People's Homestead Ass'n v. Staub

3 Teiss. 93, 1906 La. App. LEXIS 5
CourtLouisiana Court of Appeal
DecidedJanuary 9, 1906
DocketNo. 3724
StatusPublished

This text of 3 Teiss. 93 (People's Homestead Ass'n v. Staub) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People's Homestead Ass'n v. Staub, 3 Teiss. 93, 1906 La. App. LEXIS 5 (La. Ct. App. 1906).

Opinions

DUFOUR, J.

The plaintiff entered into a contract with John C. Staub to build a house for him for the sum of $6300, payable in five installments at the time and in the manner specified in such contract.

Three installments aggregating’ $3500 were paid, but previous to the maturity of the fourth, the owner, on the assumption that the contractor had violated his contract by failing to finish the work at the appointed time, completed the' work and paid out the money necessary for that purpose.

Pie then filed a concursus, depositing $988.05 in Court and citing all parties in interest, claimed the first privilege on the amount in part payment of demurrage, and asked for judgment for the balance against the contractor and his surety.

[95]*95The only appellants are the surety, and a material man, the Alfred Hiller Company.

The surety’s present contention is:

First. That the bond is not good as a conventional bond because it was intended as a bond under the act of 1894.

Second. That the surety is discharged because the terms of the contract were modified without his consent.

Third. That the violation of the contract was passive' and there was no putting in default until January 13, 1902, and de-murrage only became due thereafter.

Fourth. That the estimate of demurrage is excessive, no al-lowancé being made for rainy days and days on which no work was done on account of strikes.

The contract provides that should the contractor at any time during the progress of said work refuse or neglect to supply a •sufficiency of material or of workmen, or cause any reasonable neglect or suspension of work or fail or refuse to comply with any part of the agreement, the owner or his agent shall have the right to take possession of the premises and may at once terminate the contract, after giving the contractor forty-eight hours notice in writing.

It is also stipulated that the work shall be finished and delivered previous to September 25, 1901, and liquidated damages would be due at the rate of $12.50 per'day, for every day thereafter that the work shall remain incomplete.

The heading of the bond recites that it is “for the faithful performance of the within contract and as security under the provisions of Act 180 of 1894.”

In the body of the bond the surety binds himself to the People’s Homestead Association and all other persons who may have rights against the contracting parties, in a sum representing the full contract price. The obligation is to pay all material men, workmen, etc., and also to secure the owner against any failure on the part of the contractor to faithfully and properly carry out his contract. There can be no doubt that, under the ruling in Hughes, vs. Smith, recently re-iterated in Lhote Co. vs. Dugue and Levy, the bond is not good as a statutory one, because an amount equal [96]*96to the price is held insufficient to protect both the owner and the statutory beneficiaries, and in consequence all the stipulations in reference to the latter must be stricken from the instrument. The result is that the material men etc., have no direct action against the surety, and the owner remains personally liable. But we see no reason why the conventional part of the agreement should not remain in force between the parties thereto. The bond was unmistakably given for the purpose; the elimination of the purpose not in accordance with law cannot affect or impair the other which is the law the parties have made for themselves.

Moreover, the suety practically acknowledges the original existence of lawful obligation when he seeks his release therefrom on the grounds previously mentioned.'

There is no merit in the claim that the surety was released because of alterations made in the contract and of extra work done. Generally speaking and with the exception of a few insignificant details, the extra work is not shown to have been done with the written consent of the Homestead Co. as required by section 6 of the contract, and it was in a measureable degree ordered and paid for by one Honor for whom the company was having the house built.

The same is true as to some of the alterations; and, as to others, it appears that they were made because Diboll, the supervising architect, did not consider the work properly done.

He was the arbiter under the contract and his decision must be final when it is. not shown to have been unreasonable and arbitrary.

In relation to the claim of release because of anticipation of payment, we find in the record three written consents of the surety for the payment of sums aggregating $2300. With the exception of an anticipation of $125 overpaid to the conti actor before the issuance of the third certificate and for which end it was given the suety in the judgment, it does not appear that he has suffered any loss or injury.

Our Code of Law, fortified by decisions enforcing it, is that the surety is discharged when by the act of the creditor, the subro-gation to his rights, mortgages and privileges can no longer be [97]*97operated in favor of the surety, or when the creditor without the consent of the surety has granted a prolongation of the term to the principal debtor.

R. C. C. 3061, 3063-2 An. 429 An. 179-29 An 844-44 An. 260.

In this instance, the surety’s right has not been impaired, as he has received a credit to the extent of the value of the antici--pation.

Neither of the two cases cited as adverse to this view is applicable.

No. 6. R. 47, in which Court said that “the surety has the right to stand upon the very terms of his contract even if he should be benefited by the change,” the point actually involved and decided was that the surety was released because, without his consent, a prolongation of the term had been granted to the principal debtor by the creditor.

In 113 La. 413, it is merely held that the surety was entitled to a strict compliance with the requirement of giving notice of the commencement of the work and was released by non-compliance therewith. The language used must be construed with reference to the particular facts of that case, in which no question of money or securities was presented, and we are unwilling to assume that it was the intention of the Court to overrule an established jurisprudence without mention of any of the cases which consecrates it.

Passing now to the question of the demurrage claimed by owner, it is firmly settled that he is entitled to demand it with a preference on the fund deposited over all sub-contractors, material, men, etc.

1 Court of Appeal 30.

But the time from which the demurrage shall be computed depends upon the determination of the. question as to whether the contract was violated actively or passively.

There is 'a passive violation when the party does not do what was covenanted to be done or does not do it at the time, or in the manner stipulated or implied from the nature of the contract. In such case it is necessary to put the debtor in default before damages can become due, unless the thing to be done was of such a na[98]*98ture, that it could only be done within a certain time which has elapsed.

R. C. C. 1931-1933-3, An. 445-4, An. 97-98, An. 788-11, An. 300-6, N. S. 624-10 R. 526.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Orleans & J. Ry. Co. v. International Const. Co.
37 So. 10 (Supreme Court of Louisiana, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
3 Teiss. 93, 1906 La. App. LEXIS 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peoples-homestead-assn-v-staub-lactapp-1906.