Pepper Construction Co. v. Travelers Indemnity Co.

23 Pa. D. & C.5th 557
Pennsylvania Court of Common Pleas, Alleghany County·Decided March 31, 2011·No. No. GD 10-20762·Published

Opinion

FRIEDMAN, J.,

Defendants have filed various preliminary objections to plaintiff’s complaint, which concerns insurance coverage for [559] plaintiff’s involvement in a serious construction accident that resulted in plaintiff being sued by two injured workmen. Plaintiff seeks declaratory judgment relief regarding coverage for the construction site accident and has also included a claim for insurance bad faith. At first, defendant Travelers denied having any duty to defend but later recognized that duty. Travelers now has paid the expenses plaintiff incurred until Travelers supplied plaintiff counsel under the policy. However, Travelers has reserved its right not to indemnify plaintiff in the event a verdict is entered against plaintiff in the underlying suit.

Plaintiff’s complaint consists of seven counts as follows:

Count I Breach of Contract, plaintiff vs. Travelers.
Count II Statutory Bad Faith, plaintiff vs. Travelers
Count III Breach of Contract, Article 9 [of the Pepper/ Waltco Subcontract], plaintiff v. Waltco
Count IV Breach of Contract, Article 10 [of the Pepper/Waltco subcontract], plaintiff v. Waltco
CountV Negligence, plaintiff vs. Sky Insurance, Inc.
Count VI Breach of Fiduciary Duty, plaintiff vs. Sky Insurance, Inc.
Count VII Vicarious Liability, plaintiff vs. Traveler (on the theory that Sky was Travelers’ agent)

According to the complaint, Waltco was Pepper’s' subcontractor; Sky was Waltco’s insurance agent; Waltco purchased general liability insurance from Travelers and [560] named Pepper as an additional insured under that policy. Two persons were injured at the work site and brought actions against Pepper and others. Pepper claims Travelers should indemnify it in full for any award against it in the underlying cases in addition to providing a defense. Pepper also claims that Waltco has a similar obligation under the Pepper/Waltco subcontract. Lastly, Pepper claims that Sky failed to procure appropriate insurance for Pepper as required by the Pepper/Waltco subcontract.

The gist of the preliminary objections of the various defendants is as follows, with the court’s thoughts as to each in parentheses:

PRELIMINARY OBJECTIONS OF THE TRAVELERS INDEMNITY COMPANY OF CONNECTICUT

(1) Since Travelers has now retained legal counsel to represent plaintiff in the underlying actions, and has also now reimbursed plaintiff for its legal costs prior to having assumed the defense, any claim based on the duty to defend is moot and should be dismissed. (We agree.)

(2) As to the demand for Travelers to pay for counsel of plaintiff’s choice, that would be a matter for reimbursement later because plaintiff already has its chosen counsel sitting in on all the proceedings in the underlying actions. (Issue raised is deferred for subsequent motion as discussed later herein.)

(3) As to the claims based on indemnity, those are “contingent, not ripe for adjudication and should be stayed.” (We agree the dollar amount of indemnification is not ripe, but we cannot say at this stage that liability is [561] not yet ripe.)

(4) Lastly, the parties to the underlying actions must be joined herein as they are indispensable parties, without whom the court lacks jurisdiction. (We agree.)

PRELIMINARY OBJECTIONS OF WALTCO, INC.:

(1) The claim regarding the duty to defend is moot since Travelers is providing a defense. (However, if Travelers at some point no longer has the duty to defend because it becomes clear that Waltco provided the wrong insurance coverage for Pepper, the question then becomes whether or not Waltco should then have to take up the cost of defending plaintiff.)

(2) The indemnity claim is not ripe as there has been no judgment entered yet against Pepper in the underlying case. (See comment above re similar preliminary objections of travelers.)

(3) The claims based on the possible inadequacy of the insurance procured is not yet known, so such claims are premature. (We agree.)

PRELIMINARY OBJECTIONS OF SKY INSURANCE, INC.

(1) The statute of limitations bars the two claims against Sky for negligence and breach of fiduciary duty. (For answer and new matter.)

(2) The claims for indemnification are not ripe and should be dismissed or stayed. (See comments re Travelers’ similar preliminary objections.)

DISCUSSION

[562] We already noted during argument that the jurisdictional paragraph (5) of the complaint needs to be amended to reflect that the case is no longer in federal court. The question is whether any other portions of the complaint must be removed or amended.

The most important question is whether or not this court lacks jurisdiction because plaintiff has not joined certain indispensable parties, those who are plaintiffs in the underlying actions as well as any defendants therein (other than Pepper and Waltco). The captions of the underlying cases are as follows:

Nicholas Barney vs. Pepper Construction Group, LLC, a corporation, Pepper Construction Co., a corporation, The Pepper Companies, Inc., a corporation, Pepper Construction

Co. of Indiana, LLC, a corporation, and Waltco, Inc., a corporation vs. Jan Skowvron, individually and t/d/b/a Southwest Crane Rental, and L&J Erection, Inc.

Brian Wright and Ashley Wright, his wife vs. Pepper Construction Group, LLC, a corporation, Pepper Construction Co., [563] a corporation, The Pepper Companies, Inc., a corporation, Pepper Construction

Co. of Indiana, LLC, a corporation, and Waltco, Inc., a corporation vs. Jan Skowvron, individually and t/d/b/a Southwest Crane Rental, and L&J Erection, Inc.

Consolidated at GD 09-16289

The provision of the Declaratory Judgments Act dealing with parties is 42 Pa. C.S.A. §7540(a), which provides as follows:

(a) General rule.-When declaratory relief is sought, all persons shall be made parties who have or claim any interest which would be affected by the declaration, and no declaration shall prejudice the rights of persons not parties to the proceeding. In any proceeding which involves the validity of a municipal ordinance or franchise, such municipality shall be made a party and shall be entitled to be heard.

Free access — add to your briefcase to read the full text and ask questions with AI

Pepper Construction Co. v. Travelers Indemnity Co., 23 Pa. D. & C.5th 557 (Pa. Super. Ct. 2011).

23 Pa. D. & C.5th 557 (Pepper Construction Co. v. Travelers Indemnity Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Vale Chemical Co. v. Hartford Accident & Indemnity Co.
516 A.2d 684 (Supreme Court of Pennsylvania, 1986)
Mine Safety Appliances Co. v. Century Indemnity Co.
2 Pa. D. & C.5th 142 (Alleghany County Court of Common Pleas, 2007)