Penns Valley Area School District v. Mid-State Construction Inc.

14 Pa. D. & C.5th 273
CourtPennsylvania Court of Common Pleas, Centre County
DecidedJuly 29, 2010
Docketno. 2008-5382
StatusPublished
Cited by1 cases

This text of 14 Pa. D. & C.5th 273 (Penns Valley Area School District v. Mid-State Construction Inc.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Centre County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Penns Valley Area School District v. Mid-State Construction Inc., 14 Pa. D. & C.5th 273 (Pa. Super. Ct. 2010).

Opinion

RUEST, J.,

Presently before the court are a motion for summary judgment filed by defendant Mid-State Construction Inc., amotion for summary judgment filed by third-party defendant Action Floor Systems LLC, and a motion in limine to preclude evidence concerning the defective nature of the gymnasium floor and responsibility therefore filed by plaintiff Penns Valley Area School District. Oral argument was held on June 3, 2010. Upon consideration of the briefs, arguments, and relevant case law, the court determines as follows:

BACKGROUND

This matter arises out of a dispute over responsibility for the replacement and costs associated with an allegedly defective gymnasium floor. In or about 2004, Penns Valley contracted with Mid-State, a general contractor, [275]*275to commence several construction projects which included renovations and additions to the Penns Valley Elementary School Building. Construction at the elementary school building included the installation of a new hardwood gymnasium floor. Third-party defendant Chambers & Sons Hardwood Flooring Inc. entered a sub-contract with Mid-State to install the gymnasium floor. Flooring materials were supplied by Action. The applicable contract documents between Penns Valley and Mid-State included a special project warranty for the gymnasium floor and a number of special instructions pertaining to installation of the floor.

Chambers completed installation of the gymnasium floor in or about February of2005. Penns Valley subsequently advised Mid-State that the floor was defective, but Penns Valley was willing to conditionally accept the floor if Mid-State would extend the warranty on materials and workmanship. Mid-State, Chambers and Action agreed to offer an extended warranty. In or about February of 2006, Penns Valley informed Mid-State that the flooring was unacceptable. After remedial efforts by Chambers proved unsuccessful, Penns Valley rejected the floor and directed Mid-State to submit a plan for the removal and replacement of the flooring. Mid-State subsequently demanded arbitration, complaining Penns Valley was illegally withholding money owed on the project.

At arbitration, the arbitrator heard expert testimony regarding the gymnasium floor and conducted a site visit attended by all parties. Chambers and Action participated in the proceedings as witnesses for Mid-State. The arbitrator found the floor was defective, due to [276]*276Chambers’ failure to comply with installation specifications, but awarded judgment in favor of Mid-State because Penns Valley had accepted the floor in exchange for the extended warranty. The arbitrator determined Penns Valley could seek full replacement of the floor under its initial warranty or the extended warranty, but did not enter an award to this effect because Penns Valley never filed a counterclaim or demand for affirmative relief.

Following arbitration, Penns Valley demanded replacement of the gymnasium floor and, in April of2008, notified Mid-State, Chambers and Action that it considered them in default. When no action was taken, Penns Valley began advertising for bids. Chambers eventually replaced the floor, with the exception of the section under the gymnasium bleachers. Penns Valley filed a complaint against Mid-State seeking reimbursement for costs and expenses associated with replacement of the floor, including costs incurred in connection with the arbitration proceedings and current litigation, as well as the future costs and expenses it will incur to replace the section of the floor under the bleachers.

PROCEDURAL HISTORY

Plaintiff initiated this lawsuit by filing a complaint against Mid-State on December 11,2008. Mid-State filed an answer with new matter on January 15, 2009. Mid-State additionally filed a third-party complaint on January 29, 2009, naming Chambers and Action as third-party defendants. Chambers filed an answer with new matter on March 30, 2009 and Action filed an answer with new matter on March 31,2009. Mid-State and Ac[277]*277tion each filed a motion for summary judgment on April 23, 2010, and Penns Valley filed a motion in limine the same day. Mid-State filed an answer to Action’s motion for summary judgment, Penns Valley filed an answer to Mid-State’s motion for summary judgment, and Action filed a brief in opposition to Penns Valley’s motion in limine. Chambers did not file a response to any of the motions.

DISCUSSION

I. Defendant Action Floor Systems LLC’s Motion for Summary Judgment

Under the Pennsylvania Rules of Civil Procedure, summary judgment may be granted where “an adverse party who will bear the burden of proof at trial has failed to produce evidence of facts essential to the cause of action or defense which in a jury trial would require the issues to be submitted to a jury.” Pa.R.C.P. 1035.2. Action avers there is no genuine issue of material fact as to the necessary elements of the causes of action asserted by Mid-State because there is no evidence or allegation that the materials provided by Action were defective, or that the failure of the floor to meet project specifications was caused by Action’s conduct.

Mid-State claims if it is deemed liable to Penns Valley, Mid-State is entitled to contribution and indemnity from Action. To recover under either theory, Mid-State must establish Action bears responsibility for the failure of the gymnasium floor. See City of Wilkes-Barre v. Kaminski Brothers Inc., 804 A.2d 89, 92 (Pa. Commw. 2002) (indemnity shifts responsibility from a party held [278]*278liable to the party whose conduct actually caused the loss); see also, Brown v. Dickey, 397 Pa. 454, 155 A.2d 836 (1959) (“The right to contribution is an equitable right based on common liability to the plaintiff.”). However, neither Mid-State nor Penns Valley has alleged or provided evidence that the materials provided by Action were defective or that the defective condition of the floor was caused by Action’s conduct. At most, Mid-State and Penns Valley allege Action provided technical advice to Chambers. This advice, however, was rendered after the floor was considered defective and neither Mid-State nor Penns Valley claims Action’s advice contributed to the defective condition. Additionally, in its motion in limine, Penns Valley maintains improper installation was the sole cause of the problem, as found by the arbitrator.

Where the non-moving party fails to adduce sufficient evidence on an issue essential to his case such that a jury could return a verdict in his favor, there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Ertel v. Patriot-News Company, 544 Pa. 93, 95, 674 A.2d 1038, 1042 (1996). As Mid-State has not adduced evidence that Action caused or contributed to the defective condition of the gymnasium floor, Mid-State’s claim for contribution and indemnification cannot withstand summary judgment.

Mid-State also seeks recovery against Action for breach of express warranty, breach of the implied warranty of merchantability and breach of implied warranty of fitness for a particular purpose. These claims also cannot survive summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hernandez, M. v. E Trade Securities
Superior Court of Pennsylvania, 2016

Cite This Page — Counsel Stack

Bluebook (online)
14 Pa. D. & C.5th 273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/penns-valley-area-school-district-v-mid-state-construction-inc-pactcomplcentre-2010.