Pennsylvania Water & Power Co. v. Reigart

193 A. 311, 127 Pa. Super. 600, 1937 Pa. Super. LEXIS 262
CourtSuperior Court of Pennsylvania
DecidedMarch 9, 1937
DocketAppeal, 8
StatusPublished
Cited by17 cases

This text of 193 A. 311 (Pennsylvania Water & Power Co. v. Reigart) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Water & Power Co. v. Reigart, 193 A. 311, 127 Pa. Super. 600, 1937 Pa. Super. LEXIS 262 (Pa. Ct. App. 1937).

Opinion

Opinion by

Parker, J.,

This appeal is presented to us for a determination of the rights of a grantee in a written grant of a right of way for the construction and maintenance of lines used in the transmission of electric current where the written contract did not precisely fix the location or extent of the land to be occupied. Pennsylvania Water and Power Company, as successor to the original grantee, filed a bill asking for an injunction to restrain Mathias Reigart, a land owner, from interfering with it in constructing lightning arresters for the protection of the power lines which it had installed at a former time. A preliminary injunction was granted and this permitted the plaintiff to complete the installation of the lightning arresters, but on final hearing the bill was dismissed and the plaintiff was refused relief. The power company has appealed from the final decree. The defendant in its answer also asked for relief. The ordér dismissing the bill provided that “the prayer that the defendant be awarded damages is refused without prejudice to his rights to pursue appropriate legal remedies.” The defendant has not appealed.

On April 13, 1923, defendant’s predecessor in title, the owner of about twenty-nine acres of land, granted to plaintiff’s predecessor, his heirs and assigns, “a free and uninterrupted right of way on, over and through” said land “for the purpose of constructing, maintaining, and operating on said right of way a line or lines for the transmission of electric current, as well as tele *603 phone and telegraph lines; together with all necessary-towers, structures, poles, hangers, wires, cables, attachments and other appliances. The said right of way to be located by engineers of said grantee, his heirs and assigns.” The grant included a right of entry on the premises for the purpose of constructing, maintaining, and operating the lines, the right to cut or trim trees and underbrush on the way, and the right to build from time to time “on said right of way, such additional transmission, telephone and telegraph lines as they may wish and determine.” The number of towers to be erected on the property was limited to one, to be located as shown by a blue print attached to the deed. That blue print also showed in a general way the center line of the proposed right of way. The grantee undertook to pay all damages to crops or fences resulting from either construction or repairs.

After the grant the original grantor conveyed about three acres of the entire property to the defendant and, as we understand it, the tower is located on the three acres.

Shortly after the right of way was granted, the plaintiff entered on the land and installed power lines including one tower and has since been maintaining the same facilities. The towers are of steel supported by four legs on concrete foundations, are approximately ninety-six feet in height, and are twenty feet square at the base so that the tower at its widest point is ten feet on each side of the center line. About sixty feet from the ground there were placed three cross arms having a spread of twenty-seven feet, or thirteen and one-half feet on each side of the center line. No telephone or telegraph lines have been installed.

The transmission of current was frequently interrupted by reason of the lines being struck with lightning and this occurred so often and to such an extent that there was an interference with the delivery of cur *604 rent. In 1935 the plaintiff undertook, in accord with well established scientific principles, to install lightning arresters consisting of two pairs of wires. The legs of the towers were connected to the legs of the next adjoining towers on each side by a light wire buried about twenty inches under the ground and on each side of the center line. The wires extended between the towers by a curve in the form of an ellipse and reached a maximum distance of twenty-five feet from the center line of the right of way. Above the transmission lines were placed two wires, one on each side, connecting the steel frames of the towers. These were placed on cross arms extending like horns from the top of the tower. These wires were known as static wires and were kept within the spread of the cross arms Which had formerly been installed and which supported the transmission lines. When this installation was completed the number of interruptions from lightning was reduced to a fraction of what it was formerly. It is apparent that the in. stallation of the lightning arresters was essential to the rendering of efficient service by the plaintiff, a public utility.

In short, we have a situation where the written grant does not precisely fix the location or limits of the way. In accord with the grant, plaintiff’s engineers located the right of way and installed the power lines and tower, and now, twelve years later, it has placed on the land a system of lightning arresters, the wires of which will extend beyond the limits of the right of way as it had been established by use. This, under the law, it cannot do if thereby the plaintiff placed an additional burden on the servient land. “Where a right of way is expressly granted and its precise location and limits are not fixed or defined by the deed, it is competent for the parties to define the location and determine the limits of the right of way by subsequent agreement, use and acquiescence: Kraut’s Appeal, 71 Pa. 64:" *605 March-Brownback Stove Co. v. Evans, 9 Pa. Superior Ct. 597, 603.

Where an easement is granted in general terms without definitely fixing its location or limits, so that the land affected by the exercise of the right cannot be ascertained from an inspection of the writing, the grantee does not thereby acquire a right to use the servient estate without limitation as to place or mode of use. “When the right granted has been once exercised in a fixed and definite course, with the full acquiescence and consent of both parties it cannot be changed at the pleasure of the grantee:" Hogg v. Bailey, 5 Pa. Superior Ct. 426, 433. The contemporaneous construction of the agreement is deemed to be a just exhibition of the intent of the parties: Kraut’s Appeal, 71 Pa. 64; Jennison v. Walker, 77 Mass. 423; Boynton v. Rees, 25 Mass. 329.

Compelled to resort to extrinsic evidence, we follow the same course as is pursued where the parties to a deed at the time of execution by mutual consent place monuments to correspond with the deed. By such act the monuments define the limits of the grant.

In Hogg v. Bailey, supra, Hogg granted a right to back water on land as much as grantee thought necessary and agreed never to claim further damage. Grantee immediately built a dam six feet six inches high backing water to a certain extent on grantor’s land. Many years later an eight-inch timber was placed on the breast of the dam sending the water farther back, destroying a road and causing other damage. The court there said (p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McNAUGHTON PROPERTIES, LP v. Barr
981 A.2d 222 (Superior Court of Pennsylvania, 2009)
Soderberg v. Weisel
687 A.2d 839 (Superior Court of Pennsylvania, 1997)
Zettlemoyer v. Transcontinental Gas Pipeline Corp.
657 A.2d 920 (Supreme Court of Pennsylvania, 1995)
Zettlemoyer v. Transcontinental Gas Pipeline Corp.
617 A.2d 51 (Commonwealth Court of Pennsylvania, 1992)
Denson v. Latranyi
12 Pa. D. & C.4th 370 (Montour County Court of Common Pleas, 1991)
August Petroleum Co. 77B v. Casciola
449 A.2d 735 (Supreme Court of Pennsylvania, 1982)
Lease v. Doll
389 A.2d 1096 (Superior Court of Pennsylvania, 1978)
Beavers v. West Penn Power Co.
436 F.2d 869 (Third Circuit, 1971)
Waggle v. Peoples Natural Gas Co.
17 Pa. D. & C.2d 550 (Westmoreland County Court of Common Pleas, 1958)
Duncan v. Gheen
138 A.2d 168 (Superior Court of Pennsylvania, 1958)
Gedekoh v. Peoples Natural Gas Co.
133 A.2d 283 (Superior Court of Pennsylvania, 1957)
United States v. Felix O'Neill, Inc.
144 F. Supp. 292 (E.D. Pennsylvania, 1956)
Babcock Lumber Co. v. Faust
39 A.2d 298 (Superior Court of Pennsylvania, 1944)
Werry Et Ux. v. Sheldon
24 A.2d 631 (Superior Court of Pennsylvania, 1941)
Cramer v. John Hancock Mutual Life Insurance
13 A.2d 651 (Atlantic County Circuit Court, N.J., 1940)

Cite This Page — Counsel Stack

Bluebook (online)
193 A. 311, 127 Pa. Super. 600, 1937 Pa. Super. LEXIS 262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-water-power-co-v-reigart-pasuperct-1937.