Pease v. City of Payette

146 P. 000, 26 Idaho 793, 1915 Ida. LEXIS 15
CourtIdaho Supreme Court
DecidedMarch 8, 1915
StatusPublished

This text of 146 P. 000 (Pease v. City of Payette) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pease v. City of Payette, 146 P. 000, 26 Idaho 793, 1915 Ida. LEXIS 15 (Idaho 1915).

Opinion

SULLIVAN, C. J.-

This action was brought against the City of Payette upon an agreed statement of facts, to test the validity of a certain contract entered into between the city and Lathrop & MeComsey, copartners, for the grading and constructing of curbs and sidewalks in Local Sidewalk, Curbing & Improvement 'District No. 1, of said city, and to test the validity of the bonds to be issued by the City of Payette for the purpose of paying for the work done under such contract.

The City of Payette has created within its boundaries a local improvement district known as Local Sidewalk & Curbing Improvement District No. 1 of said city, and has made an assessment against the property therein,'apportioning thereto the expense of the construction work contemplated. Said city on or about January 5, 1914, by resolution of its council, required notice to be given to contractors for bids upon the contemplated construction of the work in such district, and in pursuance thereof such notices were given.

The bids received thereunder were not opened oh the day set therefor by reason of the fact that W. A. Coughanour had in the meantime obtained a temporary injunction against said City of Payette, restraining the opening of said bids. Upon the dissolution of said injunction a new notice was given, stating that bids would be received up to noon of April 10, 1914, in response to which four bids were submitted. The bids were not opened upon the day set therefor by reason of the fact that said Coughanour took an appeal from the order dissolving the injunction, which was by the supreme court of this state [797]*797affirmed on or about July 10, 1914 (Coughanour v. City of Payette, 26 Ida. 280, 142 Pac. 1076), and immediately thereafter the last bids received were opened and the contract for doing the work let to said Lathrop & McComsey. The bids for the construction of the work were made upon certain plans and specifications attached to the agreed statement of the case, which specifications contained among other subdivisions Nos. 8, 17, 26, 27 and 32.

The provisions of these subdivisions and the failure to comply with the provisions of subd. 26 plaintiff claims invalidated the contract and the bonds to be issued in payment of the work to be done thereunder. The provisions of said subd. 26 have not been complied with, in that the said Lathrop & McComsey gave a private bond and not a surety company bond as required by said subdivision, and gave such private bond for sixty per cent of .the estimated cost of the work under the contract as let. Said private bond was approved and accepted by the council of the City of Payette. Upon the approval of said contract, said Lathrop & McComsey immediately proceeded to commence work under said contract and have performed about $7,000 worth of labor and will, unless restrained, complete such contract, and the City of Payette will, unless restrained, issue bonds of the aforementioned improvement district in payment of said contract, and will collect assessments from plaintiff and others similarly situated.

This matter was heard upon the agreed statement of facts by the seventh judicial district court in and for Canyon county, and judgment was entered in favor of the city, from which judgment this appeal is taken.

The questions presented on this appeal concern the proper construction of said subdivisions above mentioned of the specifications under .which the contract was let, and whether the requirements thereof tend to increase the cost of the work and whether they would prevent contractors from bidding for said work.

Respondents in their brief divided their argument into two subdivisions, under the following heads:

1. Are subdivisions 8, 17, 26, 27 and 32 of the purported plans and specifications such as to render the contract invalid [798]*798if it be admitted that said subdivisions are a part of said contract ?

2. Subdivisions 8 and 27 are no part of the plans and specifications of the contract.

Said subdivisions are as follows:

Subd. 8. Defects or Damages. “All settlements, defects or damages in any portion of the works, whether caused by the contractor, his agents or the public at large, or resulting from strikes, fires or any acts of nature shall be repaired and made at the contractor’s expense. All damages to fences, trees, sidewalks, waterpipes, sewers or other public or private property along or near the line of the work, or in the vicinity thereof, must, wherever the engineer shall direct, be made good to the satisfaction of the owners of the same, at the entire expense of the contractor. No private property outside of the line of the right of way shall be entered by the contractor without his first obtaining the consent of the owner. ’ ’ Subd. 17. Inspectors. “The city or the engineer may appoint inspectors and any such inspector shall always have the right to stop the work, if in his opinion, the contractor is not complying with these specifications, plans, instructions and orders; and if at any time the inspector shall stop the work, the contractor shall not proceed again with said work until the engineer shall have examined and passed upon the question in dispute and the engineer’s decision shall be final. Any work done after the inspector has ordered it stopped, as well as all work found at variance with these specifications,- shall be at once removed by the contractor. ’ ’

Subd. 26. Bond for Completion of Work. “The successful bidder shall furnish a Surety Co. Bond satisfactory to the City Council within thirty (30) days after the acceptance of the proposal by the City, for the faithful performance and successful completion of the work, and said bond to amount to 4.0 per cent of the amount of the contract.”

Subd. 27. Guarantee Bond. “ On or before the completion of the work and before final payment is made, the contractor shall furnish a good and sufficient Surety Co. bond for $10,000.00, same to run for one year from final completion of [799]*799works, guaranteeing that the works shall be free from all defects, either in construction or material, or both, and guaranteeing that the repairing of any such defects appearing in the work within one year from the completion of contract shall be paid for by the contractor, said repairs to be made under the direction of the engineer.”

Subd. 32. Engineering Expenses, etc. “It is further understood and agreed that the contractor, in addition to furnishing material, labor and doing the work as hereinbefore mentioned at the unit prices herein named, shall pay to the City of Payette for the purpose of applying on the overhead expenses such as engineering, inspection, etc., the sum of One Thousand and no one-hundredths (1,000.00) Dollars, as follows, to wit: At the time of payment of each monthly estimate, the same percentage of $1,000.00 as shown by the estimate for that month of the percentage of the work completed in said month. ’

Counsel for appellant contends that the requirements of said subdivisions 8, 17, 27 and 32 tend to increase the cost of the work and prevent contractors from bidding thereon; while counsel for respondent contends that said subdivisions of the specifications are no part of the contract, and even if they were considered as a part of the contract, they would not make the contract invalid or void.

There is nothing in the provisions of subd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coughanour v. City of Payette
142 P. 1076 (Idaho Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
146 P. 000, 26 Idaho 793, 1915 Ida. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pease-v-city-of-payette-idaho-1915.