Perez-Gurri Corp. v. McLeod

238 So. 3d 347
District Court of Appeal of Florida·Decided November 22, 2017·No. 15-2590 & 17-1478·Published·Cited by 21 cases

Opinion

Third District Court of Appeal State of Florida

Opinion filed November 22, 2017.

Not final until disposition of timely filed motion for rehearing.

Nos. 3D15-2590 & 3D17-1478 Lower Tribunal No. 13-30482

Perez-Gurri Corporation, etc., Appellant,

vs.

Don McLeod, et al.,

Appellees.

Appeals from the Circuit Court for Miami-Dade County, Bronwyn C.

Miller, Judge.

GPG Law, and Christopher J. Perez-Gurri (Fort Lauderdale); Samson Appellate Law, and Daniel M. Samson, for appellant.

Quintairos, Prieto, Wood & Boyer, P.A., and Thomas A. Valdez and Karen M. Shimonsky (Tampa), for appellee M2G2 Architects, LLC.

Before LOGUE, SCALES, and LUCK, JJ.

LOGUE, J.

Perez-Gurri Corporation (the General Contractor) appeals a trial court order dismissing its professional malpractice action and entering summary judgment in favor of M2G2 Architects, LLC. Because an issue of material fact remains as to whether M2G2 Architects provided services for a construction project the General Contractor undertook with the City of Miami, and because the General Contractor’s claim against M2G2 Architects was not contractually barred, we reverse.

The General Contractor is a Florida construction company that successfully bid on, and became the general contractor for, a City of Miami renovation project for the Caribbean Marketplace in Little Haiti. The City’s prime consultant on the project subcontracted with Don McLeod and McLeod Architectural Group to prepare design documents for the renovation. In May 2013, Don McLeod established a new firm, M2G2 Architects, LLC. When construction on the renovation project was delayed, the General Contractor brought an action against multiple architects, engineers, and consultants, including M2G2 Architects.

The General Contractor alleged in its fourth amended complaint that M2G2 Architects committed professional malpractice that delayed the construction. M2G2 Architects moved for summary judgment on the basis that it played no role in the project. It also argued that the General Contractor’s claim against it was

contractually barred by a “No Damages for Delay” clause in the contract between the General Contractor and the City of Miami.

The trial court granted M2G2 Architects’ motion for summary judgment. It found that “the record evidence conclusively establishes that no services were rendered by M2G2 in conjunction with the project.” And it further concluded that even if M2G2 Architects played a role in the project, its principal, Don McLeod, was the architect of record and a representative of the City, and the no delay damages clause precluded any claim for delay damages against the City and its representatives. This appeal followed.

We reverse the trial court’s entry of summary judgment entered in favor of M2G2 Architects for two reasons. First, an issue of material fact remains as to whether M2G2 Architects was involved in the renovation project. And second, the contract between the General Contractor and the City does not insulate M2G2 Architects from liability.

Summary judgment “is designed to test the sufficiency of the evidence to determine if there is sufficient evidence at issue to justify a trial or formal hearing on the issues raised in the pleadings.” The Fla. Bar v. Greene, 926 So. 2d 1195, 1200 (Fla. 2006). “A party should not be put to the expense of going through a trial, where the only possible result will be a directed verdict.” Perez-Rios v. Graham Companies, 183 So. 3d 478, 479 (Fla. 3d DCA 2016) (quoting Martin

Petroleum Corp. v. Amerada Hess Corp., 769 So. 2d 1105, 1108 (Fla. 4th DCA 2000)). Because summary judgment tests the sufficiency of the evidence to justify a trial, it “is proper only if, taking the evidence and inferences in the light most favorable to the non-moving party, and assuming the jury would resolve all such factual disputes and inferences favorably to the non-moving party, the non-moving party still could not prevail at trial as a matter of law.” Moradiellos v. Gerelco Traffic Controls, Inc., 176 So. 3d 329, 334-35 (Fla. 3d DCA 2015). “At both the trial and appellate level, all evidence and inferences from the evidence must be taken in the light most favorable to the non-moving party.” Id. at 334. This court reviews de novo a trial court’s ruling on a motion for summary judgment. Volusia Cty. v. Aberdeen at Ormond Beach, L.P., 760 So. 2d 126, 130 (Fla. 2000).

Here there remains a genuine issue of material fact as to whether M2G2 Architects rendered services on the renovation project. While there may be evidence that M2G2 Architects did not provide services on the project, there is also ample record evidence that it did. Among this evidence is a January 23, 2014 email from Don McLeod, advising that his company McLeod Architectural Group was no longer in business, and stating, “[a]ll services provided related to the Caribbean Marketplace since mid-summer have been through M2G2 Architects LLC.” M2G2 Architects also demanded payment for services rendered on the project from July 15, 2013, through December 30, 2013. And a January 29, 2014

email from another principal of M2G2 Architects to the City demanded payment and stated that M2G2 Architects had been providing services on the project since July 2013. Further, M2G2 Architects’ website indicated that it was “honored to have played a role in ensuring that this iconic community venue [the Caribbean Marketplace] is functioning again.” A jury or factfinder could reasonably infer from these statements by M2G2 Architects or its principals that services to the project were provided by M2G2 Architects.

M2G2 Architects, however, contends the deposition testimony of its principals—who provided an explanation for those communications—is so persuasive as to conclusively establish that M2G2 Architects was not involved in the project at issue. But a motion for summary judgment is not a trial by affidavit or deposition. Summary judgment is not intended to weigh and resolve genuine issues of material fact, but only identify whether such issues exist. If there is disputed evidence on a material issue of fact, summary judgment must be denied and the issue submitted to the trier of fact. Here, the documentary evidence, viewed in the light most favorable to the General Contractor, indicates at a minimum that there remains a disputed issue of material fact as to whether M2G2 Architects rendered services on the project.

Turning to the question of whether the no delay damages provision bars the General Contractor’s claim against M2G2 Architects, we review the trial court’s

interpretation of the contract de novo. Charbonier Food Servs., LLC v. 121 Alhambra Tower, LLC, 206 So. 3d 755, 758 (Fla. 3d DCA 2016). “When interpreting a contract, the court must first examine the plain language of the contract for evidence of the parties’ intent.” Murley v. Wiedamann, 25 So. 3d 27, 29 (Fla. 2d DCA 2009). A single term or group of words must not be read in isolation. American K-9 Detection Servs., Inc. v. Cicero, 100 So. 3d 236, 238-39 (Fla. 5th DCA 2012). “Rather, ‘the goal is to arrive at a reasonable interpretation of the text of the entire agreement to accomplish its stated meaning and purpose.’” Id. (quoting Ware Else, Inc. v. Ofstein, 856 So. 2d 1079, 1081 (Fla. 5th DCA 2005)). “[W]e are constrained by law to construe a contract as a whole so as to give effect, as here, to all provisions of the agreement if it can be reasonably done.” McArthur v. A.A. Green & Co. of Fla., 637 So. 2d 311, 312 (Fla. 3d DCA 1994).

We agree with the trial court that the contract between the City and the General Contractor expressly provides that the General Contractor waived its right to seek delay damages. But the question is whether the parties contracted to have this waiver extend only to the City or to other parties such as M2G2 Architects. We conclude that the contract, read in its entirety, waives delay damages only against the City and not against other parties like M2G2 Architects.

Free access — add to your briefcase to read the full text and ask questions with AI

Perez-Gurri Corp. v. McLeod, 238 So. 3d 347 (Fla. Ct. App. 2017).

238 So. 3d 347 (Perez-Gurri Corp. v. McLeod) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Grace & Naeem Uddin Inc. v. Miami-Dade County
District Court of Appeal of Florida, 2026
Saleena Mia Bernard v. Bookxchange, LLC
District Court of Appeal of Florida, 2025
Citizens Property Insurance Corporation v. Ramon Arias
District Court of Appeal of Florida, 2024
TBC FLORIDA, LLC v. INFINITY BISCAYNE MYRTLE MEMBER, LLC
District Court of Appeal of Florida, 2023
ERIC DICKSTEIN AND OWEN TREPANIER v. RICHARD C. WALKER
District Court of Appeal of Florida, 2023
BPI SPORTS, LLC, etc. v. FLORIDA SUPPLEMENT LLC, etc.
District Court of Appeal of Florida, 2022
RICHARD CLEVELAND v. WESTPORT RECOVERY CORPORATION
District Court of Appeal of Florida, 2021
CARLOS VEGA v. SAFEPOINT INSURANCE COMPANY
District Court of Appeal of Florida, 2021
FALLANG FAMILY LIMITED PARTNERSHIP v. PRIVCAP COMPANIES LLC
District Court of Appeal of Florida, 2021
Cascar, LLC v. City of Coral Gables
274 So. 3d 1231 (District Court of Appeal of Florida, 2019)
All Seasons Condo Assoc. v. Patrician Hotel
274 So. 3d 438 (District Court of Appeal of Florida, 2019)
Keys Country Resort v. 1733 Overseas Highway
272 So. 3d 500 (District Court of Appeal of Florida, 2019)
Gonzalez v. Citizens Property Ins. Corp.
273 So. 3d 1031 (District Court of Appeal of Florida, 2019)
Shands v. City of Marathon
District Court of Appeal of Florida, 2019
Martinez Sr. v. Taurus International Manufacturing
251 So. 3d 328 (District Court of Appeal of Florida, 2018)