People ex rel. O'Malley v. Illinois Commerce Commission

606 N.E.2d 79, 237 Ill. App. 3d 1022, 179 Ill. Dec. 247, 1992 Ill. App. LEXIS 1963
CourtAppellate Court of Illinois
DecidedSeptember 25, 1992
DocketNos. 1—91—0046, 1—91—0172, 1-91-0501 cons.
StatusPublished

This text of 606 N.E.2d 79 (People ex rel. O'Malley v. Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People ex rel. O'Malley v. Illinois Commerce Commission, 606 N.E.2d 79, 237 Ill. App. 3d 1022, 179 Ill. Dec. 247, 1992 Ill. App. LEXIS 1963 (Ill. Ct. App. 1992).

Opinion

JUSTICE RAKOWSKI

delivered the opinion of the court:.

Petitioner-appellant, the People of Cook County ex rel. Jack O’Malley, State’s Attorney of Cook County (Cook County), appeals an order of respondent-appellee Illinois Commerce Commission (the ICC), which held that respondent-appellee Commonwealth Edison Company (Edison) did not violate the law in the dispatch of its western coal fired plants. The order appealed from was entered in a fuel adjustment proceeding, as required by statute (see Ill. Rev. Stat. 1985, ch. 111⅔, par. 9—220). At issue in such a proceeding is whether a utility collected authorized amounts under its fuel adjustment clause during a given year when compared to the actual costs of fuel and power purchased by the utility. After considering Cook County’s arguments, we affirm.

The relevant facts are as follows. The electronic service rates Edison charges to its customers are subject to advance approval by the ICC under the statutory authority of the Illinois Public Utilities Act (the Act) (Ill. Rev. Stat. 1985, ch. 111⅔, par. 1 et seq.). Edison may only charge its customers the rates it has on file with the Commission. Generally, once rates are established with the ICC they are fixed. Section 9—220 of the Act, however, also provides in pertinent part:

“Notwithstanding the provisions of [this Article], the Commission may authorize the increase or decrease of rates and charges based upon changes in the cost of fuel used in the generation or production of electronic power *** through the application of fuel adjustment clauses.” (Ill. Rev. Stat. 1985, ch. 111⅔, par. 9—220.)

This exception exists for the purpose of allowing fuel costs or savings to be passed through to customers promptly, absent the need for frequent rate case proceedings. Re Uniform Fuel Adjustment Clauses (Ill. Com. Comm’n 1981), 45 Pub. Util. Rep. 4th 1, 3-4.

A uniform fuel adjustment clause (FAC) the ICC adopted in 1981 (see Commission General Order 211, reported at 83 Ill. Adm. Code §425 (1991)) (the Code) contains a mathematical formula by which fuel charges to customers change each month to reflect changing costs of fuel and purchased power, and allows for current recovery of such costs by the utility. Under section 425.20 of the Code, fuel costs which are passed through this section of the Code are required to represent either actual, historical costs or estimates of actual costs as they become available.

Section 9—220 also provides that the ICC monitor the application of a utility’s FAC. Utilities file with the ICC monthly calculations of FAC charges and submit to annual audits of FAC charges and costs. (Re Uniform Fuel Adjustment Clauses, 45 Pub. Util. Rep. 4th at 18.) Additionally, section 9—220 provides that the ICC conduct annual public hearings to determine the prudence of costs passed on to consumers and to reconcile the costs collected under the FAC with the actual costs incurred. The ICC will order refunds if it determines that the charges passed on through the FAC do not represent actual costs of prudently purchased fuel. It was via the authority of section 9—220 that the ICC ordered Edison sub judice to present a reconciliation and to demonstrate prudence of its purchases of fuel and power during the relevant periods.

Section 425.40(a) of the Code requires that electrical utilities adhere to economic dispatch in the operation of their generating units. That section defines “economic dispatch” as:

“the operation of the electric utility’s system, utilizing the sources of available power to achieve minimum overall costs, taking into consideration the utility’s voltage, frequency, reliability, environmental, safety and service quality requirements, as well as the utility’s existing contractual obligations.” 83 Ill. Adm. Code §425.40(a) (1991).

William Gould, the ICC’s senior economic analyst in the planning and operations section of the engineering department of the public utilities division, testified that the principles of economic dispatch require that incremental and fixed costs be distinguished. Fixed costs are those costs which are incurred regardless of the amount of generation or operation of a generating unit — or whether energy is produced at all. Incremental costs, on the other hand, are those costs which vary with production and are proportional to the amount of energy produced. A utility satisfies the economic dispatch requirement when units with lower incremental costs are operated ahead of those with higher incremental costs. In order to minimize total system costs, the utility must dispatch its generating units based upon incremental costs, and not based on total costs or other costs.

In the mid-1970’s, Edison entered into long-term coal contracts with three coal companies — Black Butte, Big Horn and Decker. These contracts shall hereinafter be referred to as the “western coal contracts.” The long-term nature of the western coal contracts was insisted upon by the contracting coal companies, and the original contracts required that Edison accept delivery of and pay for a designated minimum quantity of coal each year. At the time the western coal contracts were entered into, Edison’s needs were based upon forecasts which projected that demand for electricity would increase at least 5% per year. The western coal contracts provided coal to suit about 60% of Edison’s needs at the time. As it turned out, electrical demand did not increase as expected, and consequently, the western coal contracts provided for the delivery of more coal than Edison needed to generate electricity.

In response, Edison negotiated a number of amendments to the western coal contracts in the years 1982, 1983, 1986 and 1988. Under the amendments, Edison paid about 75% of the contracts’ cost of a ton of coal as “mineral rights” or “reserve charge” when it could not take the costs as scheduled. Upon this payment, Edison was entitled to defer delivery of the paid-for coal to a later date, and Edison would be obligated to pay the remaining 25% when it accepted delivery of the deferred coal.

Testimony before the ICC established that minimum overall costs are realized when generating units are dispatched on the basis of incremental costs. ICC staff witness William Gould testified that as fixed costs are always present, only variable or incremental costs should effect the dispatch of the utility’s generating system. Staff witness Kenneth Costello testified that “dispatching on the basis of incremental costs minimizes a utility’s total operating costs.” Robert Beckwith, Edison’s manager of fuel, stated that as Edison was obliged to pay for mineral rights, they should be considered as fixed costs and not used for dispatching purposes. Costello agreed that Edison’s calculation of incremental costs for the dispatch of its western coal fired units properly excluded the 75% reserve charge.

The ICC found that Edison’s dispatch methodology should be upheld, and that the evidence established that Edison’s system is operated to achieve minimum overall cost and satisfied the requirement of economic dispatch.

On June 21, 1989, the ICC staff filed a motion to amend the hearing schedule with respect to the issue of Edison’s prudence in its western coal contracts in 1985 and 1986.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People Ex Rel. Hartigan v. Illinois Commerce Commission
510 N.E.2d 865 (Illinois Supreme Court, 1987)
Desai v. Metropolitan Sanitary District of Greater Chicago
466 N.E.2d 1045 (Appellate Court of Illinois, 1984)
Moncada v. Illinois Commerce Commission
571 N.E.2d 1004 (Appellate Court of Illinois, 1991)
Antioch Milling Co. v. Public Service Co.
123 N.E.2d 302 (Illinois Supreme Court, 1954)
Village of Apple River v. Illinois Commerce Commission
165 N.E.2d 329 (Illinois Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
606 N.E.2d 79, 237 Ill. App. 3d 1022, 179 Ill. Dec. 247, 1992 Ill. App. LEXIS 1963, Counsel Stack Legal Research, https://law.counselstack.com/opinion/people-ex-rel-omalley-v-illinois-commerce-commission-illappct-1992.