Penneys Construction Company LLC v. Ducci Electrical Contractors, Inc.

CourtDistrict Court, D. Connecticut
DecidedJuly 18, 2024
Docket3:22-cv-00524
StatusUnknown

This text of Penneys Construction Company LLC v. Ducci Electrical Contractors, Inc. (Penneys Construction Company LLC v. Ducci Electrical Contractors, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Penneys Construction Company LLC v. Ducci Electrical Contractors, Inc., (D. Conn. 2024).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF CONNECTICUT PENNEY’S CONSTRUCTION ) 3:22-CV-00524 (SVN) COMPANY, LLC, ) Plaintiff, ) ) v. ) ) DUCCI ELECTRICAL CONTRACTORS, ) INC., ) Defendant. ) July 18, 2024 RULING AND ORDER ON DEFENDANT’S MOTION FOR SUMMARY JUDGMENT Sarala V. Nagala, United States District Judge. In this action, Plaintiff Penney’s Construction Company, LLC (“Penney’s”), the subcontractor on a federally-funded roadwork project, alleges that Defendant Ducci Electrical Contractors, Inc. (“Ducci”), the general contractor on the project, intentionally discriminated against it on the basis of race when it terminated Penney’s from the project and hired another subcontractor. Plaintiff brings racial discrimination claims pursuant to 42 U.S.C. § 1981 and Title VI of the Civil Rights Act of 1964, 42 U.S.C. § 2000d et seq., in addition to a common law breach of contract claim and a claim for violation of the Connecticut Unfair Trade Practices Act (“CUTPA”), Conn. Gen. Stat. § 42-110a et seq. Defendant brings counterclaims for breach of contract and anticipatory breach by repudiation. Am. Answer, ECF No. 20 at 10. Defendant seeks summary judgment on all of Plaintiff’s claims, contending Plaintiff has not established a material factual dispute, primarily regarding whether Ducci intentionally discriminated on the basis of race. For the reasons set forth below, Defendant’s motion is GRANTED. I. FACTUAL BACKGROUND1 On May 5, 2021, Defendant, a general contractor, prepared and filed a bid to perform the work necessary to complete a project, entitled Coordinated Traffic Signal System (“CTSS”) and Connected Vehicle Technology – Phase I, State Project No. 0070250 (the “Project”), for the

Connecticut Department of Transportation (“ConnDOT”). Pl.’s L.R. 56(a)2 St. ¶ 3. It was awarded the contract, as it was the low bidder. See id. By regulation, companies engaged in certain transit projects funded at least in part by the federal government must engage the services of Disadvantaged Business Enterprises (“DBEs”). 49 C.F.R. § 26. A DBE is a “for-profit small business concern – (1) That is at least 51 percent owned by one or more individuals who are both socially and economically disadvantaged; and (2) Whose management and daily business operations are controlled by one or more of the socially and economically disadvantaged individuals who own it.” 49 C.F.R. § 26.5. For the Project, Ducci was required to utilize one or more DBEs to perform work with more than 6% of the value of the Project contract. Pl.’s L.R. 56(a)2 St. ¶ 4. Ducci was entitled to use any DBE it chose, regardless

of price, subject to certain requirements. Id. ¶ 7. Accordingly, Ducci solicited bids from various DBEs based on the list of DBEs compiled by ConnDOT. Id. ¶ 3. Penney’s is a DBE as that term is used and defined in 49 C.F.R. § 26.5; it is owned by Preston Neal, a Black man. Id. ¶ 2. Penney’s submitted a bid to Ducci to perform specific items of work on the Project relating to concrete curbing, sidewalks, and ramps. Id. ¶ 9. Another DBE, Star Construction Corporation (“Star”), which is owned by a white female, also provided a bid to Ducci. Id. ¶ 8. Plaintiff was selected for the Project and, on June 28, 2021, electronically signed

1 The factual background is taken primarily from Plaintiff’s Local Rule 56(a)2 Statement, ECF No. 51-1 (“Pl.’s L.R. 56(a)2 St.”). The facts are undisputed, unless otherwise indicated. a subcontract with Ducci. Id. ¶ 5. ConnDOT approved the requisite forms and the hiring of Penney’s, which was required before work could commence. Id. ¶¶ 11, 13. Over the course of the next several months, numerous issues arose between Penney’s and Ducci regarding the scope of work to be performed by Penney’s, resulting in no work being

performed by Penney’s on the Project at any time through February 2, 2022. Id. ¶ 25. The largest issue appears to have been the use of concrete that was precast, as opposed to being poured or cast in place. There is no dispute that pour-in-place concrete is more expensive. Penney’s contends that the contract initially allowed for all precast concrete curbing, which was the basis for its bid. See Def.’s Mot. for Summ. J. App’x, ECF No. 40-1 at 108, 111, Neal Tr. 22:2–19, 33:12–21. Penney’s claims that, after the contract was signed, and a few weeks after their initial September 2021 meeting, the scope of work changed when Penney’s was informed of the need for more pour- in-place concrete than it had anticipated. Neal Tr., ECF No. 40-1 at 111, 118, 145, 33:12–21, 61:23–62:3, 169:29–170:6. This issue, in addition to the need for winter work and other issues regarding curb radii, led Penney’s to request more money to complete the Project. Id. at 126,

95:16–22. For its part, Ducci contends that the Project specifications never changed, and a “fast- track schedule” provided to Plaintiff prior to signing the subcontract clearly identified “the need for winter work/concrete.” See, e.g., ECF No. 40-1 at 409 (Ducci’s December 13, 2021, letter to Penney’s detailing Ducci’s position). On October 26, 2021, Ducci sent Penney’s photos of work locations that Ducci contended would be ready for Penney’s to start work on as of November 3, 2021. Pl.’s L.R. 56(a)2 St. ¶ 21. Penney’s disputes that the sites were ready. Id.; Neal Aff., ECF No. 51-2, ¶¶ 5–10.2 The same day, Penney’s contacted Ducci and Debra Goss, a director of the ConnDOT Office of Contract Oversight responsible for oversight of the DBE program, stating that a change order was necessary for the cost associated with winter conditions. Pl.’s L.R. 56(a)2 St. ¶¶ 10, 23.

The parties’ contract contains the following provision concerning the subcontractor’s failure to perform: If, in the opinion of the Contractor, the Subcontractor shall at any time . . . (2) fail or neglect in any respect to prosecute the Work according to the Project Schedule or the Subcontract Documents; . . . [or] (4) fail to comply with any provision of this Subcontract or the Subcontract Documents,” [Ducci could provide three calendar days’ notice that it would, at its option] “(i) take such steps as are necessary to overcome the conditions, in which case the Subcontractor shall be liable to the Contractor for the cost thereof; (ii) terminate for default the Subcontractor’s right to proceed under the Subcontract; or (iii) seek specific performance of the Subcontractor’s obligations hereunder.

ECF No. 40-1 at 335. On December 13, 2021, Ducci sent Penney’s a default letter, outlining the reasons why Ducci believed Penney’s was in breach of contract, and demanding Penney’s commence work. Pl.’s L.R. 56(a)2 St. ¶ 27. On January 11, 2022, Ducci sent Penney’s a formal notice of intent to terminate the contract in five days, subject to the approval of ConnDOT. Id. ¶ 31. Penney’s sent a letter in response, which did not raise the issue of discrimination of any kind. Id. ¶ 33. On January 14, 2022, Ducci sent another letter acknowledging receipt of Plaintiff’s letter, referencing Plaintiff’s request for a change order adding $130,000 to its subcontract, and

2 Throughout the Local Rule Statement, Penney’s “admits” that certain statements were made in Neal’s deposition, but denies other elements of the statements, pointing to an affidavit from Neal. See, e.g., Pl.’s L.R. 56(a)2 St. ¶¶ 42– 44.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McDonnell Douglas Corp. v. Green
411 U.S. 792 (Supreme Court, 1973)
Texas Department of Community Affairs v. Burdine
450 U.S. 248 (Supreme Court, 1981)
Kremer v. Chemical Construction Corp.
456 U.S. 461 (Supreme Court, 1982)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
University of Tennessee v. Elliott
478 U.S. 788 (Supreme Court, 1986)
Carnegie-Mellon University v. Cohill
484 U.S. 343 (Supreme Court, 1988)
Ruiz v. County of Rockland
609 F.3d 486 (Second Circuit, 2010)
Shelley Weinstock v. Columbia University
224 F.3d 33 (Second Circuit, 2000)
Reeves v. Sanderson Plumbing Products, Inc.
530 U.S. 133 (Supreme Court, 2000)
Naples v. Keystone Building & Development Corp.
990 A.2d 326 (Supreme Court of Connecticut, 2010)
Bridgeport Guardians, Inc. v. Delmonte
553 F. Supp. 601 (D. Connecticut, 1983)
Perry v. Manocherian
675 F. Supp. 1417 (S.D. New York, 1987)
Chance v. Reed
538 F. Supp. 2d 500 (D. Connecticut, 2008)
Jackson v. University of New Haven
228 F. Supp. 2d 156 (D. Connecticut, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Penneys Construction Company LLC v. Ducci Electrical Contractors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/penneys-construction-company-llc-v-ducci-electrical-contractors-inc-ctd-2024.