. App. 322, 1877 Mo. App. LEXIS 93
CourtMissouri Court of Appeals
DecidedJuly 3, 1877
StatusPublished
Cited by1 cases

This text of 4 Mo. App. 322 (Perkinson v. City of St. Louis) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perkinson v. City of St. Louis, 4 Mo. App. 322, 1877 Mo. App. LEXIS 93 (Mo. Ct. App. 1877).

Opinion

Baeewell, J.,

delivered the opinion of the court.

This is an action upon a special contract for grading and macadamizing Grand Avenue from Chouteau Avenue to the Gravois Eoad, in St. Louis. The petition alleges that on June 13, 1866, the plaintiff made an agreement in writing with the defendant, signed and sealed by plaintiff and subscribed by defendant, acting therein by and through Truman J. ITorner, its city engineer, duly authorized for that purpose, whereby plaintiff agreed to grade and macadamize Grand Avenue from Chouteau Avenue to the Gravois Eoad, or so much thereof as may be ordered, strictly in accordance with the directions of the city engineer, and under his supervision and control, the work to be done in a certain specified manner, fully set out in the petition; that defendant, by said agreement, was to pay plaintiff 33 cents per cubic yard and $6.40 per square of 100 cubic feet for macadamizing, the grading to be paid for as the work progresses, at the discretion of the city engineer, by warrants of the city auditor drawn on the city treasury, payable out of the funds available for the improvement of streets and alleys, and the macadamizing to be paid for by special [323]*323tax bills against adjacent property; that the contract was approved by the city counsellor, and by the board of delegates and the board of aldermen, whereupon it became obligatory and binding upon the parties thereto; that afterwards, in 1866, plaintiff was ordered by defendant to proceed to do all the work embraced in the contract, and in pursuance of this order, and the contract, he began the work, and continued the same until stopped by defendant without any legal excuse or ground for stopping him ; that at such time plaintiff had performed 290,047 cubic yards of grading, and that there was then remaining to be done of said grading, in order to the completion of the same, 145,000 cubic yards, and that there was then remaining to be done of said macadamizing, in order to the completion of the same, 3,000 squares; that at the prices stipulated plaintiff would have realized a large profit upon the said grading and macadamizing so remaining to .be done, if the defendant had permitted him to do the same in pursuance of the agreement; that at the time of the refusal there were in the street and alley fund of defendant’s treasury funds available for the grading work embraced in said agreement, and that there have since been sufficient funds in the fund of said treasury, available for said grading work, to have fully paid for their completion. Plaintiff says that defendant has paid him on account of said grading work the sum of $6,425, and there was due him on the-day of-, 18 — , the balance of $3,150.17 on account of said grading work done as aforesaid; that said sum was on that day demanded of the defendant, but no part thereof has been paid. Plaintiff says that he has been damaged, by being prevented from performing his contract, in the sum of' $10,250, for which and for said balance, with interest, thereon and costs of suit, he prays judgment.

Plaintiff, for another further cause of action, says that, from the-day of-, 186 — , to the-day of-,. 186 — , he, at the instance and request of defendant, and [324]*324under tbe order and direction of its then city engineer, did 500 cubic yards of grading on -, between tbe Pacific Railroad and Mill Creek sewer, which was reasonably worth the sum of 33 cents per cubic yard, whereby defendant became indebted to plaintiff in the sum of $165, for which, with interest and costs, he asks judgment.

Defendant demurred to the first count of the petition, on the ground that it improperly united a claim for a balance due on contract with a claim for damages for breach of contract. To the second count defendant demurred on the ground that it did not set forth facts sufficient to constitute a cause of action. The demurrer was overruled as to the first count, and sustained as to the-second count.

The answer admits the making of the contract as alleged, and says that the contract contained these conditions, not set out in the petition :

“And it is hereby distinctly understood and agreed that the city engineer shall have the right to suspend this contract, or annul the same, whenever the appropriations made therefor by ordinance are either exhausted or unavailable.
“ This contract is entered into subject to the provisions of the existing ordinances of the city, and to the express power of the city engineer to suspend or annul said contract for any failure on the part of the contractor to fulfil or comply with same. Should the work be suspended or annulled by the city engineer, it shall not entitle the contractor to any damages on account thereof.”

The defendant also says that by ordinance No. 5740 the sum of $3,000 was appropriated for the work in question, and by ordinance No. 8825 the further sum of $3,500 was so appropriated, and that no other or further appropriations for the same have ever been made; that up to July 24, 1867, plaintiff had done grading under said contract amounting, at the rates stipulated in said contract, to the sum of $6,494.34, which exhausted the appropriation for said work, with the exception of $5.66, and that there was duly paid [325]*325to the plaintiff by defendant, at the time, $6,425, leaving a balance of $69.34 due plaintiff, which was duly tendered ; that due notice that the fund was exhausted, and that the work was suspended for that reason, was given to plaintiff. The answer denies that there were funds for said work in the city treasury, except as stated in the answer, and says that there have been no funds since in the treasury for that purpose; and says that plaintiff was entitled to do only so much of said work as he was ordered to do, and that he was ordered to do no more work than that set out in the answer, and that when that was completed he was directed to stop, the contract annulled, and the work suspended. The new matter in the answer was put in issue by the reply.

On the trial the contract was introduced, and it contains the conditions set out in the petition and answer, and provides that “ the city engineer, under the provisions of ordinances Nos. 5740 and 5825, and by virtue of authority in him vested by general ordinances of the city, did let unto the said Henry Perldnson the grading and macadamizing of Grand Avenue from Chouteau Avenue to Gravois Road, and that the said Perldnson agreed to do such work, or so much thereof as may be ordered, strictly in accordance with the directions of the city engineer, and under his supervision and control,” etc.

Plaintiff introduced the following ordinances of the city: Nos. 5740 and 5825, approved January 27 and March 20, 1866, respectively, and which appropriate, together, the sum of $6,500 for the work in question, and authorize the city engineer to cause Grand Avenue to be graded from Chouteau Avenue to the Gravois Road, and a carriage-way of thirty feet to be macadamized; No. 6141, approved March 29, 1867, appropriating $1,500 for grading Grand Avenue from Lafayette to Pontiac, which is part of the work described in the contract; No. 7809, approved July 12, 1871, appropriating $1,500 for grading Grand Avenue [326]*326from Lafayette to Park Avenue, which is part of the contract work; No. 8593, approved July 16, 1873, for grading from Yista to Chouteau Avenue, part of the contract work; and ordinances Nos. 5839 and 6450, approved April 14, 1866, and March 16, 1868, which, amongst other things, appropriate $90,000 to grading streets and alleys.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gibson v. Zimmerman
27 Mo. App. 90 (Missouri Court of Appeals, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
4 Mo. App. 322, 1877 Mo. App. LEXIS 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perkinson-v-city-of-st-louis-moctapp-1877.