Peri Formwork Systems, Inc. v. Lumbermens Mutual Casualty Co.

112 A.D.3d 171, 975 N.Y.S.2d 422

This text of 112 A.D.3d 171 (Peri Formwork Systems, Inc. v. Lumbermens Mutual Casualty Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peri Formwork Systems, Inc. v. Lumbermens Mutual Casualty Co., 112 A.D.3d 171, 975 N.Y.S.2d 422 (N.Y. Ct. App. 2013).

Opinion

OPINION OF THE COURT

Chambers, J.

During a nonjury trial in this action, the plaintiff argued [173]*173that, under the doctrine of law of the case, it was not required to prove the amount it was owed on its mechanic’s liens because this Court had previously determined that issue on a prior appeal (see Peri Formwork Sys., Inc. v Lumbermens Mut. Cas. Co., 65 AD3d 533 [2009]). After the trial, the Supreme Court adopted the plaintiffs argument. This was error because this Court did not resolve that issue on the prior appeal. Since the plaintiff failed to carry its burden of proving the amount it was owed on its mechanic’s liens, it was not entitled to recover on the subject bonds filed to discharge the liens. In addressing the issues raised on this appeal, we take the opportunity to review the statutory requirements for recovery under the Lien Law, and the limits on recovery imposed by the principle of subrogation.

The defendants LC White Plains, LLC (hereinafter LC White Plains) and Cappelli Enterprises, Inc. (hereinafter Cappelli, and hereinafter together the owners) owned the White Plains City Center (hereinafter the property). The owners contracted with the defendant George A. Fuller Company (hereinafter the general contractor) to construct several buildings in multiple phases at the property. The general contractor hired Rogers & Sons Concrete, Inc., as a concrete subcontractor (hereinafter the concrete subcontractor), who, in turn, hired the plaintiff, a sub-subcontractor, to provide formwork and related supplies and services. The concrete subcontractor and the plaintiff entered into a rental agreement pursuant to which the plaintiff agreed to supply certain materials at a rental rate of 5% of list value per 28-day period.

On March 19, 2004, the plaintiff filed a mechanic’s lien in the sum of $423,055.97. On March 31, 2004, the defendant Arch Insurance Company (hereinafter Arch) posted a surety bond in the sum of $466,296.57, discharging the lien. A second lien was filed on November 4, 2004, in the sum of $57,966.89. On September 26, 2005, Cappelli and Arch posted a lien discharge bond in the sum of $63,763.58.

The plaintiff then commenced this consolidated action against, among others, the owners, the general contractor, and Arch, inter alia, to recover on the bonds. At the completion of discovery, the plaintiff moved for summary judgment on the claims to recover on the bonds. In an order entered March 26, 2008, the Supreme Court, inter alia, granted that branch of the plaintiffs motion, stating:

“The Court finds that [the plaintiff] has established its entitlement to summary judgment as to the Arch [174]*174surety lien bonds filed with respect to the amounts alleged to be due under the [concrete subcontractor’s] contracts; defendants have raised no genuine issues of fact with respect thereto. Accordingly, [the plaintiff] is granted summary judgment with respect to [the] Arch surety bonds.”

The plaintiff appealed from that order, and the owners, the general contractor, and Arch cross-appealed from the order. This Court modified the order by denying that branch of the plaintiff’s motion which was for summary judgment on its claims to recover on the two bonds filed to discharge its mechanic’s liens (see id. at 534). In the body of the decision and order, this Court explained that the plaintiffs

“liens were valid only as to any amount still due and unpaid to the [concrete] subcontractor. Since a triable issue of fact exists as to whether the [concrete] subcontractor was owed any money and, if so, the amount, at the time the plaintiff’s liens were filed, the plaintiff was not entitled to summary judgment” {id. at 535 [citations omitted]).

The action proceeded to a nonjury trial, where counsel for the plaintiff continually asserted that he did not need to prove the amount the plaintiff was owed on its mechanic’s liens. At the outset of trial, counsel for the plaintiff maintained that this Court’s prior decision and order limited the issue presented to determining “the amount of money that was due and owing from [the owners and the general contractor] to [the concrete] subcontractor ... at the time of the filing of the mechanic’s lien or thereafter.” Later, during cross-examination of the president of the concrete subcontractor, counsel for the plaintiff objected to a line of inquiry regarding the amount of the liens, asserting that the liens had already been found valid by this Court, and reiterating his position that the issue at trial was limited to “the amounts still due to the [concrete] subcontractor.” Counsel’s objection was overruled. During the trial, evidence was produced showing that the general contractor owed money to the concrete subcontractor as of March 19, 2004, when the first lien was filed, and that the general contractor paid the concrete subcontractor approximately $2.7 million after the liens were filed.

On June 4, 2010, the plaintiff moved pursuant to Lien Law § 19 (4) (d) and CPLR 2508 to require the owners to post an additional undertaking in the sum of $308,465.43 to bond the [175]*175mechanic’s liens, claiming that the interest on the liens exceeded the amount of the bonds by that amount. In an order entered October 19, 2010, the Supreme Court denied the motion.

In a decision entered December 14, 2010, the Supreme Court directed dismissal of the complaint insofar as asserted against LC White Plains and the general contractor, and found that the plaintiff was entitled to judgment against Arch and Cappelli in the principal sum of $530,060.15, the total sum of the bonds. The court noted that, since there was no privity between the owners and the plaintiff, the measure of the plaintiffs liens was the value of the labor and material added to the property, rather than the contract price. The court further stated:

“Be that as it may, as indicated above, Defendants challenged the validity of the liens when they moved for summary judgment before Justice Rudolph. Whether they challenged them as exceeding the reasonable value of the materials furnished does not appear. In any event, Justice Rudolph held them valid as to the amounts claimed therein and that holding was affirmed on appeal. It is therefore law of the case.”

On May 31, 2011, the Supreme Court entered judgment in favor of the plaintiff and against Arch and Cappelli in the principal sum of $530,060.15.

Lien Law § 3 provides, inter alia, that a “subcontractor [or] materialman . . . who performs labor or furnishes materials for the improvement of real property . . . shall have a lien for the principal and interest, of the value, or the agreed price, of such labor ... or materials upon the real property improved or to be improved.” In other words, a lienor is required to prove the debt it is owed, which requires proof of either the price of its contract or the value of the materials supplied to the project (see 76A NY Jur 2d, Mechanics’ Liens § 24 [“A subcontractor is allowed to claim to the extent of (his or her) debt”]). As explained in two leading New York treatises on mechanic’s liens,

“[t]he amount of a mechanic’s lien is limited by the contract under which it is claimed; the lienor should ordinarily be bound by the price term contained in the contract to which lienor is a party . . . Typically, the ‘value’ measure would be resorted to if there were no ‘agreed price.’ In an appropriate case, [176]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Evans
727 N.E.2d 1232 (New York Court of Appeals, 2000)
Heckmann v. . Pinkney
81 N.Y. 211 (New York Court of Appeals, 1880)
In re Aho
347 N.E.2d 647 (New York Court of Appeals, 1976)
Metropolitan Steel Industries, Inc. v. Perini Corp.
36 A.D.3d 568 (Appellate Division of the Supreme Court of New York, 2007)
Allison v. Allison
60 A.D.3d 711 (Appellate Division of the Supreme Court of New York, 2009)
Peri Formwork Systems, Inc. v. Lumbermens Mutual Casualty Co.
65 A.D.3d 533 (Appellate Division of the Supreme Court of New York, 2009)
Frackson v. Brown & Williamson Tobacco Corp.
67 A.D.3d 213 (Appellate Division of the Supreme Court of New York, 2009)
Erickson v. Cross Ready Mix, Inc.
98 A.D.3d 717 (Appellate Division of the Supreme Court of New York, 2012)
Timothy Coffey Nursery/Landscape, Inc. v. Gatz
304 A.D.2d 652 (Appellate Division of the Supreme Court of New York, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
112 A.D.3d 171, 975 N.Y.S.2d 422, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peri-formwork-systems-inc-v-lumbermens-mutual-casualty-co-nyappdiv-2013.