Pell v. Baur

16 N.Y.S. 258, 41 N.Y. St. Rep. 99, 1891 N.Y. Misc. LEXIS 406
CourtNew York City Court
DecidedNovember 23, 1891
StatusPublished

This text of 16 N.Y.S. 258 (Pell v. Baur) is published on Counsel Stack Legal Research, covering New York City Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pell v. Baur, 16 N.Y.S. 258, 41 N.Y. St. Rep. 99, 1891 N.Y. Misc. LEXIS 406 (N.Y. Super. Ct. 1891).

Opinion

Osborne, J.

This action was brought to foreclose a mechanic’s lien filed by plaintiffs, and the defendant Baur appeals from so much of the judgment rendered by the special term of this court as decrees that plaintiffs have a lien next in priority to that of the defendant Tweed, to the extent of $2,002.68, and interest on the fund deposited in court by the defendant Schloen, who was the owner of the premises affected by the liens filed by plaintiffs and the other defendants. It appears from the case on appeal that on August 18, 1890, the defendants Matthew Thornton and Christian Baur entered into a written contract with the defendant Schloen to erect and finish the new buildings on the south-east corner of Hall street and Saratoga avenue, in this city, agreeable to architect’s drawings and specifications, and to provide all material proper and sufficient for the completing and finishing “all the mason, iron, carpenter, tinner, painter, plumber, and other works of the said buildings,” for the sum of $19,050, to be paid in seven different installments, as provided in said contract; that between September 2, 1890, and January 16, 1891, plaintiffs sold to defendant Thornton lumber and timber used in the erection of said buildings, to the amount of $2,002.68; that on January 19, 1891, at 9:04 A. M., plaintiffs filed the notice of lien sought to be foreclosed herein for the lumber and timber so furnished by them. The defendant Baur, in his answer, sets up that he is a mason, and defendant Thornton is a carpenter; that he furnished an estimate to the owner for the furnishing of all the brick, stone, and mason work for the buildings, and that defendant Thornton likewise furnished an estimate to the owner to furnish all the carpenter, plumber, tinner, painter, and other work upon said buildings; that the estimates of both Baur and Thornton were separately accepted by the owner; that, for the convenience of all parties, only one contract was made and drawn between the owner, of the first part, and said Baur and Thornton, of the second part, which included the entire work upon the buildings, but that the interests of Baur and Thornton were separate and distinct; that, as the work progressed, the owner paid to Thornton and to Baur the amounts coming to each of them, according to their respective estimates for the work done [260]*260by them severally; denies that he ever purchased any lumber or timber from the plaintiffs; that on January 17, 1891, Baur and Thornton executed a notice of lien for $5,050, the balance due and unpaid under said contract; that immediately thereupon Thornton assigned all his interest in said notice of lien, and the moneys due thereunder, to defendant Baur, and Baur then executed an agreement to pay, out of the moneys received by him under said notice of lien, the sum of $2,700, alleged to be the balance coming to Thornton, to various material-men to whom Thornton was indebted; that on January 19, 1891, at 9:01 a. m., said notice of lien and the assignment thereof were duly filed. Baur then prays judgment of foreclosure of the lien of Thornton and Baur, so filed by him, as a first lien. The defendant Schloen paid into court the sum of $4,532, which was accepted in discharge of the liens filed against his premises. Defendant Hilzinger, a subsequent lienor, made default in pleading. The judgment rendered provided for the payment of the lien filed by defendant Tweed as a first claim on the fund paid into court, and no exception is taken thereto. The judgment further provided that, out of the moneys so deposited in court, there should next be paid to plaintiffs the sum of $2,002.68, with interest and costs, and that defendant Baur is entitled to the balance. The contention of the defendant Baur is that, out of the funds so deposited as aforesaid, there was due to the defendant Thornton, on his separate estimate, a balance of $2,182, and to the defendant Baur, on his separate estimate, the sum of $2,850; and that, by the filing of the notice of lien by Thornton and Baur three minutes before that of plaintiffs’, and the assignment by Thornton to Baur of Thornton’s interest in their notice of lien, as well as by reason of the imperfections of plaintiffs’ lien, Baur became entitled to a judgment in his favor for the whole of said deposit, less the amount of Tweed’s lien, and this appeal, as before stated, is from so much of the judgment as gives plaintiffs a priority of payment over Baur.

The learned trial judge has found that the defendants Thornton and Baur were partners in the erection of the buildings in question. Exception is taken by the appellant Baur to this finding, and it is very plain that the judgment in favor of plaintiffs is largely dependent upon the correctness of this conclusion. It appears from the evidence, and is so found, that, prior to the execution of the written contract, Schloen, the owner, received a written estimate from Thornton to furnish all the carpenter, timber, plaster, and painter’s work for the buildings for $9,800, and that he also received from Baur a written estimate to furnish all the mason,- iron, and brick work for $9,250, and that Schloen accepted these estimates. The testimony shows that the owner, Schloen, met Baur and Thornton at the house of Mr. Vollweiler, the architect, by appointment, to sign agreements. Mr. Vollweiler testifies: “I commenced to figure out how much each one v, ould get when he had certain work completed. Then those gentlemen told me that they would not put me to that great bother to figure out everything separately; that they wanted to get through quick; and that I should write out the estimates for both in one agreement. Question by the Court. They would take one contract ? Answer. Yes, sir; one contract. Q. And that is the way that contract came to be made ? A. That is the way it came. ” The owner testified that he made payments, as the work progressed, to either Baur or Thornton, on the order of the architect. “Question. Did Thornton and Baur tell you that, when a payment was earned under this contract, it made no difference to whom you paid the money, whether it was to Thornton or Baur ? Answer. Well, they said that, if the money should be paid, they would divide it among themselves. Q. Did they tell you that, when a payment was made due under this contract, it did not make any difference who you paid it to,—whether you paid it to Thornton ortoBaur? A. Well, they said that to me; yes, sir.” Baur testifies that there was no understanding between him and Thornton about dividing the money on the payments, except that he was to get $9,800, and Thornton was to get [261]*261$9,250, and that they did not intend to be partners. The installments to be paid under the contract, it is well to note, are in such amounts as not to be susceptible of application to make up the amount of the estimate or offer of either Baur or Thornton without dividing them up, and the periods in the progress of the work designated for the maturity of the several installments, in almost every case, involve and require the performance of mason as well as carpenter work. When Baur and Thornton made out their notice of lien, they described themselves, as the contractors who had performed the work and furnished the materials, and they described their claim as arising under the written agreement of August 13,1890, by which they were to be paid $19,050, and that there remained unpaid the sum of $5,250. This notice of lien was signed and verified by both of them, and there is not an intimation in it of each of them having a separate contract with the owner, and being, respectively, entitled to balances due on such separate contracts, as Baur now claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
16 N.Y.S. 258, 41 N.Y. St. Rep. 99, 1891 N.Y. Misc. LEXIS 406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pell-v-baur-nycityct-1891.