Pennzoil Company v. Federal Energy Regulatory Commission

742 F.2d 242, 1984 U.S. App. LEXIS 18298
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 24, 1984
Docket84-4287
StatusPublished
Cited by13 cases

This text of 742 F.2d 242 (Pennzoil Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennzoil Company v. Federal Energy Regulatory Commission, 742 F.2d 242, 1984 U.S. App. LEXIS 18298 (5th Cir. 1984).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge.

The petition seeks review of an interlocutory order issued by the Federal Energy Regulatory Commission in the Independent Oil and Gas Association of West Virginia proceedings in FERC Docket Nos. RI74188 and RI75-21. Because we conclude that the orders of the Commission are not ripe for judicial review, we grant the Commission’s motion to dismiss.

I.

The lengthy procedural history of the IOGA case is explained in our opinion in Pennzoil Co. v. FERC, 645 F.2d 394 (5th Cir.1981). We set out only the history relevant to this appeal. In 1974 IOGA small producers 1 petitioned the Federal Power *243 Commission under the Natural Gas Act, 15 U.S.C. § 717 et seq. (1982), for permission to charge higher rates in their sales to interstate pipelines. The proceeding was resolved in 1976 with settlement agreements 2 that authorized escalation of rates in certain circumstances. The Natural Gas Policy Act of 1978, 15 U.S.C. § 3301 et seq. (1982), generated the question whether the settlement agreements permitted the IOGA producers to charge the maximum lawful prices of the NGPA, and accordingly, one of the interstate pipelines sought its answer from the FPC. The case is currently pending before an administrative law judge. 3

Petitioner Pennzoil became involved in the current IOGA proceedings in 1982 when it purchased West Virginia gas acreage from several small producers. The existing gas sales contracts between these small producers and the pipeline purchaser, Columbia Gas Transmission Corporation, were subject to the terms of the original IOGA settlements. Pennzoil and Columbia amended these contracts so that Pennzoil could charge and collect the ceiling prices permitted under the NGPA, but when Pennzoil filed the amended contracts with the Commission, the New York Public Service Commission protested Pennzoil’s rate change as inconsistent with the IOGA settlement agreements. The Commission determined that the dispute was a matter appropriate for resolution in the ongoing IOGA proceeding and referred the case to the presiding AU. 4

Upon transfer of its contracts to the IOGA proceeding, Pennzoil filed a Motion for Summary Judgment based on two contentions: (1) that Pennzoil, as a large producer, was not subject to the settlement agreements; and (2) that even if Pennzoil were subject to the settlements, those agreements did not prohibit the amended bilateral contracts with Columbia. Shortly thereafter, Pennzoil requested that the AU omit an initial decision and transfer the Motion for Summary Judgment directly to the Commission. The AU instead certified the Motion to Omit Initial Decision, and, while that motion was pending before the Commission, denied Pennzoil’s Motion for Summary Judgment.

The order which Pennzoil invites us to review was issued by the Commission on January 11, 1984. The order denied the Motion to Omit Initial Decision, and, in effect, denied the underlying Motion for Summary Judgment as well. 5 The Commission ruled that Pennzoil, as purchaser of gas producing properties covered by the IOGA proceeding, was subject to the terms of the settlement agreements. The Commission also declined to decide whether the Pennzoil-Columbia contract amendments were consistent with the settlement agreements, finding that that issue raised genuine issues of material fact as to what the parties to the 1976 IOGA settlements intended when they entered into those agreements. After the Commission denied Pennzoil’s application for rehearing of the order, this appeal was filed.

*244 II.

Our authority to review orders of the Commission derives from Section 19(b) of the NGA, 15 U.S.C. § 717r(b) (1982), as well as Section 506 of the NGPA, 15 U.S.C. § 3416 (1982). Although those statutes do not require it, courts have refused to hear appeals from Commission orders where the orders were not ripe for judicial review. Placid Oil Co. v. FERC, 666 F.2d 976, 981 (5th Cir.1982). The policies that inform this rule are those outlined by the Court in Abbott Laboratories v. Gardner, 387 U.S. 136, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967):

to prevent courts, through avoidance of premature adjudication, from entangling themselves in abstract disagreements over administrative policies, and also to protect the agencies from judicial interference until an administrative decision has been formalized and its effects felt in a concrete way by the challenging parties.

Id. at 148, 87 S.Ct. at 1515. Courts have used four criteria to determine whether issues are ripe for judicial review: (1) whether the issues presented are purely legal; (2) whether the challenged agency action constitutes “final agency action” within the meaning of the Administrative Procedure Act; (3) whether the challenged agency action has or will have a direct and immediate impact on the petitioner; and (4) whether the resolution of the issues will foster, rather than impede, effective enforcement and administration by the agency. Placid Oil Co. v. FERC, 666 F.2d at 981; Pennzoil Co. v. FERC, 645 F.2d at 398.

The first of the two issues Pennzoil submits for our review — whether Pennzoil, as a major producer, is subject to the IOGA settlement agreements — is a purely legal issue. The second issue is whether the settlement agreements prohibit Pennzoil's contract amendments with Columbia. According to the Commission, the answer to this question turns on “whether the parties [to the 1976 IOGA settlements] intended to allow bilateral amendment to their contracts,” 6 a factual question to be resolved at the hearing before the ALJ. Thus, the Commission argues, the issues presented' are not “purely legal.” Pennzoil asserts that the Commission mischaracterizes the second issue submitted for review. Pennzoil takes the position that the Commission is obligated to interpret the settlement agreements and orders approving them as a matter of law, and therefore, according to Pennzoil, the second issue is simply whether the Commission can require Pennzoil to participate in the proceeding being conducted by the AU.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
742 F.2d 242, 1984 U.S. App. LEXIS 18298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennzoil-company-v-federal-energy-regulatory-commission-ca5-1984.