People v. A.J. Davinroy Contractors

618 N.E.2d 1282, 249 Ill. App. 3d 788, 188 Ill. Dec. 712, 1993 Ill. App. LEXIS 1245
CourtAppellate Court of Illinois
DecidedAugust 12, 1993
DocketNo. 5-91-0770
StatusPublished
Cited by10 cases

This text of 618 N.E.2d 1282 (People v. A.J. Davinroy Contractors) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People v. A.J. Davinroy Contractors, 618 N.E.2d 1282, 249 Ill. App. 3d 788, 188 Ill. Dec. 712, 1993 Ill. App. LEXIS 1245 (Ill. Ct. App. 1993).

Opinion

JUSTICE LEWIS

delivered the opinion of the court:

The State of Illinois, through the Illinois Attorney General’s office, appeals from the denial of its complaint against defendant, A.J. Davinroy Contractors (Davinroy), wherein the State sought an injunction and monetary penalties against defendant for alleged violations of the Illinois Environmental Protection Act (the Act) (Ill. Rev. Stat. 1991, ch. 1111/2, par. 1001 et seq.). The complaint alleged that defendant had allowed large quantities of raw sewage to be discharged into Gooselake Ditch (the ditch), in violation of sections 12(a) and (f) of the Act. (Ill. Rev. Stat. 1991, ch. 1111/2, pars. 1012(a), (f).) The court, after a bench trial, entered an order denying all relief requested by the State, finding that the problem about which the State complained had been in existence for many years before defendant’s involvement, that defendant had no practical alternative other than to discharge the sewage into the ditch, and that an injunction would be moot because the defendant had already completed all work at the site. The State appeals, claiming that the trial court’s decision was against the manifest weight of the evidence under both sections 12(a) and (f). (Ill. Rev. Stat. 1991, ch. 1111/2, pars. 1012(a), (f).) For reasons more fully stated below, we reverse the trial court’s order.

Prior to the hearing, the court entered partial consent orders between the Illinois Environmental Protection Agency (agency) and the Village of Cahokia (village) and an engineering firm working for the village, Hurst-Rosche Engineers, Inc. (engineers). In exchange for the village’s agreement to cooperate in the prosecution of the case against Davinroy and payment of a $10,000 fine, the agency agreed to dismiss its case against the village for an alleged violation resulting out of the same construction project on which Davinroy was working. Similarly, the engineers were also dismissed out of the case in return for their agreement to pay a $3,500 penalty and to help prosecute the case against Davinroy.

At the hearing, Joseph Mahlandt, an engineer from the agency, testified that Davinroy was the contractor hired by the village in 1984 to repair or install several lift stations for the village’s sewer system. Davinroy did not have a permit authorizing the discharge of contaminants during that construction project. The parties stipulated to the admission of 12 exhibits which detailed Mahlandt’s inspections of the construction site and his findings regarding discharge of sewage into the ditch. Basically, the main problem with Davinroy’s work, according to Mahlandt, was that its equipment was not properly maintained so that periodically the pumps would malfunction or stop working altogether and raw sewage would ran into the ditch instead of through the sewer line to the treatment plant. The repair of the lift stations required Davinroy to bypass the normal sewer route at each construction site so that the work could be performed in a dry area. In order to bypass the normal system, pumps were used and the sewage was thereby rerouted to a main sewage line running some three miles from this construction site to the treatment plant: The contract between Davinroy and the village provided that Davinroy was to maintain the sewage flow through the lift stations as work was commenced at each station. The contract gave defendant the option of either using the existing bypass system which was already in place, since most of the lift stations were not operational by the time Davinroy began its work, or installing a system of its own. Davinroy chose to use the temporary system already in place.

Specifically, the exhibits stipulated to by the parties established that Mahlandt observed raw sewage being discharged into the ditch from construction sites trader the control of Davinroy on seven separate occasions between July 25, 1984, and May 24, 1985. On at least one occasion, Davinroy admitted to a violation and was advised to pump the sewage around the work station and into the same downstream manhole that it had been Using previously. Davinroy claimed that the sewage had always flowed into the ditch at this area of the sewer system, but Mahlandt assured Davinroy’s owner during his initial inspection of July 25, 1984, that Davinroy’s activities over the weekend of July 20 were definitely the cause of the condition of the ditch at that time, which was grayish in appearance with significant gasification. Each time Mahlandt inspected, he found that the ditch adjacent to Davinroy’s work sites was a turbid gray color and had a septic, sewage odor. Further, many of the problems were initially reported to the agency from people who lived near the ditch, rather than by the engineers, village, or Davinroy.

In addition to the memorandums from Mahlandt specifying the results of his inspections of the ditch and the construction sites, the parties also stipulated to a letter from the engineers to Davinroy, dated August 11, 1984. The letter advised that raw sewage was bypassing the sewer system and flowing directly into the ditch. It stated that Davinroy had been advised of this problem on numerous occasions in the past. According to the letter, Davinroy had agreed to rectify the problem but had not. Therefore, the letter advised Davinroy that it was in violation of its contract in that Davinroy was responsible for the operation and maintenance of the existing pumping systems in each location where its crews were working. Further, the letter advised Davinroy that its actions were violating agency regulations. Davinroy was directed to immediately begin to sterilize the ditch by using chlorine, which was to be done to the satisfaction of the agency. All costs were to be borne by Davinroy. Finally, the letter stated that Davinroy’s continued failure to comply with the engineers’ requests and the requirements of the contract between Davinroy and the village would be sufficient reason for the engineers to recommend that the village terminate the contract and deduct all expenses from payments remaining due to Davinroy.

On January 30, 1985, Mahlandt collected water samples from the ditch upstream and downstream from the construction site and also collected samples of the sewage being discharged into the ditch. The results of the tests, which were stipulated to by the parties, show that the levels of contaminants in the discharge itself as well as in the ditch just downstream from the construction site exceeded the levels allowable under agency regulations but that the contaminants were within acceptable levels upstream from the construction site.

The only other witness for the State was Dean Mcllravey, the general manager of the engineers, Hurst-Rosche. He testified that at the time Davinroy started work on the lift stations, a temporary bypass system was in place, and Davinroy chose to use that system rather than bring in its own equipment. During the period when Davinroy was working on the lift stations, Mcllravey did not believe that the main sewer line past the lift stations was damaged, but he could not specifically remember. Previously, Mahlandt had testified that he could not swear that the main sewer line was functioning properly during the time Davinroy was working on the lift stations. Mcllravey stated that during the time when Davinroy was working on the sewer, he did not know of any sewage breaks occurring in the area where Davinroy was working other than those caused by Davinroy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People ex rel. Madigan v. Lincoln, Ltd.
2016 IL App (1st) 143487 (Appellate Court of Illinois, 2016)
Illini Environmental, Inc. v. The Environmental Protection Agency
2014 IL App (5th) 130244 (Appellate Court of Illinois, 2014)
Illini Environmental, Inc. v. The Environmental Protection Agency
2014 IL App (5th) 130244 (Appellate Court of Illinois, 2014)
Gonzalez v. Pollution Control Bd.
2011 IL App (1st) 093021 (Appellate Court of Illinois, 2011)
Gonzalez v. Pollution Control Board
2011 IL App (1st) 93021 (Appellate Court of Illinois, 2011)
Illinois State Toll Highway Authority v. Amoco Oil Co.
783 N.E.2d 658 (Appellate Court of Illinois, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
618 N.E.2d 1282, 249 Ill. App. 3d 788, 188 Ill. Dec. 712, 1993 Ill. App. LEXIS 1245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/people-v-aj-davinroy-contractors-illappct-1993.