Pedernales Electric Cooperative, Inc.// Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon v. Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon//Cross-Appellee, Pedernales Electric Cooperative, Inc.

CourtCourt of Appeals of Texas
DecidedDecember 11, 2024
Docket03-22-00797-CV
StatusPublished

This text of Pedernales Electric Cooperative, Inc.// Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon v. Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon//Cross-Appellee, Pedernales Electric Cooperative, Inc. (Pedernales Electric Cooperative, Inc.// Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon v. Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon//Cross-Appellee, Pedernales Electric Cooperative, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pedernales Electric Cooperative, Inc.// Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon v. Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon//Cross-Appellee, Pedernales Electric Cooperative, Inc., (Tex. Ct. App. 2024).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-22-00797-CV

Appellant, Pedernales Electric Cooperative, Inc.// Cross-Appellants, Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon

v.

Appellees, Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon//Cross- Appellee, Pedernales Electric Cooperative, Inc.

FROM THE COUNTY COURT AT LAW NO. 2 OF HAYS COUNTY NO. 19-1250-C, THE HONORABLE ROBERT UPDEGROVE, JUDGE PRESIDING

MEMORANDUM OPINION

In this case involving an easement for an electric transmission line, appellant

Pedernales Electric Cooperative, Inc. (PEC) and cross-appellants Samuel S. White, Janette

Barlow, Gregory Colon and Stephanie Colon (the Landowners) appeal the trial court’s final

judgment issuing a permanent injunction prohibiting PEC from operating the electric

transmission line at an increased voltage and awarding damages and attorney’s fees to the

Landowners for breach of the easement. In five issues on appeal, PEC contends that the trial

court erred in: (1) interpreting the easement to disallow PEC from increasing the voltage of the

line; (2) issuing a permanent injunction against PEC to prevent it from operating the line at an

increased voltage; (3) awarding damages to the Landowners for breach of the easement;

(4) awarding an amount of damages to the Landowners that was not supported by the evidence;

and (5) awarding attorney’s fees to the Landowners. In a single issue on cross-appeal, the Landowners assert that the trial court erred in not disallowing PEC from engaging in other

actions associated with the increased voltage, such as building taller poles made of steel.

Because we agree with PEC that the increased voltage and PEC’s other challenged actions

associated with the increase did not violate the terms of the easement, we will reverse the trial

court’s judgment and render judgment that Landowners take nothing on their claims.

BACKGROUND

In 1968, the Landowners’ predecessors in title, J.B. and Katherine Winn,

conveyed to PEC an “easement and right of way” (the Winn Easement) “for an electric

transmission and/or distribution line, consisting of variable number of wires, and all necessary or

desirable appurtenances (including towers, H-frames or poles made of wood, metal or other

materials, telephone and telegraph wire, props and guys), over, across and upon” a sixty-foot-

wide strip of land, described by metes and bounds, running across the Landowners’ properties in

Hays County near Wimberley. The Winn Easement also granted to PEC:

the right of ingress and egress over [the] adjacent lands to or from said right of way for the purpose of constructing, reconstructing, inspecting, patrolling, hanging new wire on, maintaining and removing said lines and appurtenances; the right to relocate within the limits of said right of way; the right to remove from said lands all trees and parts thereof, or other obstructions, which endanger or may interfere with the efficiency of said lines or their appurtenances.

PEC subsequently constructed a four-mile, high-voltage, 69-kilovolt transmission line on

wooden poles that ran across numerous properties, including those belonging to the Landowners.

Today, this transmission line is the primary source of electricity for the Wimberley area.

Over time, Wimberley’s increasing demand for electricity significantly increased

the peak load requirements for PEC’s transmission system. In 2017, to meet the increased

2 demand, PEC sought approval from the Public Utility Commission (PUC) to upgrade its

transmission line, including the portion that runs across the Landowners’ properties, from a

69-kilovolt line to a 138-kilovolt line. The upgrade project, which PUC approved in 2019,

included taller poles made of steel and larger electricity conductors. In its order approving the

project, PUC found that the Wimberley area had experienced “significant growth over the last

several years,” that “PEC’s existing facilities are insufficient to meet the anticipated future

growth of the area,” and that the upgrade would “provide the necessary infrastructure capacity to

support the growing loads in Wimberley, provide needed capacity for backup to feeders at

adjacent substations,” and decrease the risk of long-term power outages. PUC also found that

the “visual feature” of the upgraded line “will not be a feature that is inconsistent with existing

features in the area” because “the project is primarily being built within the exact same corridor

as the existing 69-kV transmission line that is being built and upgraded,” and “[f]rom an

aesthetics perspective, the project will not present a view dissimilar to other linear rights-of-way

throughout the area following completion of construction and restoration activities.”

In late 2019, PEC began installing new steel poles on the Landowners’ properties

near the location of the original wooden poles. The number of poles did not change; both the

original and upgraded lines had four poles spread across the three subject properties. However,

the new poles were taller; the old poles were approximately 48 feet tall while the new poles were

between 67 and 72 feet tall. Shortly after constructing the poles, PEC hung new wire on the

poles and energized the line, increasing the voltage from 69 to 138 kilovolts.

In September 2019, at around the same time that PEC had begun installing the

new poles, the Landowners filed suit against PEC, asserting claims for breach of contract,

trespass, and “impermissible additional servitude.” Specifically, the Landowners alleged that the

3 Winn Easement did not convey to PEC the right to upgrade the line, that PEC’s access to their

properties as part of its upgrade project constituted a trespass, that “[t]he voluntary and

intentional actions of PEC constitute an impermissible additional servitude across the Plaintiffs’

properties,” and that PEC “has acted beyond the scope of the Winn Easement by accessing

Plaintiffs’ properties as part of the ‘upgrade’ project,” thereby breaching the easement.

In their petition, the Landowners sought temporary and permanent injunctive

relief, and in November 2019, the trial court held a hearing on their request for a temporary

injunction. At the conclusion of the hearing, the trial court took the matter under advisement and

suggested that the parties proceed to mediation, which they did. In January 2021, after mediation

had failed, the trial court granted the Landowners a temporary injunction, prohibiting PEC from:

(1) continuing work on the capacity-upgrade project on the Landowners’ properties,

(2) operating the transmission line at its upgraded capacity, and (3) accessing the Landowners’

properties for maintenance or operations in connection with the capacity-upgrade project. 1 PEC

filed an appeal of the temporary injunction and a motion for emergency relief, seeking the

issuance of a supersedeas bond. This Court remanded the case to the trial court for the entry of

an order requiring PEC to post a supersedeas bond and stayed the temporary injunction. See

Pedernales Elec. Coop., Inc. v. White, No. 03-21-00034-CV, 2021 WL 401982, at *3 (Tex.

App.—Austin Feb. 4, 2021) (per curiam) (order and mem. op.).

The case continued in the court below. The parties filed cross-motions for

summary judgment on liability, advancing conflicting interpretations of the easement. The

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Marcus Cable Associates, L.P. v. Krohn
90 S.W.3d 697 (Texas Supreme Court, 2002)
Centerpoint Energy Houston Electric LLC v. Bluebonnet Drive, Ltd.
264 S.W.3d 381 (Court of Appeals of Texas, 2008)
Coleman v. Forister
514 S.W.2d 899 (Texas Supreme Court, 1974)
Johnson v. Southwestern Public Service Co.
688 S.W.2d 653 (Court of Appeals of Texas, 1985)
Central Power and Light Company v. Holloway
431 S.W.2d 436 (Court of Appeals of Texas, 1968)
Guynes v. Galveston County
861 S.W.2d 861 (Texas Supreme Court, 1993)
Houston Pipe Line Company v. Dwyer
374 S.W.2d 662 (Texas Supreme Court, 1964)
DeWitt County Electric Cooperative, Inc. v. Parks
1 S.W.3d 96 (Texas Supreme Court, 1999)
Knox v. Pioneer Natural Gas Company
321 S.W.2d 596 (Court of Appeals of Texas, 1959)
Lower Colorado River Authority v. Ashby
530 S.W.2d 628 (Court of Appeals of Texas, 1975)
Pine v. Gibraltar Savings Association
519 S.W.2d 238 (Court of Appeals of Texas, 1974)
Hancox v. Peek
355 S.W.2d 568 (Court of Appeals of Texas, 1962)
Severance v. Patterson
370 S.W.3d 705 (Texas Supreme Court, 2012)
Southwestern Bell Telephone, L.P. v. Emmett
459 S.W.3d 578 (Texas Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Pedernales Electric Cooperative, Inc.// Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon v. Samuel S. White, Janette Barlow, Gregory Colon and Stephanie Colon//Cross-Appellee, Pedernales Electric Cooperative, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/pedernales-electric-cooperative-inc-samuel-s-white-janette-barlow-texapp-2024.