Pennsylvania Department of Environmental Protection v. Beazer East, Inc.

553 F. App'x 153
Court of Appeals for the Third Circuit·Decided January 2, 2014·No. 13-1209·Unpublished

Opinion

OPINION OF THE COURT

VAN ANTWERPEN, Circuit Judge.

The Commonwealth of Pennsylvania Department of Environmental Protection (“DEP/Appellant”) appeals from the orders of the United States District Court for the Western District of Pennsylvania granting the motions to dismiss in favor of Beazer East, Inc. (“Beazer”), Boldan, Inc. (“Boldan”), Carnegie Mellon University (“CMU”), CBS Corporation (“CBS”), and Exxon Mobil Corporation (“Exxon”). Appellant brought suit in federal court seeking reimbursement for cleanup costs under the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (“CERCLA”), 42 U.S.C. §§ 9601-9675. Appellant had previously raised similar claims under the Pennsylvania Hazardous Sites Cleanup Act (“HSCA”), 35 P.S. § 6020.101 et seq., in state court. 1 For reasons which follow, we affirm the decision of the District Court, granting the motions to dismiss for failing to file within the requisite time period prescribed under CERCLA’s statute of limitations.

I.

The site in question (“Site”) is a 118 acre former landfill located in Penn Township, Westmoreland County, Pennsylvania. The Site was formerly a strip mine and operated as a landfill for industrial and municipal waste, buried in pits on the property. 2 Beginning in 1988, the Pennsylvania DEP was aware of a release or threatened release of hazardous substances at the Site, and by 1999 completed investigative assessments and reports. 3 From December *155 2001 until September 2002 DEP conducted several sampling events and excavated test pits, exposing 17 drums containing paint wastes, solvents, and acids that were removed and disposed of off site. 4

Following the testing period, DEP sought to undertake an “interim response,” 5 to remove and dispose all hazardous materials from the Site and grade and backfill the land. Between June 2003 and January 2004 the interim response was completed, removing 7,835 drums and containers, 490.82 tons of waste, 3,500 tons of contaminated soil, 20 gas cylinders, and 60 tons of tires. Once removal was over, the land was restored and groundwater monitors placed during the investigatory period were dismantled and abandoned. The cost to DEP for this removal was $3.7 million, and DEP sought to recover this jointly and severally from the five Appel-lees in the District Court complaint that is now on appeal.

II.

The claim against the present Appellees was filed, pursuant to CERCLA, 42 U.S.C. § 9706, in the United States District Court for the Western District of Pennsylvania on August 21, 2009. DEP filed an Amended Complaint on March 31, 2010, pursuant to an order of the Court. The action before the District Court was dismissed via motion as to CMU, CBS, and Exxon for a statute of limitations violation. DEP filed a Motion for Reconsideration or in the alternative a motion for Certification of Appeal, which was denied on September 28, 2011. On October 28, 2011, DEP dismissed all remaining claims against Beazer and Boldan under Federal Rule of Civil Procedure 41(a)(2), and the District Court closed the case.

DEP filed its first appeal with this Court, which was denied on April 24, 2012, the panel finding the voluntary dismissal on October 28, 2011 did not provide the finality necessary for appeal. On January 9, 2013, Beazer and Boldan, the two remaining parties in the case, moved to dismiss DEP’s Amended Complaint under Federal Rule of Civil Procedure 12(b)(6). The Court granted the motion and this appeal followed. 6

III.

The District Court had jurisdiction pursuant to section 113(b) of CERCLA, 42 *156 U.S.C. § 9613(b), 7 and 28 U.S.C. § 1B31. 8 This Court has jurisdiction pursuant to 28 U.S.C. §§ 1291, 2106.

We exercise plenary review over a district court’s grant of a motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6). Grier v. Klem, 591 F.3d 672, 676 (3d Cir.2010). The key inquiry in the matter is whether, accepting the factual allegations in the light most favorable to the Appellant, and drawing all reasonable inferences therefrom, the complaint “contain[ed] sufficient factual matter, accepted as true, to state a claim to relief that is plausible on its face.” Ashcroft v. Iqbal, 556 U.S. 662, 677-78, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009) (internal quotation marks omitted).

IV.

Free access — add to your briefcase to read the full text and ask questions with AI

Pennsylvania Department of Environmental Protection v. Beazer East, Inc., 553 F. App'x 153 (3d Cir. 2014).

553 F. App'x 153 (Pennsylvania Department of Environmental Protection v. Beazer East, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Exxon Corp. v. Hunt
475 U.S. 355 (Supreme Court, 1986)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Grier v. Klem
591 F.3d 672 (Third Circuit, 2010)
Hatco Corp. v. W.R. Grace & Co.—Conn.
849 F. Supp. 931 (D. New Jersey, 1994)
United States v. Alcan Aluminum Corp.
964 F.2d 252 (Third Circuit, 1992)