People ex rel. Ryan v. Boyes

208 Mich. 58
CourtMichigan Supreme Court
DecidedDecember 22, 1919
DocketDocket No. 51
StatusPublished
Cited by1 cases

This text of 208 Mich. 58 (People ex rel. Ryan v. Boyes) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People ex rel. Ryan v. Boyes, 208 Mich. 58 (Mich. 1919).

Opinion

Sharpe, J.

On May 10, 1915, the defendant Boyes entered into a contract with the city of Grand Rapids, in which he agreed to install a water main in said city [59]*59for a distance of about two miles. Bids had been asked for this work, which was to be done in conformity with plans, specifications and blue prints, made a part of the contract.' While a lump sum in payment was fixed in the contract, it was arrived at by computing a number of items which comprised the bids on the labor and material required in executing the work contemplated in the contract. In this contract Boyes agreed “to do all work and furnish all materials for laying a high pressure water main from water works pumping station, to Michigan street,” according to the plans, specifications and drawings theretofore adopted by the board of public works of said city, which were made a part of the contract. The work included the digging of a trench for a 80-inch pipe and installing the pipe therein from Michigan street to a point designated as “Zero” on the drawings. From this point to the pumping station, a 48-inch pipe was to be installed. This particular work was described in the proposal as follows:

“Item 10-A. — For building and installing complete all cast iron pipe and specials, valves and brick masonry necessary to connect the 30-inch pipe to the discharge line at the pumping station, including excavation and back .filling, replacing gravel and brick roadways, removing, replacing and cutting existing pipe lines and all incidental labor and materials, the sum of seven hundred dollars and no cents ($700.00) lump sum.”

For this item, 109 feet in length, a lump sum of $700 had been bid by Boyes. For excavating for the trenches along the rest of the line, he was to receive 69 cents per lineal foot, except where rock was encountered, for which his agreed compensation was $4 per cubic yard. There was a provision for extra excavating, which will be hereafter referred to. The work was to be’ commenced within ten days after the [60]*60signing of the contract and to be completed on or before December 1, 1915; the time of beginning, rate of progress and time of completion being essential conditions of the contract. The board of public works was given the right, in case it appeared that the contractor was dilatory or did not employ sufficient force, to place additional men and teams on the work and render such assistance as it deemed advisable for the completion of the contract within the time fixed therefor, and charge the expenses thereof to the contractor.

Boyes subsequently associated the defendant Fitzpatrick with him as a partner, and they sublet a part of this work to the plaintiff by a contract entered into on May 17, 1915. This contract reads as follows:

“These articles of agreement, made this 17th day of May, A. D. 1915, by and between D. W. Boyes and James R. Fitzpatrick, of Grand Rapids, Michigan, party of the first part, and O. H. Ryan of Grand Rapids, Michigan, party of the second part,
“Witnesseth: In connection with the installation of that contract known as the East End Water Main contract extending from the city pumping station, at Coldbrook, Monroe and Ottawa streets to the intersection at Michigan avenue and Diamond street.
“The party of the second part agrees to perform the following work: Do all excavating, leaving ditch in a suitable condition to install pipe, valves, fittings, etc., excepting as hereinafter noted; all back filling, removing surplus excavation, removing all gravel where directed, carefully, and place to one side.
“The party of the second part agrees to remove dirt from ditch to subgrade after ditch has been refilled and leave same for replacing of gravel. Party of the second part agrees to put gravel back in the ditch if same can be put back with teams and scrapers, excess excavation to be loaded and hauled away.
“Party of the second part will put all pipe, valves and fittings into the ditch and handle same until bell and spigot ends are properly placed together (by party of the first part), remove all surplus material from streets after job is completed, excavate all rock.
[61]*61“At creek crossing excavation will be done up to the walls of the bridges, pipe, etc., handled and swung over the sides of the bridge. The excavation in the creek and other work necessary will not be done by the party of the second part. At railroad crossings where tracks are removed, excavation, back filling, etc., will be done as heretofore mentioned. Where tracks are not removed excavating and loading will be done by parties of the first part, but the excavated material will be hauled and re-hauled by party of the second part. This provision applies to all work at street crossings.
“All underground work, if any, in the line of the( ditch or within the four feet in the nature of water pipe, gas pipe, laterals, telephone service, or any underground wiring will be taken care of by the party of the first part (without expense to the party of the second part), unless damaged by the party of the second part. If anything is disturbed outside of line of ditch or outside of the four feet by the party'of the second part, same will be taken care of by the party of the second part.
“All gravel excavated will be saved and stored if desired by the party of the first part.
“The party of the second part agrees to begin work within fifteen (15) days and have same completed not later than November 1st, A. D. 1915.
“The party of the first part agrees to pay the party of the second part at the rate of fifty-five (55) cents per lineal foot of ditch for all material excavated.
“For rock excavation the party of the first part agrees to pay to party of the second part four dollars ($4.00) per cubic yard.
“The party of the second part in performing his work agrees to do so in entire accordance with plans and specifications and under the direction of the engineer.
“The party of the second part can shore ditch at his discretion, unless shoring is required by the engineer.
“The party of the second part agrees to furnish to the party of the first part satisfactory surety bonds, the same as the first party furnished the city of Grand Rapids, namely, the sum of 25% of value of the con[62]*62tract. These bonds to be by a surety company or by two acceptable individuals.
“The terms of payment are as follows:
“Party of the second part to be paid 85% of work performed up to the time of the preparation of each estimate and to be paid his pro rata share out of each estimate received by the party of the first part.”

The meritorious question presented is whether or not plaintiffs contract included the excavation work between the point designated as “Zero” on the drawings and the pumping station, a distance, as before stated, of 109 feet, and particularly described in “Item 10-A.” The plaintiff was somewhat delayed in his work, and the defendants Boyes and Fitzpatrick did all of the work under this item and also in extending the 30-inch main from “Zero” easterly for 361 feet.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McDaniel v. Hancock
43 N.W.2d 68 (Michigan Supreme Court, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
208 Mich. 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/people-ex-rel-ryan-v-boyes-mich-1919.