Johnson Creek in Whiteside county,, at the place here in question, runs in a southwesterly direction and passes through the farm of Joseph Perido, the appellee. Originally somewhat crooked, the bed of the stream has been straightened and deepened by a drainage district. The drainage district built levees of earth on each side of the new channel, and there were box culverts and iron culverts at places to allow water from the adjacent lands to pass into the creek, and these sluiceways were protected by gates to prevent water passing from the creek upon the lands. About a mile or a mile and a quarter below appellee’s farm, the Fenton & Thompson Eailroad Company built an embankment and laid thereon its railroad tracks across the valley drained by this creek and by Otter creek, just south of this, and built a bridge over Johnson Creek. It was supported by eight rows of four wooden piles each, and the piles were twelve to eighteen inches in diameter, and said rows were about fourteen or fifteen feet apart. The rows were at right angles to the railroad track and at an angle of 42 degrees to the stream, ánd there was proof that a person standing ten or fifteen rods up stream in the middle of the creek could not see through underneath the bridge, but the piles proved practically a solid obstruction to his vision. On December 30, 1906, after the ordinary water in the creek had been frozen over, there was a heavy rain and flood, and there was an ice gorge in Johnson Creek which dammed the water back so high at appellee’s farm that it swept away the dike on the southeast side and flooded a large portion of his farm, and the waters left the bed of the creek and flowed across his land. Johnson Creek came from sand hills some miles above. The flood carried large quantities of sand upon portions of appellee’s farm, and made the rest of it so wet and swampy that, according to appellee’s proof, it was unfit for cultivation the next year. Appellee’s proof was that between twenty-eight and twenty-nine acres of the farm were covered with sand to a depth of from eight and a half inches to twenty-four inches. On March 1, 1906, preceding this overflow, the Chicago, Burlington & Quincy Bailroad Company, appellant, purchased the railroad of the Fenton & Thompson Bail-road Company and thereafter operated the same. Appellee brought this action against appellant to recover damages for the injury to his land occasioned by said overflow, charging that the manner in which the wooden piles were set and maintained across the stream caused the forming of this ice gorge and the consequent injury to his land. Appellee had a verdict for $1,610.82. The court below denied a motion by appellant for a new trial, and gave appellee a judgment on the verdict, from which defendant below appeals.

It is contended that the court below erred in sustaining objections to questions put by appellant to certain experts, with reference to the formula recognized among engineers for the capacity of bridges, and whether this bridge afforded an adequate outlet for the waters of the territory drained by Johnson Creek. It was not stated as a cause of action in appellee’s declaration, nor did appellee seek to prove, that the bridge was insufficient to allow the waters to pass through but the alleged cause of action was the setting of the rows of piles at an angle of 42 degrees with the course of the creek and thereby obstructing the flow of ice and debris down the stream and causing an ice gorge and a consequent flood over appellee’s lands. The inquiry whether the bridge was recognized by engineers as sufficient to carry the waters of the valley was therefore immaterial.

The trial court permitted both parties to show the conditions existing on December 30, 1906, and for a few days thereafter, immediately below the bridge, but confined that inquiry to the immediate vicinity of the bridge. The dike broke and was swept away and appellee’s farm was flooded about four o’clock in the afternoon of December 30. Appellant introduced evidence tending to show that there was no ice at the railroad bridge at that time, but that the gorge of ice was then formed some distance above the bridge, and that at four o’clock that afternoon at the railroad bridge the water was flowing northeast up stream. Appellant then sought to introduce a plat of all the surrounding country, showing that Otter Creek and Johnson Creek joined about a quarter of a mile below this railroad bridge, and that the joint stream was crossed a little further down by a highway bridge and still further down by railroad bridges of the Chicago, Milwaukee & St. Paul Railroad and of another line of appellant. Appellant then inquired of witnesses what caused the water to run northeast up stream at the bridge in question. The trial court refused to admit that part of the plat which showed the union of Johnson and Otter Creeks, and the highway and railroad bridges below, and required that part of the plat to be cut out before admitting the rest of the plat in evidence, and refused to admit proof of what caused the water at the bridge to flow up stream.

Free access — add to your briefcase to read the full text and ask questions with AI

Perido v. Chicago, Burlington & Quincy Railroad, 144 Ill. App. 446, 1908 Ill. App. LEXIS 488 (Ill. Ct. App. 1908).

144 Ill. App. 446 (Perido v. Chicago, Burlington & Quincy Railroad) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ohio & Mississippi Railway Co. v. Thillman
32 N.E. 529 (Illinois Supreme Court, 1892)