Pennsylvania Department of Environmental Protection v. Beazer East, Inc.

553 F. App'x 153
CourtCourt of Appeals for the Third Circuit
DecidedJanuary 2, 2014
Docket13-1209
StatusUnpublished

This text of 553 F. App'x 153 (Pennsylvania Department of Environmental Protection v. Beazer East, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Department of Environmental Protection v. Beazer East, Inc., 553 F. App'x 153 (3d Cir. 2014).

Opinion

OPINION OF THE COURT

VAN ANTWERPEN, Circuit Judge.

The Commonwealth of Pennsylvania Department of Environmental Protection (“DEP/Appellant”) appeals from the orders of the United States District Court for the Western District of Pennsylvania granting the motions to dismiss in favor of Beazer East, Inc. (“Beazer”), Boldan, Inc. (“Boldan”), Carnegie Mellon University (“CMU”), CBS Corporation (“CBS”), and Exxon Mobil Corporation (“Exxon”). Appellant brought suit in federal court seeking reimbursement for cleanup costs under the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (“CERCLA”), 42 U.S.C. §§ 9601-9675. Appellant had previously raised similar claims under the Pennsylvania Hazardous Sites Cleanup Act (“HSCA”), 35 P.S. § 6020.101 et seq., in state court. 1 For reasons which follow, we affirm the decision of the District Court, granting the motions to dismiss for failing to file within the requisite time period prescribed under CERCLA’s statute of limitations.

I.

The site in question (“Site”) is a 118 acre former landfill located in Penn Township, Westmoreland County, Pennsylvania. The Site was formerly a strip mine and operated as a landfill for industrial and municipal waste, buried in pits on the property. 2 Beginning in 1988, the Pennsylvania DEP was aware of a release or threatened release of hazardous substances at the Site, and by 1999 completed investigative assessments and reports. 3 From December *155 2001 until September 2002 DEP conducted several sampling events and excavated test pits, exposing 17 drums containing paint wastes, solvents, and acids that were removed and disposed of off site. 4

Following the testing period, DEP sought to undertake an “interim response,” 5 to remove and dispose all hazardous materials from the Site and grade and backfill the land. Between June 2003 and January 2004 the interim response was completed, removing 7,835 drums and containers, 490.82 tons of waste, 3,500 tons of contaminated soil, 20 gas cylinders, and 60 tons of tires. Once removal was over, the land was restored and groundwater monitors placed during the investigatory period were dismantled and abandoned. The cost to DEP for this removal was $3.7 million, and DEP sought to recover this jointly and severally from the five Appel-lees in the District Court complaint that is now on appeal.

II.

The claim against the present Appellees was filed, pursuant to CERCLA, 42 U.S.C. § 9706, in the United States District Court for the Western District of Pennsylvania on August 21, 2009. DEP filed an Amended Complaint on March 31, 2010, pursuant to an order of the Court. The action before the District Court was dismissed via motion as to CMU, CBS, and Exxon for a statute of limitations violation. DEP filed a Motion for Reconsideration or in the alternative a motion for Certification of Appeal, which was denied on September 28, 2011. On October 28, 2011, DEP dismissed all remaining claims against Beazer and Boldan under Federal Rule of Civil Procedure 41(a)(2), and the District Court closed the case.

DEP filed its first appeal with this Court, which was denied on April 24, 2012, the panel finding the voluntary dismissal on October 28, 2011 did not provide the finality necessary for appeal. On January 9, 2013, Beazer and Boldan, the two remaining parties in the case, moved to dismiss DEP’s Amended Complaint under Federal Rule of Civil Procedure 12(b)(6). The Court granted the motion and this appeal followed. 6

III.

The District Court had jurisdiction pursuant to section 113(b) of CERCLA, 42 *156 U.S.C. § 9613(b), 7 and 28 U.S.C. § 1B31. 8 This Court has jurisdiction pursuant to 28 U.S.C. §§ 1291, 2106.

We exercise plenary review over a district court’s grant of a motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6). Grier v. Klem, 591 F.3d 672, 676 (3d Cir.2010). The key inquiry in the matter is whether, accepting the factual allegations in the light most favorable to the Appellant, and drawing all reasonable inferences therefrom, the complaint “contain[ed] sufficient factual matter, accepted as true, to state a claim to relief that is plausible on its face.” Ashcroft v. Iqbal, 556 U.S. 662, 677-78, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009) (internal quotation marks omitted).

IV.

The determination of whether a plausible claim for relief exists turns on whether the action undertaken by DEP on the Site was “removal” 9 or “remedial action,” 10 as the statute of limitations period differs for each pursuant to 42 U.S.C. § 9613(g)(2)(A-B). 11 Appellees’ claim the action was a “removal” and since the DEP finished its clean up in January 2004, the complaint filed in August 2009 was beyond the three- *157 year period for timely filing. 12 DEP argues that even though its actions were labeled as “interim” 13 they were in fact a permanent remedy and should qualify as “remedial” under CERCLA, thus invoking the six-year statute of limitations period. For a “remedial” action, the starting date for the statute of limitations would normally have been June of 2003. However, DEP entered into a tolling agreement with all five Appellees on March 6, 2009 agreeing, for the purposes of the statute of limitations under CERCLA, that the six month period from February 20, 2009 to August 20, 2009 would not be included in the calculations. This agreement had the effect of moving the filing date from June 2009 to December 2009. Accordingly, Appellants claim that their filing date of August 2009 was within the six year statute of limitations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Exxon Corp. v. Hunt
475 U.S. 355 (Supreme Court, 1986)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Grier v. Klem
591 F.3d 672 (Third Circuit, 2010)
Hatco Corp. v. W.R. Grace & Co.—Conn.
849 F. Supp. 931 (D. New Jersey, 1994)
United States v. Alcan Aluminum Corp.
964 F.2d 252 (Third Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
553 F. App'x 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-department-of-environmental-protection-v-beazer-east-inc-ca3-2014.