Peggy Hartman D/B/A Hartman Homes v. P. J. Norman

CourtCourt of Appeals of Texas
DecidedOctober 19, 2017
Docket09-16-00333-CV
StatusPublished

This text of Peggy Hartman D/B/A Hartman Homes v. P. J. Norman (Peggy Hartman D/B/A Hartman Homes v. P. J. Norman) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peggy Hartman D/B/A Hartman Homes v. P. J. Norman, (Tex. Ct. App. 2017).

Opinion

In The

Court of Appeals Ninth District of Texas at Beaumont ____________________

NO. 09-16-00333-CV ____________________

PEGGY HARTMAN D/B/A HARTMAN HOMES, Appellant

V.

P.J. NORMAN, Appellee __________________________________________________________________

On Appeal from the 136th District Court Jefferson County, Texas Trial Cause No. D-191,942 __________________________________________________________________

MEMORANDUM OPINION

After conducting a bench trial in a breach of contract case concerning a

residential construction contract, the trial court made findings of fact and

conclusions of law and rendered judgment in favor of appellee, P.J. Norman. In a

single issue, appellant, Peggy Hartman d/b/a Hartman Homes, complains that the

trial court erred in concluding that the Texas Construction Trust Fund Act (“CTRA”)

imposed a duty on Hartman to provide an accounting to Norman. We affirm the trial

court’s judgment.

1 BACKGROUND

In April 2011, Norman contracted with Hartman to remodel and construct

additions to her existing home for a fixed contract amount of $250,000. Norman’s

counsel introduced into evidence a copy of the construction contract, which did not

include Hartman’s signature. The contract provides that the purchase price of the

project shall be set at $250,000, “subject to additions and deductions pursuant to

authorized change orders and allowances.” The contract specifies that all change

orders to the original plan “need to be agreed upon, including cost, additional time

considerations, approximate dates when the work will begin and be completed, a

legal description of the location where the work will be done and signed by both

parties.” The contract provides that “[t]he Owner will make payments to the

contractor pursuant to the attached construction draw schedule as work required by

said schedule is satisfactorily completed.” The contract further provides that if

“payment is not received by the Contractor within (3 days) . . . after delivery of

payment demand for work satisfactorily completed, contractor shall have the right

to stop work or terminate the contract at his option.”

In February 2012, Norman filed suit against Hartman, alleging that Hartman

had breached the contract by failing to complete the renovations as provided in the

contract. Specifically, Norman alleged that after she paid Hartman over $200,000,

2 Hartman had only completed a small portion of the renovations they agreed upon.

Norman requested that Hartman provide an accounting of the monies spent on the

renovations. Norman pleaded that Hartman never provided an accounting and failed

to finish the renovations, so Norman was forced to hire a new contractor to finish

the project. Norman sought actual damages and attorney’s fees. Hartman filed an

answer denying Norman’s allegations and a counter-petition alleging that Norman

breached the contract by failing to abide by its terms, thereby prohibiting Hartman

from completing the project.

During trial, Norman testified that the construction project included adding

approximately 5500 square feet to her current home, and that the scope of the work

included building a three-car garage, a garage for a forty-foot motorhome, and a pool

house, as well as adding two bedrooms and two bathrooms, remodeling a bathroom,

and knocking out a wall. Norman testified that she provided Hartman with two sets

of plans that showed the work that needed to be done, and Hartman gave her a

contract indicating that Hartman could complete the job for $250,000. According to

Norman, Hartman’s bid included both sets of plans, and while the second set of plans

included additional square footage, Norman maintained that she did not significantly

change the square footage of the job after receiving Hartman’s bid.

3 Norman testified that she paid a $50,000 deposit before Hartman began

construction, and that the deposit was part of the purchase price of the project.

Norman explained that although Hartman did not present her with a construction

draw schedule indicating when payments were to be paid, Norman paid Hartman an

additional $150,000. Norman testified that she paid Hartman a total of $200,000

without ever seeing a draw schedule indicating the percentage of work that Hartman

had completed. Norman also testified that she did not question Hartman because

they were friends and she thought Hartman was honest.

Norman explained that during construction, she had made a few changes to

the original plans. Concerning the bathroom remodel, Norman’s changes included

painting the bathroom, upgrading to a Jacuzzi tub, and updating the bathroom light

fixtures. Norman’s other changes included extending her closet out to the end of the

garage, switching to French doors in the breakfast room, and constructing a fence,

an outdoor fireplace, and a brick wall to cover the pool equipment. Norman testified

that she and Hartman never discussed the cost of the change orders or put them in

writing, but Norman estimated that the value of those changes was approximately

$6000.

Norman testified that after she paid Hartman $200,000, Hartman requested an

additional $50,000, and at that point, Norman asked Hartman to provide an

4 accounting. According to Norman, before signing the contract, Hartman had assured

her that Hartman could provide an accounting at any point during construction.

Norman explained that she asked for the accounting because, based on the work that

had been completed, she did not believe that Hartman had spent $200,000 on her

home. Norman testified that she interpreted the phrase “satisfactorily completed” to

mean that she needed to be satisfied with the work that had been done before she

released the final payment. Norman explained that she withheld the final payment

because, based on the progress of the job, she did not believe that Hartman had done

enough work. According to Norman, in asking for an accounting, she was requesting

that Hartman provide her with the construction draw schedule so she could

determine what percentage of work had actually been completed.

Norman maintained that she complied with the contract when she requested

an accounting. Norman testified that Hartman never provided an accounting of

invoices for the $200,000; instead, Hartman provided an invoice for add-ons, some

of which Norman disputed. Norman also testified that she never agreed to verbally

make change orders under the contract. Norman explained that after she and

Hartman argued over the accounting, she refused to give Hartman more money, and

Hartman walked off and never finished the job. Norman maintained that she wanted

5 Hartman to finish the job, but she had to pay other contractors to complete the

project.

Norman presented evidence showing that it cost her $236,677.51 to finish the

job after Hartman left, and she testified that other than some changes to the cabinetry

in the master bathroom, she finished the project just as Hartman would have.

Norman sought damages amounting to the difference between the amount she paid

contractors to finish the job and the amount she would have paid Hartman under the

contract.

Hartman testified that she bid the project on the first set of plans, which did

not include a shop or the garage for the motorhome. Hartman explained that she had

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
Weinberger v. Longer
222 S.W.3d 557 (Court of Appeals of Texas, 2007)
Joe Kenny v. Portfolio Recovery Associates, LLC
464 S.W.3d 29 (Court of Appeals of Texas, 2015)
Direct Value, LLC and Martin F. Cody, Jr. v. Stock Building Supply, LLC
388 S.W.3d 386 (Court of Appeals of Texas, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Peggy Hartman D/B/A Hartman Homes v. P. J. Norman, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peggy-hartman-dba-hartman-homes-v-p-j-norman-texapp-2017.