Penn-Dixie Steel Corp. v. Occupational Safety And Health Review Commission

553 F.2d 1078, 5 OSHC (BNA) 1315, 1977 U.S. App. LEXIS 13613
CourtCourt of Appeals for the Seventh Circuit
DecidedApril 29, 1977
Docket75-1819
StatusPublished

This text of 553 F.2d 1078 (Penn-Dixie Steel Corp. v. Occupational Safety And Health Review Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Penn-Dixie Steel Corp. v. Occupational Safety And Health Review Commission, 553 F.2d 1078, 5 OSHC (BNA) 1315, 1977 U.S. App. LEXIS 13613 (7th Cir. 1977).

Opinion

553 F.2d 1078

5 O.S.H. Cas.(BNA) 1315, 1977-1978 O.S.H.D. ( 21,780

PENN-DIXIE STEEL CORP. (formerly Continental Steel
Corporation), Petitioner,
v.
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION and John T.
Dunlop, Secretary of Labor, Respondents.

No. 75-1819.

United States Court of Appeals,
Seventh Circuit.

Argued April 12, 1976.
Decided April 29, 1977.

Ronald Clay Bennett, Joseph E. O'Leary, Chicago, Ill., George Preonas, Los Angeles, Cal., for petitioner.

Nancy L. Southard, U. S. Dept. of Labor, Washington, D. C., for respondents.

Before FAIRCHILD, Chief Judge, BAUER, Circuit Judge, and CAMPBELL, Senior District Judge.*

WILLIAM J. CAMPBELL, Senior District Judge.

Penn-Dixie Steel Corp. (Penn-Dixie) petitions this court to review an order of the Occupational Safety and Health Review Commission affirming a penalty assessed by the Secretary of Labor (Secretary) under the Occupational Safety and Health Act of 1970 (OSHA). 29 U.S.C. § 651 et seq.

The record indicates that Penn-Dixie is a large corporation which makes steel and steel products at its Kokomo, Indiana plant. On April 19, 1973, respondent Secretary made a physical inspection of the Penn-Dixie facility in Kokomo. This inspection included noise level readings in the Melt Shop Charging Floor Area, the Barbed Wire Area and the Nail Mill. In all three of these areas, the noise levels exceeded the amounts allowed in Table G-16 of 29 CFR 1910.95.

As a result of this inspection, on May 7, 1973, the Secretary cited Penn-Dixie for one serious and two nonserious violations.** Specifically, the Secretary charged Penn-Dixie with failure to comply with the standards relating to employee protection against noise exposure, failure to implement feasible engineering and administrative controls to reduce noise levels, and failure to ventilate adequately its galvanizing operation. The Secretary served Penn-Dixie with proposed penalties of $600, $150, and $150 for each respective violation, and established the dates on which the violations were to be abated.

In a cover letter transmitting the citations and proposed penalties, the Secretary advised Penn-Dixie that it had the right to contest the citations, proposed penalties, or both before the Occupational Safety and Health Review Commission. The transmittal letter then stated the following:

"If you do contest, you must so notify the Area Director within 15 working days after receipt of the certified mail notice regarding proposed penalties. If you fail to contest within 15 working day period, the citation and proposed assessment of penalties shall be deemed to be a final order not subject to review by any court or agency."

The concluding paragraph of a document entitled "Notification of Proposed Penalty," states as follows in relevant part:

". . . (The) Citations, this Notification, and the proposed assessment shall be deemed to be the final order . . . and not subject to review by any court or agency, unless, within 15 working days from the date of receipt of this notice, you notify the official named below in writing that you intend to contest the Citation or this Notification of Proposed Penalty before the Review Commission. . . ." (Emphasis in original).

The above quoted paragraphs advised the employer of his rights under 29 U.S.C. § 659(a).

The record indicates that Penn-Dixie Vice President Downing wrote to the Area Director on May 22, 1973, requesting an extension of the date by which several of the alleged violations were to be corrected. The Area Director complied with this request by issuing amended citations reflecting the extended abatement dates sought by Penn-Dixie.

The record further shows that on May 29, 1973, Penn-Dixie's manager of employee relations Shively, on behalf of Downing, sent a letter to the Area Director. The first sentence of the letter indicates Penn-Dixie's protest of the penalties assessed as a result of the inspection. The letter then details Penn-Dixie's position with respect to the cited violations, and concludes that "the penalty assessed appears to be for our failure to do what no one else has been able to do so far."

The Secretary interpreted this letter as a contest only of the proposed penalties, and not of the underlying citations. To confirm this interpretation, the Secretary's regional attorney telephoned Shively and asked if Penn-Dixie only meant to contest the proposed penalties. He received an answer to the effect that Penn-Dixie's contest was in reference to the amount of the penalties.

Pursuant to 29 U.S.C. § 659(c), the Secretary transmitted the contest to the Occupational Safety and Health Review Commission (Commission), and filed a formal complaint alleging that the contest was limited to certain penalties, that the penalties were proper, and that the citations underlying the penalties had become final by operation of law. Penn-Dixie, through Downing, timely filed an answer to the complaint in the form of a letter addressed to the Commission. The letter denied the allegations of the three violations in issue here, and attacked the propriety of the proposed penalties, but did not deny the allegation that the underlying violations were not before the Commission. Thereafter, Penn-Dixie, through counsel, filed an Amended Answer contesting both the penalties proposed and the underlying citations.

The Secretary moved to strike the Amended Answer on the grounds that the Commission was without jurisdiction to adjudicate the underlying violations because Penn-Dixie's notice of contest was limited to the proposed penalties. The Administrative Law Judge, finding the intent of the May 29, 1973 Shively letter of protest sufficiently ambiguous to support an inference that the citations, as well as the penalties, were contested, denied the motion to strike.

At the hearing held on December 4, 1973, the Secretary introduced evidence supporting the proposed penalties. With respect to the violations which formed the basis for the citations, the Secretary introduced no evidence establishing an affirmative case regarding the availability of feasible engineering controls. Rather, the Secretary indicated to the Administrative Law Judge that he intended to "stand on the point that the contest was directed to the penalty, not to the citation. . . ." At the hearing, the Secretary called Shively as a witness and the following colloquy took place:

Q. Now, with reference to the first of these letters, letter dated May 29, 1973, do you recall that after submitting that, and within the fifteen working day period for contest that I called the Respondent on the phone and spoke to you?

A. Yes, I recall that.

Q.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
553 F.2d 1078, 5 OSHC (BNA) 1315, 1977 U.S. App. LEXIS 13613, Counsel Stack Legal Research, https://law.counselstack.com/opinion/penn-dixie-steel-corp-v-occupational-safety-and-health-review-commission-ca7-1977.