OPINION OF THE COURT
VAN ANTWERPEN, Circuit Judge.
The Commonwealth of Pennsylvania Department of Environmental Protection (“DEP/Appellant”) appeals from the orders of the United States District Court for the Western District of Pennsylvania granting the motions to dismiss in favor of Beazer East, Inc. (“Beazer”), Boldan, Inc. (“Boldan”), Carnegie Mellon University (“CMU”), CBS Corporation (“CBS”), and Exxon Mobil Corporation (“Exxon”). Appellant brought suit in federal court seeking reimbursement for cleanup costs under the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (“CERCLA”), 42 U.S.C. §§ 9601-9675. Appellant had previously raised similar claims under the Pennsylvania Hazardous Sites Cleanup Act (“HSCA”), 35 P.S. § 6020.101
et seq.,
in state court.
For reasons which follow, we affirm the decision of the District Court, granting the motions to dismiss for failing to file within the requisite time period prescribed under CERCLA’s statute of limitations.
I.
The site in question (“Site”) is a 118 acre former landfill located in Penn Township, Westmoreland County, Pennsylvania. The Site was formerly a strip mine and operated as a landfill for industrial and municipal waste, buried in pits on the property.
Beginning in 1988, the Pennsylvania DEP was aware of a release or threatened release of hazardous substances at the Site, and by 1999 completed investigative assessments and reports.
From December
2001 until September 2002 DEP conducted several sampling events and excavated test pits, exposing 17 drums containing paint wastes, solvents, and acids that were removed and disposed of off site.
Following the testing period, DEP sought to undertake an “interim response,”
to remove and dispose all hazardous materials from the Site and grade and backfill the land. Between June 2003 and January 2004 the interim response was completed, removing 7,835 drums and containers, 490.82 tons of waste, 3,500 tons of contaminated soil, 20 gas cylinders, and 60 tons of tires. Once removal was over, the land was restored and groundwater monitors placed during the investigatory period were dismantled and abandoned. The cost to DEP for this removal was $3.7 million, and DEP sought to recover this jointly and severally from the five Appel-lees in the District Court complaint that is now on appeal.
II.
The claim against the present Appellees was filed, pursuant to CERCLA, 42 U.S.C. § 9706, in the United States District Court for the Western District of Pennsylvania on August 21, 2009. DEP filed an Amended Complaint on March 31, 2010, pursuant to an order of the Court. The action before the District Court was dismissed via motion as to CMU, CBS, and Exxon for a statute of limitations violation. DEP filed a Motion for Reconsideration or in the alternative a motion for Certification of Appeal, which was denied on September 28, 2011. On October 28, 2011, DEP dismissed all remaining claims against Beazer and Boldan under Federal Rule of Civil Procedure 41(a)(2), and the District Court closed the case.
DEP filed its first appeal with this Court, which was denied on April 24, 2012, the panel finding the voluntary dismissal on October 28, 2011 did not provide the finality necessary for appeal. On January 9, 2013, Beazer and Boldan, the two remaining parties in the case, moved to dismiss DEP’s Amended Complaint under Federal Rule of Civil Procedure 12(b)(6). The Court granted the motion and this appeal followed.
III.
The District Court had jurisdiction pursuant to section 113(b) of CERCLA, 42
U.S.C. § 9613(b),
and 28 U.S.C. § 1B31.
This Court has jurisdiction pursuant to 28 U.S.C. §§ 1291, 2106.
We exercise plenary review over a district court’s grant of a motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6). Grier
v. Klem,
591 F.3d 672, 676 (3d Cir.2010). The key inquiry in the matter is whether, accepting the factual allegations in the light most favorable to the Appellant, and drawing all reasonable inferences therefrom, the complaint “contain[ed] sufficient factual matter, accepted as true, to state a claim to relief that is plausible on its face.”
Ashcroft v. Iqbal,
556 U.S. 662, 677-78, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009) (internal quotation marks omitted).
IV.
The determination of whether a plausible claim for relief exists turns on whether the action undertaken by DEP on the Site was “removal”
or “remedial action,”
as the statute of limitations period differs for each pursuant to 42 U.S.C. § 9613(g)(2)(A-B).
Appellees’ claim the action was a “removal” and since the DEP finished its clean up in January 2004, the complaint filed in August 2009 was beyond the three-
year period for timely filing.
DEP argues that even though its actions were labeled as “interim”
they were in fact a permanent remedy and should qualify as “remedial” under CERCLA, thus invoking the six-year statute of limitations period. For a “remedial” action, the starting date for the statute of limitations would normally have been June of 2003. However, DEP entered into a tolling agreement with all five Appellees on March 6, 2009 agreeing, for the purposes of the statute of limitations under CERCLA, that the six month period from February 20, 2009 to August 20, 2009 would not be included in the calculations. This agreement had the effect of moving the filing date from June 2009 to December 2009. Accordingly, Appellants claim that their filing date of August 2009 was within the six year statute of limitations.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION OF THE COURT
VAN ANTWERPEN, Circuit Judge.
The Commonwealth of Pennsylvania Department of Environmental Protection (“DEP/Appellant”) appeals from the orders of the United States District Court for the Western District of Pennsylvania granting the motions to dismiss in favor of Beazer East, Inc. (“Beazer”), Boldan, Inc. (“Boldan”), Carnegie Mellon University (“CMU”), CBS Corporation (“CBS”), and Exxon Mobil Corporation (“Exxon”). Appellant brought suit in federal court seeking reimbursement for cleanup costs under the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (“CERCLA”), 42 U.S.C. §§ 9601-9675. Appellant had previously raised similar claims under the Pennsylvania Hazardous Sites Cleanup Act (“HSCA”), 35 P.S. § 6020.101
et seq.,
in state court.
For reasons which follow, we affirm the decision of the District Court, granting the motions to dismiss for failing to file within the requisite time period prescribed under CERCLA’s statute of limitations.
I.
The site in question (“Site”) is a 118 acre former landfill located in Penn Township, Westmoreland County, Pennsylvania. The Site was formerly a strip mine and operated as a landfill for industrial and municipal waste, buried in pits on the property.
Beginning in 1988, the Pennsylvania DEP was aware of a release or threatened release of hazardous substances at the Site, and by 1999 completed investigative assessments and reports.
From December
2001 until September 2002 DEP conducted several sampling events and excavated test pits, exposing 17 drums containing paint wastes, solvents, and acids that were removed and disposed of off site.
Following the testing period, DEP sought to undertake an “interim response,”
to remove and dispose all hazardous materials from the Site and grade and backfill the land. Between June 2003 and January 2004 the interim response was completed, removing 7,835 drums and containers, 490.82 tons of waste, 3,500 tons of contaminated soil, 20 gas cylinders, and 60 tons of tires. Once removal was over, the land was restored and groundwater monitors placed during the investigatory period were dismantled and abandoned. The cost to DEP for this removal was $3.7 million, and DEP sought to recover this jointly and severally from the five Appel-lees in the District Court complaint that is now on appeal.
II.
The claim against the present Appellees was filed, pursuant to CERCLA, 42 U.S.C. § 9706, in the United States District Court for the Western District of Pennsylvania on August 21, 2009. DEP filed an Amended Complaint on March 31, 2010, pursuant to an order of the Court. The action before the District Court was dismissed via motion as to CMU, CBS, and Exxon for a statute of limitations violation. DEP filed a Motion for Reconsideration or in the alternative a motion for Certification of Appeal, which was denied on September 28, 2011. On October 28, 2011, DEP dismissed all remaining claims against Beazer and Boldan under Federal Rule of Civil Procedure 41(a)(2), and the District Court closed the case.
DEP filed its first appeal with this Court, which was denied on April 24, 2012, the panel finding the voluntary dismissal on October 28, 2011 did not provide the finality necessary for appeal. On January 9, 2013, Beazer and Boldan, the two remaining parties in the case, moved to dismiss DEP’s Amended Complaint under Federal Rule of Civil Procedure 12(b)(6). The Court granted the motion and this appeal followed.
III.
The District Court had jurisdiction pursuant to section 113(b) of CERCLA, 42
U.S.C. § 9613(b),
and 28 U.S.C. § 1B31.
This Court has jurisdiction pursuant to 28 U.S.C. §§ 1291, 2106.
We exercise plenary review over a district court’s grant of a motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6). Grier
v. Klem,
591 F.3d 672, 676 (3d Cir.2010). The key inquiry in the matter is whether, accepting the factual allegations in the light most favorable to the Appellant, and drawing all reasonable inferences therefrom, the complaint “contain[ed] sufficient factual matter, accepted as true, to state a claim to relief that is plausible on its face.”
Ashcroft v. Iqbal,
556 U.S. 662, 677-78, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009) (internal quotation marks omitted).
IV.
The determination of whether a plausible claim for relief exists turns on whether the action undertaken by DEP on the Site was “removal”
or “remedial action,”
as the statute of limitations period differs for each pursuant to 42 U.S.C. § 9613(g)(2)(A-B).
Appellees’ claim the action was a “removal” and since the DEP finished its clean up in January 2004, the complaint filed in August 2009 was beyond the three-
year period for timely filing.
DEP argues that even though its actions were labeled as “interim”
they were in fact a permanent remedy and should qualify as “remedial” under CERCLA, thus invoking the six-year statute of limitations period. For a “remedial” action, the starting date for the statute of limitations would normally have been June of 2003. However, DEP entered into a tolling agreement with all five Appellees on March 6, 2009 agreeing, for the purposes of the statute of limitations under CERCLA, that the six month period from February 20, 2009 to August 20, 2009 would not be included in the calculations. This agreement had the effect of moving the filing date from June 2009 to December 2009. Accordingly, Appellants claim that their filing date of August 2009 was within the six year statute of limitations. For reasons outlined below, in reading the facts in the light most favorable to the Appellant, we find DEP instituted a “removal” action and failed to timely file. Thus, the District Court acted properly in its order granting Appellees’ motions to dismiss.
Courts and agencies have struggled to distinguish removal and remedial actions under § 9607(a) of the statute.
Environmental Protection Agency (“EPA”) regulations describe a “removal” action as a subsection or precursor to “remedial action.” 40 C.F.R. § 300.415(d) (“Removal actions shall, to the extent practicable, contribute to the efficient performance of any anticipated long-term remedial action with respect to the release concerned.”).
Remedial action is defined as “those actions consistent with permanent remedy taken
instead of, or in addition to, removal action
in the event of a release or threatened release of a hazardous substance into the environment-”
Id.
§ 300.5 (emphasis added).
Decisions in the courts of this Circuit have furthered the regulatory definitions, postulating the general distinction is that removal actions are primarily those intended for short-term clean-up arrangements, while remedial actions effect long-term or permanent remedies.
See United States v. Alcan Aluminum Corp.,
964 F.2d 252, 259 n. 10 (3d Cir.1992) (“Typically, a ‘removal’ action is an action intended to remove the hazardous waste from the area, whereas a ‘remedial’ action involves a long-term effort to remedy the damaged environment.”).
Lower courts and Pennsylvania regulatory decisions have been more forthcoming about a difference between the terms, as have our sister Circuit. “A removal action is not converted into a remedial action just because it effects a permanent remedy.”
Hatco Corp. v. W.R. Grace & Co. Conn.,
849 F.Supp. 931, 962 (D.N.J.1994);
see also General Elec. Co. v. Litton Indus. Automation Sys.,
920 F.2d 1415, 1419 n. 4 (8th Cir.1990) (rejecting argument that “an excavation that totally and permanently cleans up a hazardous waste site never can be classified as a removal action.”). Additionally, the Pennsylvania Environmental Hearing Board “interprets] the term ‘interim response’ to mean response actions taken prior to the development and execution of a remedial action.”
Comm. of Penn. Dept. of Enviro. Prot. v. Crown Recycle & Recovery, Inc.,
1998 E.H.B. 1204 (Pa.Env.Hrg.Bd. Nov. 4, 1998).
V.
We exercise plenary review over the filings of the parties, including matters of public record and authentic documents.
Pension Benefit Guar. Corp. v. White Consol. Indus., Inc.,
998 F.2d 1192, 1196 (3d Cir.1993). We believe the District Court properly granted the motions to dismiss because the actions undertaken by Appellant were a “removal,” and thus, the statute of limitations period was exceeded.
Even when taken in the light most favorable to the Appellant, the Amended Complaint fails to justify the conclusion that the disposal on the Site was “remedial” and thus subject to a longer statute of limitations period. In its early public bulletins (attached as documents before this Court), DEP initially categorized its cleanup actions as an “interim” response. Later, DEP adjusted its terminology, calling it a “limited interim response,” claiming it was akin to a “remedial” response under CERCLA. Yet, DEP offers no evidence as to where the term “limited” is defined nor effectively articulates what about the actions undertaken made them “remedial” as opposed to “removal.” Next, although it claims that costs ran beyond the $2 million cap for state “interim” (aka “removal”) responses, DEP’s plan said the work would “cost less than $2 million and take less than 1 year,” and thus the final price was only a cost overrun as opposed to remedial action.
(Joint Appendix at 182.) Furthermore, DEP has filed papers adjoining its brief which contradict its present arguments. In its 2003 Statement of Decision, an agency document drafted by the DEP outlining the plan to be undertaken on the Site, DEP stated there was “an immediate threat of a release of hazardous substances ... that presents a substantial danger to the public health, safety,
and the environment.” DEP continued, stating, “[t]he response is
not a final remedial
response
pursuant to Section 504 of the HSCA.... Additional response action may be needed to achieve a complete and final cleanup for the site.”
(Id.
at 137.) (emphasis added). Despite these pri- or statements, DEP now argues “[m]ulti-ple paragraphs of DEP’s Amended Complaint allege that DEP’s response did not address an immediate or imminent release ... determining] that a response to address an immediate or imminent threat was not necessary.” (Appellant’s Brief at 39.)
In applying the various regulatory and statutory definitions to the actions of Appellant, what was undertaken was a “removal” action. The actions were a “cleanup or removal of released hazardous substances” more than a “permanent remedy.”
See
42 U.S.C. § 9601(23)-(24). In fact, DEP presumed in its prior Statement of Decision that “[a]dditional response action may be needed to achieve a complete and final cleanup for the site.” (Joint Appendix at 188.) What was undertaken was intended to “remove the hazardous waste from the area,” not “remedy the damaged environment.”
United States v. Alcan Aluminum Corp.,
964 F.2d 252, 259 n. 10 (3d Cir.1992).
Appellant sought further discovery from the District Court to better define the term “limited” and provide greater factual justification for its actions being “remedial.” Even drawing all reasonable inferences, our review of the amended complaint fails to find either a definition for the term “limited interim response” or viable justification of “remedial” action. Thus, we interpret the actions as “removal” and, therefore, Appellant failed to file a claim within the time requirements under the statute of limitations. Accordingly, the dismissal by the District Court was valid.
VI.
For the foregoing reasons, the Order of the District Court granting Appellees’ motions to dismiss is affirmed.