People Ex Rel. Vermont Marble Co. v. Bollin

219 N.W. 613, 242 Mich. 683
CourtMichigan Supreme Court
DecidedJune 4, 1928
DocketDocket No. 56.
StatusPublished

This text of 219 N.W. 613 (People Ex Rel. Vermont Marble Co. v. Bollin) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People Ex Rel. Vermont Marble Co. v. Bollin, 219 N.W. 613, 242 Mich. 683 (Mich. 1928).

Opinion

Clark, J.

Plaintiff Vermont Marble Company furnished material for erecting the James Scott water fountain on Belle Isle to defendant Emil J. Bollin, trading as John Bollin Company, principal contractor with *684 the city of Detroit. The defendant Southern Surety Company was surety on the construction bond and also on the statutory bond for the protection of'those furnishing material and labor on the job. The city was to make payment to the principal contractor on architect’s certificates of progress of the work furnished from time to time, and such contractor agreed that when he received a payment from the city he would immediately pay to plaintiff its portion applicable on material furnished. There is some evidence that the principal contractor withheld from plaintiff from time to time sums due it upon such certificates and from payments made by the city. The sums so withheld were to draw interest under a fair construction of the contract. When the aggregate of the sums withheld was a large amount, the principal contractor defaulted under its contract with the city and the defendant surety company then conferred with those interested, including plaintiff, and decided to accept responsibility and to complete the job. In this regard there is evidence tending to show an understanding between the parties hereto that no interest on the amounts then due plaintiff would be charged. This evidence is strongly corroborated by the subsequent conduct of plaintiff, especially sending a number of statements of account in which no interest charge appears. When the job was completed defendant surety company concededly owed plaintiff $2,000, but plaintiff contends for the further sum of nearly $2,700 interest. On motion, a verdict was directed for plaintiff for the full amount a,nd judgment entered thereon. Defendant surety brings error.

The judgment must be reversed. Whether plaintiff was entitled to any interest and if so, how much, were, as above indicated, questions of fact for the jury.

That it is upon plaintiff, under section 14830, 3 *685 Comp. Laws 1915, that it may recover, to prove full payment to its laborers and materialmen, is, because of *the extensive oral argument in this court, not likely to arise again and is therefore passed.

Judgment reversed. New trial granted.' Costs to appellant.

Fead, C. J., and North, Fellows, Wiest, McDonald, Potter, and Sharpe, JJ., concurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
219 N.W. 613, 242 Mich. 683, Counsel Stack Legal Research, https://law.counselstack.com/opinion/people-ex-rel-vermont-marble-co-v-bollin-mich-1928.