Pennsylvania Co. v. Ebaugh

53 N.E. 763, 152 Ind. 531, 1899 Ind. LEXIS 182
Indiana Supreme Court·Decided May 10, 1899·No. No. 18,383·Published·Cited by 32 cases

Opinion

Hadley, J.

Appellee brought this action against appellant to recover damages for the loss of an arm which resulted from injuries received while attempting to couple cars while in the service of appellant as a brakeman on one of its freight trains. The complaint is in three paragraphs. A demurrer to each was overruled. Answer in general denial. Verdict and judgment for appellee. Error is assigned upon the. overruling of the demurrers to the complaint; in overruling appellant’s motion for judgment upon answers to interrogatories, notwithstanding the general verdict; and in overruling appellant’s motion for a new trial.

The negligence charged in the first paragraph relates to the order of the conductor to the plaintiff to couple two cars of different construction, — the draw-bars of one being higher than the draw-bars of the other, and the deadwoods so negligently constructed and maintained that the cars were but eight inches apart when the deadwoods, collided, — which [532] conditions were known to the defendant, and unknown to the plaintiff, and on account of which conditions the plaintiff, in attempting to couple said two cars, was caught between them, held fast, and injured. The second, in addition, alleged that the north rail of the track where the plaintiff was ordered to make the coupling had a strong, sharp splinter of iron protruding therefrom, and that, when the plaintiff stepped in to make the coupling, said splinter penetrated his shoe and held him fast, wherpby he was injured. The third charges that the night was very dark, and the plaintiff, acting under the rules and regulations of the company, and orders of the conductor, took his station at the standing car, and signaled for the backing and slowing up of the train, but, instead of coming back slowly, the conductor negligently cut two cars from the rear of the backing train, that, unrestrained, rushed violently and unexpectedly upon and injured him.

Appellant requested the court to charge the jury that if they found the plaintiff was injured solely by the negligence of the conductor of the train, and that the defendant was free from fault in employing said conductor, or in retaining him in its service, such injury was the result of the negligence of a co-employe, and that they should find for the defendant. Appellant’s counsel says in his brief: “The overruling of the demurrer to each paragraph of the complaint, and the refusal to give said instruction to the jury, present the question of the validity of the Employers’ Liability Act.” No objection is made to either paragraph of the complaint, nor to the refusal of the court to give said instruction number twenty, further than that the act of 1*893 (Acts 1893, p. 29é, section 1083 Burns 1894), upon which it is claimed they rest, is obnoxious to the Constitution. Since the brief was written, this court has decided the question 'here propounded adversely to the position assumed by the appellant. Pittsburgh, etc., R. Co. v. Montgomery, ante, 1; Pittsburgh, etc., R. Co. v. Hosea, ante, 412.

[533] The correctness of certain instructions given and refused is challenged by appellant’s motion for a new trial. Appellee submits that the instructions given and refused are not properly in the record, because no filing of the same is disclosed. Both sets are made part of the record by order of court, and both are fully set out in the order. This brings them properly into the 'record. Close v. Pittsburgh, etc., R. Co., 150 Ind. 560.

Appellee also contends that neither the instructions given nor those refused are in the record so as to question them severally. The alleged error is stated in the motion for a new trial as follows: Eor “error of the court in refusing to •give to the jury each of the instructions severally asked, numbered one, two, three,” etc. Eor “error of the court in giving to the jury each of the instructions given by the court numbered one, two, three,” etc. “Each” is a word of distribution,— implies severalty, — and the assignment is sufficient to challenge each instruction of each set. Terre Haute, etc., R. Co. v. McCorkle, 140 Ind. 613.

Free access — add to your briefcase to read the full text and ask questions with AI

Pennsylvania Co. v. Ebaugh, 53 N.E. 763, 152 Ind. 531, 1899 Ind. LEXIS 182 (Ind. 1899).

53 N.E. 763 (Pennsylvania Co. v. Ebaugh) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Conrad v. Tomlinson
279 N.E.2d 546 (Indiana Supreme Court, 1972)
Siebeking v. Ford, Admx., Etc.
148 N.E.2d 194 (Indiana Court of Appeals, 1958)
Pennsylvania R.R. Co. v. Hemmer, Admx.
186 N.E. 285 (Indiana Supreme Court, 1933)
Green Engineering Co. v. Rosinski
105 N.E. 938 (Indiana Court of Appeals, 1914)
Terre Haute, Indianapolis & Eastern Traction Co. v. Young
104 N.E. 780 (Indiana Court of Appeals, 1914)
Burford v. Dautrich
103 N.E. 953 (Indiana Court of Appeals, 1914)
Newsom v. Chicago & Eastern Illinois Railroad
101 N.E. 26 (Indiana Court of Appeals, 1913)
Indianapolis Traction & Terminal Co. v. Mathews
97 N.E. 320 (Indiana Supreme Court, 1912)
Lake Erie & Western Railroad v. Hennessey
97 N.E. 331 (Indiana Supreme Court, 1912)
Ittenbach v. Thomas
96 N.E. 21 (Indiana Court of Appeals, 1911)
United States Cement Co. v. Koch
85 N.E. 490 (Indiana Court of Appeals, 1908)
Grand Trunk Western Railway Co. v. Melrose
78 N.E. 190 (Indiana Supreme Court, 1906)
Evansville Gas & Electric Light Co. v. Raley
76 N.E. 548 (Indiana Court of Appeals, 1905)
Chicago, Indianapolis & Louisville Railway Co. v. Barnes
73 N.E. 91 (Indiana Supreme Court, 1905)
Indianapolis & Greenfield Rapid Transit Co. v. Foreman
69 N.E. 669 (Indiana Supreme Court, 1904)
Chicago & Bloomington Stone Co. v. Nelson
69 N.E. 705 (Indiana Court of Appeals, 1904)