People Ex Rel. Board of Trustees of Chicago State University v. Siemens Building Technologies, Inc.

900 N.E.2d 414, 387 Ill. App. 3d 606, 326 Ill. Dec. 778, 2008 Ill. App. LEXIS 1316
CourtAppellate Court of Illinois
DecidedDecember 24, 2008
Docket1-08-1258
StatusPublished
Cited by2 cases

This text of 900 N.E.2d 414 (People Ex Rel. Board of Trustees of Chicago State University v. Siemens Building Technologies, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People Ex Rel. Board of Trustees of Chicago State University v. Siemens Building Technologies, Inc., 900 N.E.2d 414, 387 Ill. App. 3d 606, 326 Ill. Dec. 778, 2008 Ill. App. LEXIS 1316 (Ill. Ct. App. 2008).

Opinion

JUSTICE THEIS

delivered the opinion of the court:

This case appears before us on an interlocutory appeal pursuant to Supreme Court Rule 308 (155 Ill. 2d R. 308) to consider three questions certified by the circuit court regarding the interpretation of the Public University Energy Conservation Act (the Act) (110 ILCS 62/1 et seq. (West 1998)). The People of the State of Illinois originally brought this action on behalf of the Board of Trustees of Chicago State University (the Board) against defendants, Siemens Building Technologies, Inc. (Siemens), Siemens Financial Services, Inc., f/k/a Siemens Credit Corporation (Siemens Financial), and MBIA Capital Corporation 1999-B Tax-Exempt Grantor Trust (MBIA) for declaratory relief, rescission, and breach of contract related to two agreements the Board entered into with defendants for the installation, purchase, and financing of certain energy conservation measures at Chicago State University (the University) purportedly designed to provide guaranteed energy and operational cost savings.

In its fourth-amended complaint, the State alleged, inter alia, that the “Performance Services Agreement” the Board entered into with Siemens violated the energy savings guarantee under the Act and that Siemens breached various provisions in the Agreement relating to that guarantee. The State sought restitution, rescission and damages arising from the alleged shortfall in energy savings to the University. The circuit court ultimately dismissed several counts of the fourth-amended complaint, finding that the guarantee could not be properly evaluated until the end of the 10-year contract term. The court also dismissed certain counts relating to the enforceability of the “Master Lease Agreement” the Board originally entered into with Siemens Financial, holding that the Act did not prohibit the financing of the environmental conservation measures by a third-party lender or prohibit an unconditional payment provision in the lease. Subsequently, the court certified three questions for interlocutory appeal pursuant to Supreme Court Rule 308. 155 Ill. 2d R. 308.

1. “Can a university, under the ‘annual’ language of [the Act] §35, sue for reimbursement of a savings shortfall before the end of the [1O] 1 -year guarantee period specified in [the Act] §20?”
2. “Does [the] 2007 amendment to [the Act] §25 merely clarify the language of §25, or does it effect a substantive change? If it effects a substantive change, is the change retroactive?”
3. “(a) Do[es] [the Act] §§5 — 15, 5 — 20, 15, 20, and 35 prevent the use of ‘hell or high water’ financing provisions under which the university must pay a lessor/financier for energy conservation measures even if the measures do not produce a savings to the university? [and] (b) Does the 2007 amendment to [the Act] §25 (see Question 2 supra) affect the answer to this question? If so, in what way?”

For the following reasons, we answer the first certified question by holding that the Act does not require an annual reimbursement of a shortfall, but the parties are not prohibited from contracting for greater protections. We need not answer the second certified question because we find the original intent of the statute can be discerned from the original legislative enactment. We answer the first part of the third certified question in the negative, ruling that the Act does not prohibit the use of “hell or high water” financing clauses.

BACKGROUND

In March 1999, the Board entered into a 10-year “Performance Services Agreement” (the Agreement) with Siemens under which Siemens was to install various energy conservation measures for the University to reduce energy consumption and increase energy efficiency at the University. The parties agreed that this Agreement constituted a “guaranteed energy savings contract” as contemplated by the Act (110 ILCS 62/5 — 15 (West 1998)) and that Siemens was a “qualified provider” of these energy services and measures as that term is defined by the Act (110 ILCS 62/5 — 20 (West 1998)).

Pursuant to section 2 of the Agreement, Siemens guaranteed that the energy and operational cost savings generated over the 10-year term would be equal to or greater than the total cost incurred by the University to complete the project. The total cost of the energy conservation measures was approximately $6 million. The Board additionally agreed to pay approximately $2 million for a maintenance program. Siemens guaranteed that the University would realize a total of at least $10 million from energy, operational and capital savings.

Under subsection 2.2 of the Agreement, the parties set forth an accounting mechanism utilized to track the savings over the term of the Agreement. The amount of guaranteed annual savings was projected for each year of the contract term. At the end of each year, Siemens was responsible for documenting whether there was an excess in savings or a savings shortfall for each annual period based on its annual projections. If there were excess savings in any annual period, Siemens would apply those savings toward the total guaranteed savings projected in the contract. However, if the actual annual energy savings fell short of the projected guaranteed savings for that year, the Board had two options: (1) carry over the shortfall into the next year and increase the savings guarantee amount for the next year; or (2) Siemens would pay the shortfall in the form of a credit toward the maintenance program.

In order to finance the purchase of these measures, in June 1999, the Board entered into a “Master Lease Agreement” (the Lease) with Siemens Financial. Under the Lease, the University borrowed over $6.2 million to purchase the energy conservation measures from Siemens and agreed to repay the loan by making annual payments to Siemens Financial of about $816,000 through 2009. The parties have given us little insight into the relationship between Siemens and Siemens Financial. However, under the Lease, the University holds title to the equipment purchased from Siemens and Siemens Financial holds a security interest in that equipment. The Lease also contains an unconditional rental payment clause the parties refer to as a “hell or high water clause” under which the Board’s obligation to make the lease payments is unconditional, notwithstanding any breach of the Agreement by Siemens. As part of the execution of this Lease, Chapman and Cutler provided an opinion letter on behalf of the University presumably expressing the University’s authorization to enter into the Lease. This letter does not appear in the record on appeal. Siemens Financial eventually assigned its rights in the Lease to another entity who, in turn, assigned its rights to MBIA.

Subsequently, in 2003, a dispute arose relating to the performance guarantee under the Agreement. The Board claimed that certain equipment it had purchased was not functioning properly and claimed an energy savings shortfall of $3 million less than projected through the first four years of the Agreement. Based upon these claims, the Board stopped making payments under the Agreement in 2003.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kircher v. Putnam Funds Trust
922 N.E.2d 1164 (Appellate Court of Illinois, 2010)
Williams v. Board of Review
917 N.E.2d 1094 (Appellate Court of Illinois, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
900 N.E.2d 414, 387 Ill. App. 3d 606, 326 Ill. Dec. 778, 2008 Ill. App. LEXIS 1316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/people-ex-rel-board-of-trustees-of-chicago-state-university-v-siemens-illappct-2008.