Peerless Woolen Mills v. Chicago Garment Co.

79 N.W.2d 500, 347 Mich. 326
CourtMichigan Supreme Court
DecidedDecember 6, 1956
DocketDocket No. 57, Calendar No. 46,180
StatusPublished
Cited by1 cases

This text of 79 N.W.2d 500 (Peerless Woolen Mills v. Chicago Garment Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peerless Woolen Mills v. Chicago Garment Co., 79 N.W.2d 500, 347 Mich. 326 (Mich. 1956).

Opinion

Carr, J.

Plaintiff brought this action to recover for goods sold and delivered to defendant under an agreement made in May, 1950. The merchandise in question was purchased to be made into hunting coats, trousers and caps, which were designed for sale to others handling such articles. It was agreed between the parties that credit in the sum of $5,000 would be extended to defendant. The proofs indicate that plaintiff shipped goods to defendant on 6 occasions, and that prior to the termination of said contract payment for 3 of said shipments was made, but apparently not within the time limit fixed by the contract. However, the shipments thus paid for are not in issue in the present case.

It is conceded thát merchandise shipped on June 29th and 30th, and on August 15, 1950, was received by defendant, which failed to make payment. The total selling price of the said goods was the sum of $8,698.17. It further appears that a check in the [328]*328sum of $l,679.65 sent by defendant to plaintiff on or. about August 25, 1950, was returned by the bank on which it was drawn because of insufficient funds to honor it: Approximately a month later this check was redeposited. This incident and the failure of defendant to make remittances for the 3 shipments involved in the present case, together with its general lack of promptness, caused thé plaintiff to insist that defendant take care of the invoices for goods shipped in accordance with the agreement. Defendant failed to do so, and on October 6, 1950, plaintiff notified it that the contract was terminated. The instant case was instituted on November 24, 1950.

In its answer to plaintiff’s declaration defendant admitted the execution of the contract' and the’ receipt of the goods for which plaintiff sought, to .recover. However, it claimed that plaintiff wrongfully terminated the contract without completing .the shipments contemplated, that defendant was forced to purchase goods in the open market at an increased price, and that, it was unable to carry out its agreements with its customers. Defendant further pleaded that during the year 1949 it had purchased merchandise from plaintiff, for which it made payment,, that there .was a shortage in the, quantity of cloth actually delivered, and that in the action based on the 1950 agreement it was entitled to recoup damages because of the claimed shortage.. Defendant accordingly attached to its. answer a ■ counterclaim. The trial judge, hearing the case without a jury, rendered judgment for the plaintiff in the full amount, claimed by it. Defendant has appealed, contending that there should have been deducted from the. amount of plaintiff’s claim the- sum of $2,135 by way of damages sustained by defendant in being compelled to purchase materials for its use from other sources, and the further sum of $2,160 because of the. alleged shortage under the 1949 contract.

[329]*329The trial judge concluded from the proofs that under the circumstances the plaintiff was justified in cancelling the contract. The finding in this regard is fully supported by the record. Defendant claims that the agreement with reference to the credit terms granted to it was in effect waived because plaintiff allowed the amount of indebtedness to it to materially exceed the sum of $5,000. It may not be said, however, that, because of its failure to stop further shipments when the credit limitation was reached, plaintiff waived its rights under the contract. Obviously, such forbearance did not operate to the prejudice of defendant. The latter ignored requests for payment and, likewise, plaintiff’s assertion that, unless remittance was made for the goods shipped and received, in accordance with the contract, steps would be taken to compel payment. It is a matter of inference also that plaintiff’s action was prompted, in part, because of the check received by it, deposited in its account, and returned by the bank on ivhich it was drawn because of insufficient funds.

A situation analogous to that in the case at bar was presented in Lower v. Muskegon Heights Co-Operative Dairy, 251 Mich 450. There the parties entered into a contract for delivery of defendant’s dairy products by. plaintiff to his customers. It was specifically provided that plaintiff should make payment, for the goods received by him and disposed of, on 4 specified dates each month. Defendant terminated the agreement because of the failure of plaintiff to comply with the requirement, and the latter brought an action to recover damages for breach of contract. Defendant submitted a counterclaim for the price of products received by plaintiff and sold to his customers but for which he had not made payment. On appeal a judgment in plaintiff’s favor was reversed, this Court holding that under the circum[330]*330stances defendant was justified in refusing to continue under the contract. In discussing the situation it was said, in part (pp 454, 455):

“This contract by its clear and unequivocal terms required plaintiff to make payment in full 4 times each month, ‘for all goods sold’ by plaintiff. The fact that there was some laxity on defendant’s part in requiring payments strictly in accordance with the contractual provision did not render such provision nugatory. Upon notice to plaintiff, defendant had the right at any time to demand payment in conformity with the terms of the contract. Defendant’s repeated-demands constituted notice to plaintiff that it was insisting upon its contractual rights. Defendant not only demanded payment of plaintiff but requested him to meet with defendant’s manager relative to the arrearages, and .asked him to turn over his route-books for inspection as provided in his contract, all of which plaintiff refused to do. Plaintiff having thus violated the contract, the defendant was justified in declining to be bound thereby; and plaintiff has no right of action fo.r damages because defendant elected so to do. This result follows regardless of whether the contract be construed to be primarily oiie of sale or • one of agency. In either case the times when' payments should be made were definitely fixed by its terms. Appellant’s assignment of error asserting that it should have-had a directed verdict as to plaintiff’s alleged cause of action is well taken.”

Like considerations are applicable in the case at bart The fact that plaintiff was lenient in its dealings with defendant did not operate as a modification of the contract, or an absolute waiver as to future operations thereunder. It was entitled to insist on defendant’s compliance in making the payments that admittedly were past due. It will be noted that plaintiff’s action in terminating the contract was not predicated on the delay in paying for [331]*331other shipments but on failure to. meet the obligations resulting from the shipment and sale of the merchandise involved in this case.

' The facts involved in Gates v. Detroit & Mackinac R. Co., 147 Mich 523, cited by counsel for. appellant in their, brief, are not analogous to those in the case at bar. There plaintiff sued for damages for breach of a contract for the transportation .of forest products. Defendant pleaded that plaintiff had not, during-prior years in which the contract had been in force, complied with its terms as to the aggregate amount of such products that would be furnished for shipment each year. However, the proofs indicated- that defendant had treated the contract as severable, that it had failed to provide • adequate facilities. for shipping, and had by its conduct waived strict performance of plaintiff’s undertaking.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCoig Materials, LLC v. Galui Construction, Inc.
818 N.W.2d 410 (Michigan Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
79 N.W.2d 500, 347 Mich. 326, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peerless-woolen-mills-v-chicago-garment-co-mich-1956.