Payette-Boise Water Users' Ass'n v. Bond

269 F. 159, 1920 U.S. Dist. LEXIS 816
CourtDistrict Court, D. Idaho
DecidedSeptember 18, 1920
DocketNo. 640
StatusPublished
Cited by1 cases

This text of 269 F. 159 (Payette-Boise Water Users' Ass'n v. Bond) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Payette-Boise Water Users' Ass'n v. Bond, 269 F. 159, 1920 U.S. Dist. LEXIS 816 (D. Idaho 1920).

Opinion

DIETRICH, District Judge.

In the decision filed on July 21, 1919 (263 Fed. 734), certain conclusions were stated, but entry of decree in accordance therewith was deferred until the September term, in the thought that possibly.the Reclamation Service might see fit in the meantime to obviate some of the objections held to be valid, and that progress could thu$ be made toward a solution of the controversy, without substantial delay or expense.

It will be remembered that the principal question in issue was the propriety of the demand of $80 per acre made against the settlers on certain of the project lands as a construction charge, and inasmuch as the Secretary of the Interior, the officer vested with final authority to speak for and bind the government, has failed to make findings, and, as a witness, was unable or unwilling explicitly to disclose the factors which he had used in his computation, the basis of the charge was in some respects left to conjecture.. By all considerations of common fairness, it was thought the settlers were so clearly entitled to be advised from an authorized source, and. in sufficient detail to enable them intelligently and fully to consider the correctness of the charge, that the absence of findings was assumed to have been the result of an oversight, rather than of design, and it was believed that, attention having been called to it, an appropriate record would be promptly supplied.

However that may be, of date October 24, 1919, the director and chief engineer of the service signed, and the Secretary approved, an instrument entitled “Statement of Cost and Conditional Dedication of Irrigation Works, Boise Irrigation Project, Idaho.” And upon October 31st a certified copy thereof was, by leave of court, filed as an exhibit in the cause, and served upon counsel for the plaintiffs. (For convenience the instrument will be referred to as the statement.) Subsequently additional pleadings Were filed, and certain settlers with interests in harmony with- those of the plaintiff were permitted to intervene ; and, further proofs having been taken, the cause is again submitted.

No direct issue was made in the original pleadings touching the interest which the settlers were to have in the system. In the statement, for the first time, the Secretary disclosed his position and informed them that upon the payment of the announced acreage charge of $80 for lands outside of, and $70 for lands within, an irrigation district, they would be recognized as being the owners of a one-half interest in the Arrowrock reservoir, 98 per cent, of the Deer Elat reservoir, and 99 per cent, of the diversion works and main canal, with a reservation, also, of the power plant at the diversion dam. In its supple[161]*161mental complaint the plaintiff asserts the need for the entire capacity of the system, and challenges the Secretary’s right to withhold any part of it, and thus we have substantially a new issue. For convenience we will first consider the propriety of the acreage charge, upon the assumption that the settlers are to have only such portions of the system as are so dedicated to their use.

In view of the conclusion heretofore reached, that the settlers must pay the actual cost of what they get, two prime factors enter into the computation of the proper acreage charge: (1) The cost of works of which the settlers are to be the beneficiaries; and (2) the acreage to be served thereby.

Cost.

First, as to the cost of the project. By the statement it is shown that the net cost of the portions of the system (other than the Arrow-rock storage) dedicated to the “project lands” (defined to be lands “under the constructed unit of the project and having no water right from private canals”) is $6,788,233.18, and of one-half of Arrowrock, so dedicated, $2,300,591.91, or a total of $9,088,825.09. It is stated that this amount includes nothing on account of surveys and investigation for other projects, nothing for drainage expenditures, except for such drainage as serves the project lands, nothing for the Notus extension, and that it is net, after making deductions for the reserved features, namely, $195,305.27 for power plant, $20,000 for 2 per cent, of Deer Flat storage, and $20,000 for 1 per. cent, of main canal, which delivers the water from the river into the Deer Flat reservoir; the explanation being that this canal cost $2,000,000 and Deer Flat $1,000,000.

Plaintiff, stating the account by a different method, reaches a different conclusion; but upon analysis it is found that the difference in result is due to a comparatively few controverted factors, and in the interest of clearness and brevity these will be referred to, without any attempt to set forth in detail the account as stated by either side.

Notus Extension.

One disturbing factor is the Notus extension; it having been excluded by the Secretary and taken into account by the plaintiff. It is not completed, and of course we cannot anticipate at this time precisely what the actual cost will be, and the acreage charge having been fixed by contract, the ultimate result may be a small profit or a small loss; neither is likely to be great. For such interests in the main canal and Deer Flat reservoir as are set apart for it, it is charged. True, no credit is given for the water developed by the drainage systems, which is its chief water resource, but only in part does such water come from project drainage systems, and besides, taking the equitable view, the plaintiff’s shareholders and other settlers on the south side are charged nothing for the mere right to appropriate water. Accordingly it is thought that there was no impropriety in excluding from consideration both the cost of this extension and the acreage to be irrigated therefrom. Were the profit or loss likely to be very considerable, a different view might very well be taken.

[162]*162Power Plant.

So with the power plant at the diversion dam. The installation was primarily for construction purposes, and it now has no utility, so far as concerns the maintenance and operation of the constructed units. If retained, it will be of value only for such revenues as may be realized from its rental or from the commercial sale of electric current. Credit is given for its cost, and apparently some allowance also for the privilege of using the waterfall; the evidence is meager upon the subject, and insufficient it is thought to warrant relief-.

Operation and Maintenance Chárge.

Prior to July 2, 1917, the date of the “public notice,” all expenses for operation and maintenance were charged to construction, and accordingly receipts arising from water rentals or operation charges were applied in reduction of construction cost. An item of $208,827.54, since collected on account of operation and maintenance, appears to be now carried as a reserve for the payment of expenses of operation and maintenance, rather than cost of construction. As I understand, it is not contended by the plaintiff that the settlers will fail to receive the benefit of the item, and it is only a question whether it shall be applied to the reduction of construction cost or in the payment of current and future operation and maintenance expenses, and hence it is a matter of little moment one way or the other. The disposition of it made by the Secretary is not thought to have been unwarranted.

General Expense.

[1]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michaelson v. Miller
26 P.2d 378 (Idaho Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
269 F. 159, 1920 U.S. Dist. LEXIS 816, Counsel Stack Legal Research, https://law.counselstack.com/opinion/payette-boise-water-users-assn-v-bond-idd-1920.