Pepper Lawson Horizon International Group, LLC v. Texas Southern University

CourtTexas Supreme Court
DecidedMay 19, 2023
Docket21-0966
StatusPublished

This text of Pepper Lawson Horizon International Group, LLC v. Texas Southern University (Pepper Lawson Horizon International Group, LLC v. Texas Southern University) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pepper Lawson Horizon International Group, LLC v. Texas Southern University, (Tex. 2023).

Opinion

Supreme Court of Texas ══════════ No. 21-0966 ══════════

Pepper Lawson Horizon International Group, LLC, Petitioner,

v.

Texas Southern University, Respondent

═══════════════════════════════════════ On Petition for Review from the Court of Appeals for the First District of Texas ═══════════════════════════════════════

PER CURIAM

This interlocutory appeal involves the application of a statutory immunity waiver in a suit alleging breach of a contract to construct university housing. See TEX. CIV. PRAC. & REM. CODE § 114.003. The trial court held that the university was not immune from suit, but the court of appeals reversed and rendered judgment dismissing the contract claims for want of subject-matter jurisdiction. We reverse and remand to the trial court. In 2014, Texas Southern University (TSU) executed a contract naming “Pepper-Lawson/Horizon International Group” as the “Contractor” on a project to construct student housing. Representatives of Pepper Lawson Construction and Horizon International Group each signed the contract as part of a joint venture subsequently formed as Pepper Lawson Horizon International Group, LLC (PLH). PLH sued TSU, alleging that, as recounted below, the university defaulted on its payment obligations under the construction contract. The construction contract required substantial project completion by July 1, 2015, and final completion by August 31, 2015, subject to justified time extensions and equitable price adjustments for certain types of delays. See infra note 1. PLH did not complete the project until February 2016. On completion, PLH invoiced TSU for $3,320,605—the remaining “balance due” under the contract, as adjusted by approved change orders—plus $3,677,580 for “additional direct costs” PLH had allegedly incurred due to “excusable delays.” TSU refused to pay the adjusted contract balance because the project was completed 155 days late and a liquidated-penalty clause in the construction contract entitles TSU to deduct $20,000 per day for untimeliness. TSU declined to pay the additional direct costs based on Section 9.7 of the construction contract, which states, “Contractor has no claim for monetary damages for delay or hindrances to the work from any cause, including without limitation any act or omission of [TSU].” After completing a contractually required dispute-resolution process, PLH sued TSU for breach of contract. PLH asserted that (1) TSU failed to grant contractually required extensions of the completion deadline for excusable delays, as provided in contract

2 Sections 9.6.2.2 and 9.6.3;1 (2) the liquidated-penalty clause did not preclude recovery of the amount due under the contract, including the excusable-delay costs, because TSU should have extended the completion deadline, which would have made the February completion date timely; and (3) PLH was not seeking delay damages under contract

1 “Excusable Delay” is defined in Section 9.6.2.2 of the contract: Excusable Delay. Contractor is entitled to an equitable adjustment of the Contract Time, issued via change order, for delays caused by the following: [1] Errors, omissions and imperfections in design . . . [2] Unanticipated physical conditions at the Site, which A/E [Architect/Engineer] corrects by means of changes to the Drawings and Specifications or for which ODR [Owner’s Designated Representative] directs changes in the Work identified in the Contract Documents. [3] Changes in the Work that effect [sic] activities identified in Contractor[’]s schedule as “critical” to completion of the entire Work, if such changes are ordered by ODR or recommended by A/E and ordered by ODR. [4] Suspension of Work for unexpected natural events (sometimes called “acts of God”), civil unrest, strikes or other events which are not within the reasonable control of Contractor. [5] Suspension of Work for convenience of ODR, which prevents Contractor from completing the Work within the Contract Time. As provided in Section 9.6.3 of the contract: Contractor[’]s relief in the event of such delays is the time impact to the critical path as determined by analysis of Contractor[’]s schedule. In the event that Contractor incurs additional direct costs because of the excusable delays other than [Suspension of Work for unexpected natural events (sometimes called ‘acts of God’), civil unrest, strikes or other events which are not within the reasonable control of Contractor] and within the reasonable control of [TSU], the Contract price and Contract Time are to be equitably adjusted by [TSU] pursuant to the provisions of Article 11. (Emphases added.)

3 Section 9.7, but rather, an equitable adjustment of the project-completion deadline and the contract price, as authorized under Section 9.6.3 for excusable delays. PLH alleged that various issues delayed project completion and increased PLH’s costs, including delays caused by TSU or within TSU’s reasonable control. Among other things, PLH discovered that “undisclosed underground obstructions” from a previous building—a pool, basement walls, and piers—remained buried under the worksite. While TSU agreed to a cost increase to remove the obstructions, it denied PLH’s request for additional time to perform the work under contract Sections 9.6.2.2 and 9.6.3. According to PLH, that delay had the added effect of pushing construction into Texas’s “wet season,” which had a record rainfall that further delayed construction. PLH requested a 67-day extension to account for rain days under a contract provision requiring TSU to extend the completion deadline for excusable delays and certain “weather days,”2 but the university only granted a 21-day extension. Finally, PLH alleged that TSU agreed to supply the project with permanent power but missed the agreed deadline by 192 days.

2 Section 9.6.2 of the contract provides for an extension of time on the following terms: “When a delay defined herein as excusable prevents Contractor from completing the Work within the Contract Time, Contractor is entitled to an extension of time. [TSU] will make an equitable adjustment and extend the number of days lost because of excusable delay or Weather Days, as measured by Contractor[’]s progress schedule.” Section 9.6.2.1, in turn, defines a “Weather Day” as “a day on which Contractor[’]s current schedule indicates Work is to be done, and on which inclement weather and related site conditions prevent Contractor from performing seven (7) continuous hours of Work between the hours of 7:00 a.m. and 6:00 p.m. Weather days are excusable delays.”

4 Because of the power delay, PLH requested a commensurate deadline extension under the contract’s excusable-delay provision, but TSU refused to grant any additional time. Along with sums allegedly due and owing under the construction contract, PLH prayed for interest and attorney’s fees under the Texas Prompt Payment Act (PPA) because the construction contract expressly required TSU to comply with that statute3 and because TSU did not pay PLH’s final invoice within the statutorily mandated 30-day period. See TEX. GOV’T CODE § 2251.021(a). TSU generally denied PLH’s allegations and asserted sovereign immunity to suit, among other defenses. Although PLH’s pleadings expressly invoked the immunity waiver in Section 114.003 of the Texas Civil Practice and Remedies Code, TSU filed a plea to the jurisdiction, asserting Section 114.003 was inapplicable because PLH failed to plead a claim covered by the waiver provision. Section 114.003 waives immunity to suit against “[a] state agency that . . . enters into a contract subject to [Chapter 114]” but only “for the purpose of adjudicating a claim for breach of an express provision of the contract” and “subject to [Chapter 114’s] terms and conditions[.]” TEX. CIV. PRAC. & REM. CODE § 114.003. Chapter 114 “applies only to a claim for breach” of certain contracts, including “a written contract for . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Texas Department of Parks & Wildlife v. Miranda
133 S.W.3d 217 (Texas Supreme Court, 2004)
Kirby Lake Development, Ltd. v. Clear Lake City Water Authority
320 S.W.3d 829 (Texas Supreme Court, 2010)
The City of Houston v. Steve Williams
353 S.W.3d 128 (Texas Supreme Court, 2011)
Bland Independent School District v. Blue
34 S.W.3d 547 (Texas Supreme Court, 2000)
Wasson Interests, Ltd. v. City of Jacksonville, Texas
489 S.W.3d 427 (Texas Supreme Court, 2016)
Rusk State Hospital v. Black
392 S.W.3d 88 (Texas Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Pepper Lawson Horizon International Group, LLC v. Texas Southern University, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pepper-lawson-horizon-international-group-llc-v-texas-southern-university-tex-2023.