People Ex Rel. McDonell v. Fidelity & Deposit Co.

205 N.W. 157, 232 Mich. 238, 1925 Mich. LEXIS 839
Michigan Supreme Court·Decided October 1, 1925·No. Docket Nos. 25, 26.·Published·Cited by 10 cases

Opinion

Wiest, J.

September 18, 1922, J. L. Sparling, doing business as J. L. Sparling Company, contracted with the city of Bay City to construct substructures, in accordance with elaborate plans and specifications, for a filtration plant, and gave bond to pay subcontractors and materialmen with the Fidelity ■& Deposit Company of Maryland as surety. September 24, 1922, J. L. Sparling Company entered into the following contract with McDonell Brothers, plaintiffs herein:

“This agreement made this 24th day of September, 1922, by and between the J. L. Sparling Co., of Bay City, Mich., parties of the first part, and McDonell Bros., of Flint, Mich., parties of the second part.
“For the excavation and backfill on the new filter plant, Bay City, Mich.
“Parties of the second part agree to furnish all labor, tools and equipment for the removing’ of all earth on the excavation for the sum of 43 cents per cubic yard measured in the excavation and to do the backfilling at 35 cents per yard measured in place.
“All earth below the original ground levels that is excavated to be paid for as excavation, and all earth placed above the original ground elevations and within. *241 the lines of backfill as per plans to be paid for as backfill.
“Parties of the second part agree to complete work in thirteen months after date.
“Parties of the first part agree to place no unnecessary obstructions in the way of the parties of the second part nor delay said parties in completing their work on time.
“This agreement deals with steam shovel excavation only and ruff grading on backfill.
“Parties of the first part agree to keep all water pumped from excavation so it will not delay the progress of steam shovel.
“Parties of the second part to be paid every two weeks on estimates of work done the previous two weeks on backfill and excavation; final estimate to be paid within two weeks after work is completed.
“The J. L. Spaeling Co.,
By J. L. Sparling.
“McDonell Beos.,
By S. J. McDonell.”

All payments made under this contract were without estimates. In July, 1923, plaintiffs quit work, claiming Sparling Company breached the contract by not paying for work done, brought this suit to recover, and did recover the contract price for work performed. Sparling Company gave notice of recoupment, claiming the contract was breached by plaintiffs. The surety company claimed plaintiffs were not subcontractors, had no consent from the city, did not contract to perform according to the obligation assumed by Sparling Company, and the city voluntarily overpaid Sparling Company. Plaintiffs had judgment for $9,804.23. Defendants prosecute writs of error severally. The jury found Sparling Company breached the contract in not paying for work done, and this finding eliminated all recoupment asserted by Sparling Company.

We do not find it necessary to consider all of the 51 errors assigned by the Sparling Company and the *242 10 errors assigned by the surety company, for the judgment must be reversed and, if tried again, it will be on entirely different issues as to rights and remedies of the parties.

The contract between plaintiffs and Sparling Company was nonapportionable, and the court was in error in permitting recovery on the sole basis of the contract price for excavating and backfilling done. Sparling Company claimed the price per yard, fixed by the contract, was an average price for the whole, and the expensive portion of the excavating and back-filling was left undone. The question is ruled by Adams v. Healy, 227 Mich. 159.

It is insisted the contract provision, requiring estimates of work done, was a prerequisite to right to be paid, and if no estimate was requested or sought by plaintiffs before quitting the job there was no default on the part of Sparling Company in making payments that would justify plaintiffs in abandoning the contract. This question is not of much importance if plaintiffs were not subcontractors, and we need only say it is now too late for Sparling Company to stand upon this requirement, for payments were made from time to time without estimates, and the failure to pay was not because no estimate had been made.

Plaintiffs quit July 14, 1923. July 12, 1923, Sparling Company paid them $300. The court refused to instruct the jury that if plaintiffs made no further request for payment but removed their steam shovel, stating they would bring another shovel to go on with the work, and failed to do so without further notice to Sparling Company, except notice they had quit, then there was a breach of the contract by plaintiffs, and they would be liable to Sparling Company for all damages. This request was properly refused; it left out of consideration the large amount *243 claimed by plaintiffs tó be due, and gave no consideration to the claim of plaintiffs of repeated efforts to obtain their pay.

It is claimed there was error in admitting evidence of an estimate given Sparling Company by the city in November, 1922, under which was obtained payment from the city in excess of work performed. We think this whole matter should have been kept out of the case, as it had nothing to do with the amount due plaintiffs for work and labor.

Free access — add to your briefcase to read the full text and ask questions with AI

People Ex Rel. McDonell v. Fidelity & Deposit Co., 205 N.W. 157, 232 Mich. 238, 1925 Mich. LEXIS 839 (Mich. 1925).

205 N.W. 157 (People Ex Rel. McDonell v. Fidelity & Deposit Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Fca US LLC v. Faurecia Automotive Seating LLC
Michigan Court of Appeals, 2022
Saginaw Pattern Makers' Ass'n v. Saginaw Pattern & Manufacturing Co.
233 N.W.2d 537 (Michigan Court of Appeals, 1975)
Georgia-Pacific Corp. v. Central Park North Co.
204 N.W.2d 321 (Michigan Court of Appeals, 1972)
Krager v. Harold E. Hedler Storage, Inc.
152 N.W.2d 708 (Michigan Court of Appeals, 1967)
City of Lansing v. Township of Lansing
97 N.W.2d 804 (Michigan Supreme Court, 1959)
Fraser v. Collier Construction Co.
8 N.W.2d 889 (Michigan Supreme Court, 1943)
E. A. Pierce & Co. v. Sayers
296 N.W. 663 (Michigan Supreme Court, 1941)
Linde Dredging Co. v. Southwest L. E. Myers Co.
67 F.2d 969 (Fifth Circuit, 1933)
Schultz v. Nickel
231 N.W. 575 (Michigan Supreme Court, 1930)
People Ex Rel. McDonell v. Fidelity & Deposit Co.
218 N.W. 694 (Michigan Supreme Court, 1928)