Pecker Iron Works, Inc. v. Sturdy Concrete Co.

96 Misc. 2d 998, 410 N.Y.S.2d 251, 26 U.C.C. Rep. Serv. (West) 1066, 1978 N.Y. Misc. LEXIS 2718
CourtCivil Court of the City of New York
DecidedNovember 2, 1978
StatusPublished
Cited by13 cases

This text of 96 Misc. 2d 998 (Pecker Iron Works, Inc. v. Sturdy Concrete Co.) is published on Counsel Stack Legal Research, covering Civil Court of the City of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pecker Iron Works, Inc. v. Sturdy Concrete Co., 96 Misc. 2d 998, 410 N.Y.S.2d 251, 26 U.C.C. Rep. Serv. (West) 1066, 1978 N.Y. Misc. LEXIS 2718 (N.Y. Super. Ct. 1978).

Opinion

OPINION OF THE COURT

Herbert A. Posner, J.

This controversy between a subcontractor (plaintiff) and a general contractor (defendant) arose indirectly as a result of the devastating cutbacks in general construction by the City of New York in the financial crisis of 1975.

Sturdy is a general contractor that specialized in doing construction work for the New York City Transit Authority and other city agencies. In August of 1974 Sturdy received oral notice that it was going to be awarded an alteration and installation of facilities contract for a paint shop at the Coney Island yard of the Transit Authority. In anticipation of the written notice (which came on September 17, 1974 with a "kicker” at the end — "subject to the approval of the Mayor of the City of New York”), Sturdy entered into an oral agreement with Pecker on August 5, 1974 "to furnish and erect the structural steel * * * etc.” for the job. Both parties agreed that since a price rise in steel was anticipated, they would beat the inflationary "clock” by ordering the steel in advance of the final contract. Based upon trade practice and past dealings with each other and the city, this seemed like a prudent business risk. However, who shall pay for the steel if the contract is never finally awarded? The Transit Authority, while approving of the structural steel order (and agreeing to inspect the steel at the plant of the Bethlehem Steel Company), nevertheless, in a letter dated August 14, 1974 disclaimed any responsibility for the cost of the steel should the final contract not be awarded. The steel was manufactured, delivered to Pecker’s facilities and paid for by Pecker. Almost one year later, July 31, 1975, the Transit Authority notified Sturdy that the award was rescinded. The plaintiff invited the defendant to take possession of the steel at its cost. Defendant, however, declined the "invitation”. Whereupon, plaintiff, to mitigate its damages sold the steel at the best price it could obtain. The net loss to Pecker for the entire transaction came (in the court’s opinion) to $4,028. Thus we have the background to this lawsuit.

Plaintiff based its claim to reimbursement upon an oral [1000]*1000agreement at the August 5, 1974 meeting with Sturdy that Sturdy would pay for all steel as billed by Bethlehem in the event a contract was not awarded. Defendant denies there was such an agreement and contends that plaintiff assumed the risk in order to get the job. To bolster its case plaintiff offered for evidence a letter sent to Sturdy on the same day that the oral agreement was made. The first part of the letter confirms the oral agreement to do the job and there is no dispute as to the language or the fact that the letter was received by defendant. The last paragraph contains the nub of the entire case, both factually and legally. The paragraph reads as follows: "In the event you are not awarded a contract on this project, then Sturdy Concrete Corp., is to pay for all steel as billed to us by Bethlehem Steel Co., plus handling and trucking.” Defendant contends that the letter is inadmissable under the Statute of Frauds, (Uniform Commercial Code, § 2-201, subd [1]); and, therefore, the alleged oral agreement for the sale of the steel is unenforceable. Subdivision (1) of section 2-201 reads as follows: "Except as otherwise provided in this section a contract for the sale of goods for the price of $500 or more is not enforceable by way of action or defense unless there is some writing sufficient to indicate that a contract for sale has been made between the parties and signed by the party against whom enforcement is sought or by his authorized agent or broker. A writing is not insufficient because it omits or incorrectly states a term agreed upon but the contract is not enforceable under this paragraph beyond the quantity of goods shown in such writing.”

Defendant also raised a self-contradictory argument that the oral agreement between the parties was not for the sale of goods but a service contract for the erection of a steel structure. In a case (almost) on "all fours”, the Appellate Division, Third Department, held that "[rjespondent was not contracting simply for the steel beams, but in essence for their erection and installation with the transfer of title to the steel a mere incident of the over-all transaction, a mere accessory to the work and labor to be performed.” (Schenectady Steel Co. v Trimpoli Gen. Constr. Co., 43 AD2d 234, 237.) However, this case is markedly different from Schenectady Steel, in that here the plaintiff is not suing on the entire agreement (which was never performed); but, only on the provision of their alleged agreement governing the financial responsibility for the steel purchased in advance.

[1001]*1001The court finds that this part of the agreement, standing alone, constitutes a contract for the sale of goods.

Plaintiff, however, does not rely on the service contract theory (which is actually in its favor); but, argues that it is entitled to the merchant exception to section 2-201 of the Uniform Commercial Code. Subdivision (2) of section 2-201 states: "Between mrechants if within a reasonable time a writing in confirmation of the contract and sufficient against the sender is received and the party receiving it has reason to know its contents, it satisfies the requirements of subsection (1) against such party unless written notice of objection to its contents is given within ten days after it is received.”

Defendant admits that it did receive the August 5 letter and that it did not give written notice of its objection. Defendant contends, however, that (1) it is not a merchant (though it concedes plaintiff is) under subdivision (2) of section 2-201 of the Uniform Commercial Code; and, (2) that its general manager called plaintiff on the phone to object to the paragraph containing the alleged agreement regarding the purchase of the steel.

THE LEGAL ISSUE — IS STURDY A "MERCHANT”?

Subdivision (1) of section 2-104 of the Uniform Commercial Code defines "merchant” as follows: " 'Merchant’ means a person who deals in goods of the kind or otherwise by his occupation holds himself out as having knowledge or skill peculiar to the practices or goods involved in the transaction or to whom such knowledge or skill may be attributed by his employment of an agent or broker or other intermediary who by his occupation holds himself out as having such knowledge or skill.” " 'Between merchants’ means in any transaction with respect to which both parties are chargeable with knowledge or skill of merchants.” (Uniform Commercial Code, § 2-104, subd [3].) Defendant would have us apply the narrow, ancient concept of a merchant (originating in the "law merchant”) as one whose "occupation is buying and selling” (Lish v Compton, 547 P2d 223, 226 [Utah]). Plaintiff, naturally, opts for a liberal interpretation, and cites: (1) that portion of the statutory definition of "merchant” which refers to "knowledge or skill”, and (2) that portion of the cross-examination of defendant’s general manager in which he conceded that Sturdy was familiar with the steel business and with the work of steel subcontractors.

[1002]*1002Statutory definitions are supposed to give the reader a sense of confidence by supplying apparently precise meaning. However, nowhere are the difficulties of definition more apparent than in subdivisions (1) and (3) of section 2-104 of the Uniform Commercial Code. The language in these definitions of a "merchant” and "between merchants” has been variously described as ambiguous,1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R.F. Cunningham & Co. v. Driscoll
7 Misc. 3d 234 (City of New York Municipal Court, 2005)
Fallsview Glatt Kosher Caterers, Inc. v. Rosenfeld
7 Misc. 3d 557 (Civil Court of the City of New York, 2005)
American Plastic Equipment, Inc. v. Cbs Inc.
886 F.2d 521 (Second Circuit, 1989)
Eastern Star, Inc. v. Union Building Materials Corp.
712 P.2d 1148 (Hawaii Intermediate Court of Appeals, 1985)
Spinnerin Yarn Co., Inc. v. Apparel Retail Corp.
614 F. Supp. 1174 (S.D. New York, 1985)
Apex Oil Company v. Vanguard Oil & Service Co. Inc.
760 F.2d 417 (Second Circuit, 1985)
E. Y. Gilkey & Sons, Inc. v. A-E Architectural Materials, Inc.
86 A.D.2d 970 (Appellate Division of the Supreme Court of New York, 1982)
Sea Harvest, Inc. v. Rig & Crane Equip. Corp.
436 A.2d 553 (New Jersey Superior Court App Division, 1981)
Boese-Hilburn Co. v. Dean MacHinery Co.
616 S.W.2d 520 (Missouri Court of Appeals, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
96 Misc. 2d 998, 410 N.Y.S.2d 251, 26 U.C.C. Rep. Serv. (West) 1066, 1978 N.Y. Misc. LEXIS 2718, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pecker-iron-works-inc-v-sturdy-concrete-co-nycivct-1978.