Perkins v. RMR Building Group

CourtNebraska Court of Appeals
DecidedApril 1, 2025
DocketA-23-947
StatusUnpublished

This text of Perkins v. RMR Building Group (Perkins v. RMR Building Group) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perkins v. RMR Building Group, (Neb. Ct. App. 2025).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

PERKINS V. RMR BUILDING GROUP

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

PERKINS, L.L.C., ET AL., APPELLANTS, V.

RMR BUILDING GROUP, LLC, AND ROBERT M. RYAN II, APPELLEES.

Filed April 1, 2025. No. A-23-947.

Appeal from the District Court for Douglas County: JEFFREY J. LUX, Judge. Reversed and remanded with directions. Steven G. Ranum and Josiah J. Shanks, of Croker, Huck, Kasher, DeWitt, Anderson & Gonderinger, L.L.C., and Robert F. Bartle, of Bartle & Geier, for appellants. Michael J. Mullen for appellees.

PIRTLE, BISHOP, and ARTERBURN, Judges. BISHOP, Judge. I. INTRODUCTION Michael Perkins is the sole owner of Perkins, L.L.C., and MHP Development, LLC, both of which are Nebraska limited liability companies. He also owns Perkins Properties, Inc., a Nebraska corporation. We will refer to Perkins and his business entities individually and collectively as “Perkins.” Robert M. Ryan II is the owner and sole member of RMR Building Group, LLC (RMR), a Nebraska limited liability company. Perkins hired RMR to work on a commercial construction project in Omaha, Nebraska. A dispute arose when RMR failed to pay one of its subcontractors, Xtreme Heating and Cooling, LLC (Xtreme), for HVAC units, even though Perkins paid RMR’s invoice that included Xtreme’s charges for those units. Perkins filed suit against RMR and Ryan for breach of contract, money had and received, unjust enrichment, conversion, fraudulent inducement, and “Piercing Corporate Veil”; Perkins sought a judgment

-1- against both defendants, jointly and severally. Following a bench trial, the Douglas County District Court entered a judgment against RMR for $549,916.58, plus prejudgment interest and costs. The district court declined to hold Ryan personally liable. Perkins appeals. Because the evidence supports piercing the limited liability company’s veil, we reverse and remand the case to the district court with directions to enter its judgment in favor of Perkins against RMR and Ryan jointly and severally. II. BACKGROUND 1. FACTS LEADING TO LAWSUIT Perkins, “[p]rimarily a developer,” who has worked in real estate for approximately 50 years, hired RMR to work on a shopping center construction project in Omaha. The parties entered into a cost-plus arrangement, in which RMR agreed to complete the project for its costs plus an overhead and profit charge of 4.5 percent. Under the arrangement, RMR sent Perkins invoices for the project’s costs and added the 4.5 percent overhead and profit charge. Upon Perkins paying the invoice, RMR was responsible for paying its subcontractors and suppliers. A written contract, dated June 7, 2021, was prepared for the first phase of construction, and a later written “Prime Contract Change Order #001,” dated August 13, 2021, was prepared for “Phase 2.” The change order reflected the “original” contract sum of $3,026,005. With the change order amount of $2,324,660, the new “contract sum” was $5,350,665. David Critser, RMR’s vice president of construction, was identified as the “Contractor’s representative” in the initial contract, as well as on the signature line for RMR. The parties did not produce a signed version of either contract, but they did not dispute the basic terms of their agreement and unsigned copies of the documents were received at trial. On January 21, 2022, during the second phase of construction, RMR submitted two invoices to Perkins: one for $669,757.08 and another for $39,876.08. The itemization contained in the $669,757.08 invoice reflected a charge of $526,236 for “HVAC Equipment-Xtreme HVAC Invoice 2173,” dated December 27, 2021. On that date, Xtreme had sent RMR an invoice for $526,236, a copy of which was provided to Perkins. The charge was for HVAC units needed for the construction project and Xtreme would not release the HVAC units until payment was made. Perkins wrote RMR a check for $709,633.16 on February 17, 2022, satisfying both invoices. Perkins’ check was deposited by RMR into its general operating bank account on February 22. Perkins learned from Critser that “[s]hortly after [Perkins] made the payment on the check to RMR” that the Xtreme invoice was not paid. Perkins “immediately” contacted an attorney, who then sent a letter to RMR (addressed to Ryan) on March 10, 2022. That letter indicated that it had come to their attention that Xtreme’s $526,236 invoice had not been paid by RMR and that “RMR may have used the funds paid by [Perkins] to pay expenses unrelated to the above referenced project.” Perkins demanded proof of payment to Xtreme and a construction lien waiver or, in the alternative, reimbursement of amounts paid by Perkins on the invoice. By the middle of March, Perkins had his “doubts” that RMR was going to finish the project and pay Xtreme “[b]ecause nobody had responded to any of the communication that . . . counsel had sent out,” and Perkins had left several messages and voicemails for which he received no response. On March 25, another letter was sent from Perkins’ attorney to RMR indicating they had received no response to the previous letter and noting that the Xtreme invoice remained unpaid. The letter also stated that

-2- Perkins was aware that RMR “has abandoned work on the Projects” and “has no intent or ability to complete the Projects.” As a result, Perkins terminated the contracts and directed RMR to cease work on the projects and to not enter job sites. This left Perkins “hanging,” so he “assessed the situation” and “decided to continue on with the people who had been working on the job and continue with where it was at and form a construction company.” And because he was “under a time guideline” to finish the project, Perkins was “forced” to form a construction company in March 2022 called Perkins & Critser Construction, LLC (Perkins & Critser). Perkins owned 90 percent of the company and Critser owned 10 percent. On May 17, 2022, Perkins issued a check to Perkins & Critser for $526,236, who then paid the Xtreme invoice from December 27, 2021, to obtain the HVAC units necessary to move forward with the project. As a result, Perkins effectively paid the same invoice twice: once when paying the RMR invoice and again when Perkins & Critser took over the project. 2. PLEADINGS Perkins filed a complaint against RMR and Ryan on April 29, 2022, alleging breach of contract, money had and received, unjust enrichment, conversion, fraudulent inducement, and “Piercing Corporate Veil.” Perkins sought to hold Ryan jointly and severally liable with RMR. Perkins filed a motion for default judgment on July 5, requesting the district court to enter a judgment against RMR on the grounds that RMR failed to answer the complaint in a timely manner. RMR filed an answer and counterclaim on August 8, and the court subsequently granted RMR leave to file its answer out of time. RMR’s counterclaim was dismissed without prejudice on August 22. 3. TRIAL Trial took place on September 18, 2023. In addition to the facts set forth above, the evidence at trial revealed the following. Perkins testified that in his 50 years of experience in the real estate industry, he had worked extensively with contractors, many of whom he hired under a cost-plus arrangement. Perkins explained that when he pays a contractor on a cost-plus basis, he expects the contractor to use those funds to pay the subcontractors and suppliers who are owed money on the project. He “assumed every sub on there and every expense was going to be paid,” and that is “normal in the industry.” Perkins put his “[c]omplete trust” in RMR to handle his funds in this manner and he never gave RMR or Ryan permission to use his funds to pay creditors on other projects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Workman v. Workman
118 N.W.2d 764 (Nebraska Supreme Court, 1962)
Gifford-Hill & Co., Inc. v. Stoller
380 N.W.2d 625 (Nebraska Supreme Court, 1986)
Christian v. Smith
759 N.W.2d 447 (Nebraska Supreme Court, 2008)
J. L. Brock Builders, Inc. v. Dahlbeck
391 N.W.2d 110 (Nebraska Supreme Court, 1986)
Huffman v. Poore
569 N.W.2d 549 (Nebraska Court of Appeals, 1997)
Moss v. Associated Underwriters
28 Neb. Ct. App. 739 (Nebraska Court of Appeals, 2020)
407 N 117 Street v. Harper
993 N.W.2d 462 (Nebraska Supreme Court, 2023)
Tegra Corp. v. Boeshart
317 Neb. 100 (Nebraska Supreme Court, 2024)
Ronnfeldt Farms v. Arp
317 Neb. 690 (Nebraska Supreme Court, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
Perkins v. RMR Building Group, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perkins-v-rmr-building-group-nebctapp-2025.