Paving Equipment of Carolina, Inc. v. Lake Providence Properties, Inc. (In re Lake Providence Properties, Inc.)

168 B.R. 864, 1993 Bankr. LEXIS 2206
CourtDistrict Court, W.D. North Carolina
DecidedSeptember 28, 1993
DocketBankruptcy No. 93-30064; Adv. No. 93-3255
StatusPublished

This text of 168 B.R. 864 (Paving Equipment of Carolina, Inc. v. Lake Providence Properties, Inc. (In re Lake Providence Properties, Inc.)) is published on Counsel Stack Legal Research, covering District Court, W.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paving Equipment of Carolina, Inc. v. Lake Providence Properties, Inc. (In re Lake Providence Properties, Inc.), 168 B.R. 864, 1993 Bankr. LEXIS 2206 (W.D.N.C. 1993).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

GEORGE R. HODGES, Bankruptcy Judge.

THIS MATTER came before the Court for trial on July 30, 1993. William G. Robinson appeared on behalf of the Plaintiff, while J. Craig Whitley represented the Defendant Trustee and Robert Lindsey, the Debtor. Although, procedurally the action covers a number of legal theories, in essence this action involves a determination of a claim filed against the Estate, by the Plaintiff Paving Equipment of the Carolinas, Inc., d/b/a Mecklenburg Paving, Inc. (“Mecklenburg Paving”). Mecklenburg Paving originally filed a secured claim against the Chapter 11 Debtor for $1,030,577.43. Objections to that claim have been filed by the Debtor, Lake Providence Properties, Inc. (“LPP” or “Debt- or”), and the Trustee James E. Wall, Sr. (“Trustee”). The Defendants contend that Mecklenburg Paving breached its prepetition contract with the Debtor and is not entitled to recovery and additionally challenge the amounts asserted in that claim. Additionally, the Trustee has argued that any claim of the Plaintiff is in the nature of equity, not debt and is subordinate to other claims in the Bankruptcy case. Because the determination of this claim could significantly affect the Bankruptcy reorganization, this matter was tried on an expedited basis with the consent of the parties.

Technically, this action was commenced by Plaintiff filing a lien perfection action in State Court pursuant to a consensual grant of relief from stay so that it might comply with technical requirements for perfecting a state law statutory lien. That action was then removed to this Court to be tried with a claim objection to be filed by the Debtor. In the interim, the Court appointed Wall as Trustee to operate the Debtor’s business. Wall was added as a defendant to this action by consent.

Defendant LPP then filed its Objection to the proof of claim and a Counterclaim on June 24, 1993. Mecklenburg Paving’s Response to the Counterclaim was filed on July 6, 1993. The Trustee filed an Answer and his Counterclaims on July 6, 1993, and LPP supplemented its earlier answer and filed an Answer dated July 8, 1993.

At the conclusion of the trial evidence, the Defendants were granted leave to verbally amend their pleadings to raise N.C.G.S. 87-1 (Mecklenburg Paving’s lack of a general contractor’s license at all times pertinent to this case) as an additional claim objection, and the Trustee’s position that Plaintiffs claims are equity, and not debt. Additionally, Plaintiff was granted leave to amend its proof of claim from a secured debt to claim an equity interest in the Debtor instead. All of the aforesaid allowed amendments are hereby deemed to have been made, and it is not necessary for any party to file any further written documents with the Court to effectuate said amendments.

FINDINGS OF FACT

1. LPP is a North Carolina Corporation whose business is the development and sale of residential real estate in Mecklenburg and Union Counties, North Carolina. The Debt- or owns and at the times in controversy was [866]*866developing three subdivisions'known as Lake Providence North, Providence Hills, and Valley Ranch. The Debtor’s President and sole shareholder is William H. Nolan, III.

2. Mecklenburg Paving is a paving contractor and a North Carolina Corporation that also does business in Mecklenburg and Union Counties, North Carolina. Robert Yon is the President and owner of the Plaintiff.

3. In the fall of 1991, LPP was undertaking development of its Providence Hills subdivision, and building a dam and 60-acre lake at its Lake Providence North subdivision. Although little more than the rough grading had been done at Providence Hills and only a minor portion of the 700' dam at the Lake had been built, LPP was running out of money. Nolan therefore approached Meck-lenburg Paving, a paving contractor who had worked for the Debtor in the past, about completing construction of the Providence Hills infrastructure.

4. The Debtor proposed that it would provide the land and sell the developed lots in Providence Hills, if Mecklenburg Paving would construct and pay the costs of developing the subdivision. In return, Mecklenburg Paving would receive part of the sales proceeds as lots were completed and sold. The Debtor’s obligations to Mecklenburg Paving were to be secured by a Deed of Trust on Providence Hills.

5. These discussions led to a letter of intent between the parties entitled Memorandum of Understanding, dated October 25, 1991, and anticipating a contract between the parties for the completion of this work.

6. Although the Memorandum was not itself a binding contract, the parties were familiar with one another and Mecklenburg Paving began work on Providence Hills on a handshake basis. Although not contemplated by the Memorandum, the work undertaken also included five construction projects unrelated to Providence Hills and the dam in the Debtor’s other subdivisions, including road grading in Lake Providence North and Valley Ranch and the construction of a second small dam in Valley Ranch (collectively referred to as the “Reed Fallon projects”).

7. Under the parties working arrangement, Mecklenburg Paving oversaw and coordinated the building of these improvements, although Nolan was on the site regularly. Plaintiff planned and oversaw the work, bought materials, and hired subcontractors and engineers for portions of the project. On other parts of the projects, such as the paving, it provided the work itself. Plaintiffs employees regularly oversaw and coordinated construction work done by others.

8. Under the arrangement, in doing the construction Mecklenburg Paving employed both its machinery as well as a dozer, loader, excavator, skidder and dump truck belonging to the Debtor.

9. At the time it was brought in, Meck-lenburg Paving was not aware and had not told by the Debtor that, the Debtor had not obtained subdivision approval for part of Providence Hills.

10. Shortly after the Memorandum was signed, Mecklenburg Paving also agreed with the Plaintiff to complete construction of a 700' earthen dam at Lake Providence North. This agreement was reflected by an Explanation Concerning Memorandum of Understanding dated November 21, 1991 (“Explanation”) (P-2). Mecklenburg Paving’s responsibility for this work was contingent upon Debtor’s continued provision of equipment and capped at a cost of $65,000, -with any overruns to be borne by Lake Providence.

11. The dam work agreement was prompted by running dispute with the Lake Providence North Landowners. Nolan had over a period of several years sold lots in Lake Providence North to individuals upon the promise that the Debtor would build a 60-acre lake in the subdivision. Prior to contracting with Yon, Nolan had signed a Consent Judgment in favor of the lot owners in which he promised to have the dam and Lake completed by a specified date. By November of 1991, however, only a small part of the construction, some grading, had been completed, and the dam was largely unbuilt. Nolan was facing being jailed by the Superior Court for contempt.

[867]*86712. Nolan brought Yon into both projects because he lacked the financial ability to complete construction himself. Mecklenburg Paving offered a “no money down” way for LPP to develop these properties. Yon’s entry into the dam project also added credibility to Nolan’s assertions that the dam would be finished and kept him out of jail.

13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mill-Power Supply Co. v. CVM ASSOCIATES
355 S.E.2d 245 (Court of Appeals of North Carolina, 1987)
Roberts v. Heffner
277 S.E.2d 446 (Court of Appeals of North Carolina, 1981)
Barrett, Robert & Woods, Inc. v. Armi
296 S.E.2d 10 (Court of Appeals of North Carolina, 1982)
Phillips v. Parton
296 S.E.2d 317 (Court of Appeals of North Carolina, 1982)
In Re Woodward
300 S.W.2d 385 (Supreme Court of Missouri, 1957)
Phillips v. Parton
300 S.E.2d 387 (Supreme Court of North Carolina, 1983)
301 East Seventh Street Ltd. Partnership v. Gellman Corp.
124 B.R. 687 (W.D. North Carolina, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
168 B.R. 864, 1993 Bankr. LEXIS 2206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paving-equipment-of-carolina-inc-v-lake-providence-properties-inc-in-ncwd-1993.