Pennsylvania R. v. Roth

163 F.2d 161, 1947 U.S. App. LEXIS 2238
CourtCourt of Appeals for the Sixth Circuit
DecidedJuly 14, 1947
DocketNo. 10434
StatusPublished
Cited by17 cases

This text of 163 F.2d 161 (Pennsylvania R. v. Roth) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania R. v. Roth, 163 F.2d 161, 1947 U.S. App. LEXIS 2238 (6th Cir. 1947).

Opinion

MILLER, Circuit Judge.

The Pennsylvania Pailroad Company appeals from a judgment rendered in favor of the plaintiff-appellee in an action to recover damages for personal injuries, brought under the provisions of the Federal Employers’ Liability Act. Sections 51 through 60, Title 45 U.S.C.A. No question is raised as to the applicability of the Act.

Under date of May 14, 1942, the United States of America entered into a written contract with the appellant by which the appellant agreed to provide certain storage yards on the line of the railroad for the Government and to furnish the necessary labor and material to make them adequate for use, and to furnish the necessary personnel and equipment for guarding and protecting the property as was from time to time required by the Government. One of the storage yards was located at Crest-line, Ohio, and was laid out upon a piece of farm land several miles from the general classification yards of the railroad. Eleven spur tracks were put down with adequate space between them for bulky loads for the purpose of operating this storage yard. The appellant, on March 1; 1944, entered into a contract with the Fritz-Rumer-Cook Company (hereinafter called the contractor), which provided for the following work to be done by the contractor :

“Unloading inbound cars; assembling and placing dunnage on ground for piling and storage of inbound shipments; removal, from inbound cars and reconditioning of blocking materials; stenciling, marking and placing in storage in said yards, inbound shipments in accordance with Government requirements; removing from storage, and stenciling and remarking outbound shipments and the loading of same on railroad cars, properly blocked and banded, as required by the Government; furnishing blocking, banding, and other necessary material when requested by the Company, recoopering damaged cases; such other work incident to the aforesaid operations as may be requested by the Company.”

Under its terms the appellant was to reimburse the contractor on a cost-plus-fixed-fee basis, based upon monthly statements submitted to and certified by the division engineer of the appellant. The contractor agreed to afford sufficient facilities for the inspection of the work and materials and to give access to its records for examination of the accounts for the purpose of determining the cost of the work, which, however, did not include the contractor’s general supervision, general office expense, general overhead nor interest charges. Inside the storage yard the work of loading and unloading Government material was carried on by the contractor’s employees under the supervision of its yard foreman, John Ohsner. Ohsner hired and fired the men who worked there, directed the Pennsylvania switch engines which entered the yard as to where to place and pick up cars for loading and unloading,, and supervised the work. Harold Naus, freight agent of the appellant, was named as consignee of [163]*163the shipments arriving at the storage yard and signed a non-negotiable receipt for material upon arrival. From time to time the Government ordered the material in the yards forwarded by sending appropriate orders to Naus who transmitted them to Ohsner. Ohsner then supervised the loading of the material and directed its movement out of the yard. Government inspectors entered the storage yard at frequent intervals, inspected the work, and complained to Ohsner in instances where the work was not being done in accordance with Government requirements, such as merchandise not being piled properly or marked correctly. Following such complaints Ohsner changed the loading or the markings according to the instructions. The Government inspectors also filed with Naus its objections to the improper storage or unloading of material at an improper point, and Naus would then issue instructions to correct the trouble.

On August 8, 1945, the appellant gave formal notice to the contractor of the termination of the contract as of August 18, 1945, which date was later extended to such later date as would be necessary to complete the loading of 75 cars. On August 21, 1945, the contractor was loading on to a flat car for shipment to Columbus a large crane owned by it and which had been used in its operations under the contract. John Blancett, a car inspector for appellant, had explained to Ohsner the manner in which the car must be loaded in order to comply with the regulations of the Association of American Railroads and to be acceptable for transportation by the appellant, and was present while the loading was taking place. Blancett showed to Ohsner and to the men working under him diagrams in the book of regulations and from time to time made suggestions as to how the crane should be fastened. At each of the four corners of the freight car a cable was looped through the crane and down through stake pockets on the flat car. The ends of the cable were overlapped and clamped together forming a loose loop. An iron bar was then thrust through the loop and twisted until the cable became taut, at which time one end of the iron bar was pulled down and placed behind a cross-tie which was bolted to the flat car, where it was held in place by tension and by nailing spikes into the cross-tie and bending them down over the bar. Three of the four cables had been fastened. The fourth cable was being worked on. The physical work was being done by two employees of the contractor named Barney and Houser. The appellee, George Roth, another employee of the contractor, was standing on the ground beside the car. He testified that Blancett asked him “Hold that, twist and help hold it down, anchor it there,” that he reached up got hold and helped hold it down, that Blancett then said, “Well, that is all. Leave it there. That is good enough,” following which he let loose of the bar and started to step away from the car. Other evidence was to the effect that Barney and Houser at the same time also let loose of the bar which proved insecurely placed behind the cross-tie, with the immediate result that it slipped from under the tension control and whirled in a reverse twist. In whirling it hit Roth on the cheekbone underneath the left eye fracturing the cheekbone and so injuring the eye that it became necessary to completely remove it from its socket.

Appellee’s amended complaint made two alternative claims. He alleged as his first cause of action that he was an employee of the Railroad Company and that his injuries were caused by the negligence of Blan-cett, appellant’s employee. For his second cause of action he alleged that if it should be determined that he was not in the employ of the appellant and accordingly not subject to the Federal Employers’ Liability Act, then his injury was caused by the negligence of the defendant and its failure to exercise ordinary care for his safety as an invitee upon the premises. At the close of the evidence appellant moved for a directed verdict under both causes of action. The District Judge overruled the motion as to the first cause of action and sustained it as to the second cause of action. He instructed the jury as a matter of law that the appellee Roth was at the time of the accident in the employ of the appellant, and left to the jury the questions of negligence and amount of damages. The jury returned a verdict for the appellee in the [164]*164amount of $14,000, upon which judgment was entered. The Court later overruled appellant’s motion for judgment notwithstanding the verdict and in the alternative for a new trial, following which this appeal was taken.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turpin v. Chicago, Burlington & Quincy Railroad Co.
403 S.W.2d 233 (Supreme Court of Missouri, 1966)
Johnson v. Louisville & Nashville Railroad
394 S.W.2d 110 (Court of Appeals of Kentucky, 1965)
Fawcett v. Missouri Pacific Railroad Company
242 F. Supp. 675 (W.D. Louisiana, 1965)
Valentine v. South Coast Corp.
218 F. Supp. 148 (E.D. Louisiana, 1963)
Patrick Mazzucola v. Pennsylvania Railroad Company
281 F.2d 267 (Third Circuit, 1960)
Baker v. Texas & Pacific Ry. Co.
309 S.W.2d 92 (Court of Appeals of Texas, 1957)
Strauss v. Reading Co.
14 F.R.D. 457 (E.D. Pennsylvania, 1953)
Cincinnati, N. O. & T. P. Ry. Co. v. Eller
197 F.2d 652 (Sixth Circuit, 1952)
Continental Cas. Co. v. Thorden Line the Benny Skou
186 F.2d 992 (Fourth Circuit, 1951)
Kelly v. Delaware River Joint Commission
85 F. Supp. 15 (E.D. Pennsylvania, 1949)
Pennsylvania R. Co. v. Barlion
172 F.2d 710 (Sixth Circuit, 1949)
Gaulden v. Southern Pac. Co.
78 F. Supp. 651 (N.D. California, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
163 F.2d 161, 1947 U.S. App. LEXIS 2238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-r-v-roth-ca6-1947.